MAPC_Revised_RFI_5_May.xlsx

XLSX spreadsheet 16 KB Posted

Attached to
Multiple Award Paving Contract (MAPC) Federal contract opportunity
Solicitation number
FA4407-15-R-0002
Issued by
Department of the Air Force Air Mobility Command

About this file

This RFI was revised on 5 May 2015.

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Paving Contract (MAPC), newest first.
File Type Posted
Revised_RFI_27_April.xlsx XLSX spreadsheet
RFI_-_MAPC_2015.xls XLS spreadsheet
Preproposal_Conference_MAPC2015.pptx PPTX presentation
Pre-Proposal_Conf._Minutes.pdf PDF
MAPC_2015_Amendment_1.pdf PDF
Revised_SOW_23_April_15.pdf PDF
Sign_in_sheet.pdf PDF
MAPC_2015_RFP-Final.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

#QUESTIONRESPONSE
1Does the government intend for the contractor to remove and dispose of the asphalt millings or do you intend to have the contractor haul the millings to a stockpile on base?The CONTRACTOR is responsible to remove/dispose the asphalt millings off base.
2There are no stripes on the existing road, does the customer want striping on this road?Yes, per the SOW.
3On the revised SOW it states "Remove and replace 2 inches asphalt on McCullough Road from the two entrances on East Drive heading to Bldg. 3900 Park Lot." The map is showing 2" at the entrance and 4" on the road to the parking lot at Building 3900. Does the map need to be updated to show 2" (instead of 4") on the road to the parking lot?I revised the drawing to reflect Mill and overlay 2" throughout.
4When the revised SOW was issued the square foot measurements were not carried forward. Are those measurements correct for us to use to bid, as the area is not accessible?Use the SF per the SOW.
5
6
7
8
9
10
11
12
13
14

Sheet2

Sheet3

File details come from the government source that posted it. Updated .