RESPONSES FOR CATHODIC TELEMENTRY.docx

DOCX document 16 KB Posted

Attached to
Install Cathodic Telemetry Water Tanks Basewide Hurlburt Field Federal contract opportunity
Solicitation number
FA4417-11-R-0033
Issued by
Department of the Air Force Special Operations Command

About this file

Responses to Questions 1 - dated 29 Jul 2011. Also see posting for Amendment 1 and attachments.

View the file

Other files for this federal contract opportunity

Other files attached to Install Cathodic Telemetry Water Tanks Basewide Hurlburt Field, newest first.
File Type Posted
E4 - REVISED.pdf PDF
FA4417-11-R-0033 - 0001.doc DOC document
E9 - REVISED.pdf PDF
Site Visit Sign in Sheet and MFR FA4417-11-R-0033 Cathodic Telementry.pdf PDF
Attch 2 Drawings Cathodic.pdf PDF
Attch_5 _Financial_Institution_Ref_Sheet Cathodic.docx DOCX document
FA4417-11-R-0033 Solicitation Cathodic.pdf PDF
Attch 1 Specifications Cathodic.pdf PDF
Attch 3 Schedule of Wage Rates Cathodic.pdf PDF
Attch 4 Past Performance Questionnaire Cathodic.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RESPONSE TO QUESTIONS 1 - 29 Jul 11

FA4417-11-R 0033, INSTALL CATHODIC TELEMENTRY

QUESTION 1. There is no description how the installed equipment will be integrated into the existing communication system.

RESPONSE: The new equipment will not be integrated under this project.

A. Is any software required to be supplied and programmed under this contract?

RESPONSE: No software is required.

B. If so what format and/or platform will it operate?

RESPONSE: Not required.

C. Is there any warranty or service contract required?

RESPONSE: Normal warranty for workmanship and materials. No service contract required.

QUESTION 2. Since the existing cathodic protection systems are turned off until next April, who will energize and proof the existing systems to confirm they are operating properly prior to hooking up this remote monitoring equipment?

RESPONSE: The base personnel will need to sign off on the install. They will need to determine if the system is able to be turned on.

QUESTION 3. Several of the locations shown on the drawings were found to be incorrect. Will corrections be made prior to the bid being received?

RESPONSE: Sheet E-4 and E-9 were corrected. No other locations are known to be out of place. Please inform the engineer of any other issues. See Attachments to Amendment 1.

QUESTION 4. Water tower site 91134 is drawn incorrectly as a stanchion type when in reality it has an enclosed base with all the equipment located inside the base. It appears the base is supported by a concrete ring wall foundation. How is conduit supposed to be run into the enclosed space? Please confirm the depth of the ring wall. Also it appeared that a concrete floor may be poured in the near future, can this be confirmed?

RESPONSE: Ring wall depth is unknown. It is also unknown if/when a concrete floor will be poured. The conduit routing concern will be the final determination of CE and shops. Their input will be required.

QUESTION 5. Spec section 01580 requires a project sign. Will such a sign be required?

RESPONSE: Per Mr James Perkins, 1 SOCES, The requirement for the Project Sign for this acquisition is waived.

QUESTION 6. Will the bid date be extended to respond to the above?

RESPONSE: The bid date will be extended FROM 2 Aug 2011, 2:00 PM (CST) TO 5 Aug 2011, 2:00 PM (CST). See Amendment 1.