FA3047-11-B-0004 Site Visit

49 KB Posted

Attached to
FA3047-11-B-0004-Design-Build, Repair Gas Mains (9000 & 10000 Areas)
Solicitation number
FA3047-11-B-0004-GasMains-9000-10000areas
Issued by

About this file

This attachment is the Site Visit Meeting Minutes.

Text of this file

FA3047-11-B-0004 - Design-Build, Repair Gas Mains (9000 & 10000 Areas)

Site Visit Meeting Highlights (4 May 2011) 0900 - 1000

1. CO confirms that there will be no other site visit allowed for this project.

2. CO emphasized that technical and contractual questions should be directed to Contracting. No questions should be sent directly to Civil Engineering and a reference should be provided for each question i.e. SOW page__, etc.

3. CO expounded on HUB ZONE rules, certification and direct rules concerning this project.

4. The following questions were raised by potential bidders during the meeting. These questions still need to be clarified by the government.

a. What is the material of the existing piping?

b. Are there going to be any steel tie ins?

c. How many areas will require boring?

d. Are there As-Builts (PDF) of the Utilities for this project?

e. Are Lackland AFB gas standards the same as those of CPS Energy?

(END)

Other files

Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .