Atch 2 Schedule of Submittals

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals Schedule SCHEDULE OF SUBMITTALS PROJECT # MXDP 10-A013 PROJECT TITLE Repair Roof Fuel Systems Maintenance, B53 SOLICITATION / CONTRACT NO.

(To be completed by Project Engineer)(To be completed by Contract Administrator)
NUMBER OF COPIES REQUIRED
LINE NUMBERITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALSOW ReferenceCERTIFICATION OF COMPLIANCEDESIGN DRAWINGSSPECIFICATIONSDESIGN CALCULATIONSSHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACTURER'S RECOMMENDATIONMANUFACTURER'S WARRANTYCATALOG DATAOPERATING INSTRUCTIONSSCHEDULES, LISTINGS, REPORTS, PLANSTECHNICAL DATA/ MSDSRESUMEREQUIRED SUBMISSION DATE

fergusog: Enter the due date from the Contractor (MM/DD/YY)

DATE RECEIVED IN CONTRACTING

fergusog: Enter the date received from the Contractor. (MM/DD/YY)

DATE TO CIVIL ENGINEERING

fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)

RETURN SUSPENSE DATE

fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

SUBMITTAL NUMBERS

fergusog: Enter the Submittal Number

DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL

fergusog: Enter Resubmittal Number

FINAL APPROVAL

fergusog: Enter the submittal final approval date

(MM/DD/YY)

REMARKS

fergusog: Enter any comments pertaining to the submittal fergusog: Enter the due date from the Contractor (MM/DD/YY) fergusog: Enter the date received from the Contractor. (MM/DD/YY) fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

fergusog: Enter the Submittal Number

APPR

fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number

DIS

fergusog: Enter date the Contractor was notified of submittal disapproval fergusog: Enter the submittal final approval date

Pre-Construction Submittals
1Progress Schedule2.2.11NLT 5 Days After NTP #1Use AF Form 3064
2Construction Site Plan2.5.a1NLT 14 Days After NTP #1
3Standing Seam Metal Roof Shop Drawings2.2.1111111NLT 14 Days After NTP #1
4Standing Seam Metal Roof Product Data2.5.b11111NLT 14 Days After NTP #1
5Gutters/Down Spouts2.5.b11111NLT 14 Days After NTP #1
6Roof Panels2.5.b11111NLT 14 Days After NTP #1
7Roof Flashing2.5.b11111NLT 14 Days After NTP #1
8Gable Anchor Clips2.5.b11111NLT 14 Days After NTP #1
9Seam Cap2.5.b11111NLT 14 Days After NTP #1
10Closures2.3.11 2.3.811111NLT 14 Days After NTP #1
11Fasteners2.5.b11111NLT 14 Days After NTP #1
12Caulking/Sealent with SDS2.5.b11111NLT 14 Days After NTP #1
13Manufacturer's Warranties2.5.f11NLT 14 Days After NTP #1
14Safety Plan2.5.a11NLT 14 Days After NTP #1
15Weather Tight Plan2.3.511NLT 14 Days After NTP #1
16Environmental Protection Plan2.5.a1NLT 14 Days After NTP #1
17Solid Waste Management Plan2.5.c1NLT 14 Days After NTP #1
18Key Personnel Resumes2.5.e11NLT 30 Days After NTP #1Superintendent, QC, and Alternates
19Work Clearance Request2.5.g1NLT 30 Days After NTP #1AF Form 103
Construction Submittals
20Progress Report4.61Bi-WeeklyUse AF Form 3065
Close-Out
21Draft DD 13545114 Days prior to Pre-Final Inspection
22As-Built Drawings7114 days before Final Inspection
23DD 135471At Final Inspection
24Construction Warranty Management Plan71Same Date as Project Acceptance
25Final Inspection Report615 days after Final Inspection
Schedule of Submittals, (SAF/AQCP)