Solicitation Amendment FA303023Q00020002 SF 30.pdf

PDF 567 KB Posted

Attached to
Goodfellow AFB - Replace Chiller Bldg 3311 Federal contract opportunity
Solicitation number
FA303023Q0002
Issued by
Department of the Air Force Air Education and Training Command

About this file

This solicitation amendment modifies the period of performance and statement of work for a federal contract to replace a chiller at Goodfellow Air Force Base in Texas. The scope of work includes removing an old chiller, pipes, fittings, and refrigerant, and installing a new chiller, base, pipes, fittings, and electrical. The period of performance is extended to 475 calendar days total to account for an estimated 55-week equipment lead time and 90 days for installation. Questions from interested vendors are due by February 15, 2023, with the agency aiming to post amendment responses within three days thereafter. Proposals for the firm-fixed-price contract are due February 24, 2023. The Department of the Air Force's Air Education and Training Command is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Goodfellow AFB - Replace Chiller Bldg 3311, newest first.
File Type Posted
Solicitation Amendment FA303023Q00020005 SF 30.pdf PDF
Solicitation Amendment - FA303023Q00020005.pdf PDF
Solicitation Amendment FA303023Q00020004 SF 30.pdf PDF
Attachment 1 - B3311_ASoW_Replace Chiller V07_NEW.pdf PDF
Site pic 3 B3311.jpg JPG image
Site Pic 4 B3311.jpg JPG image
Site Pic 2 B3311 (1).jpg JPG image
Site Pic - Existing Trane RTAC data tag.jpg JPG image
FA303023Q0002 - Questions - B3311 - 28 Feb 2023.docx DOCX document
REV.1_TE-1a_B3311 Chiller Replacement_Enclosurew detail_1MAR.pdf PDF
Site Pic 5 B3311.jpg JPG image
Site Pic 2 B3311 (2).jpg JPG image
Site Pic - Main distro Panel B3311.jpg JPG image
Attachment 1 - B3311_ASoW_Replace Chiller_1135105_V6.pdf PDF
Attachment 6 - Instructions to Offerors and Evaluation Criteria.pdf PDF
Solicitation Amendment FA303023Q00020003 SF 30.pdf PDF
Attachment 5 - HVAC Chiller System Justification and Approval 7 Aug 19.pdf PDF
Attachment 7 - Drawings(Mechanical Enclosure).pdf PDF
Attachment 1 - B3311 Chiller Replacement Statement of Work (SOW)_v05_Revised February 2023.pdf PDF
Attachment 5 - HVAC Chiller System JA - 7 Aug 19.pdf PDF
Attachment 3 - Nonappropriated Fund Standard Clauses 6 May 2022.pdf PDF
Attachment 2 - Contractors Guide.pdf PDF
Attachment 4 - BAL Template(Working Copy).docx DOCX document
Solicitation Amendment - FA303023Q00020001.pdf PDF
Attachment 1 - B3311 Chiller Replacement Statement of Work (SOW)_v04_Revised January 2023.pdf PDF
Solicitation Amendment FA303023Q00020001 SF 30.pdf PDF
Show all 26

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

Created On: 06 Feb 2023, 03:33 PM Central Standard Time

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

Supplies or Services & Prices or Costs

The following CLIN(s) / SLIN(s) / ELIN(s) were modified:

INFORMATION FROM TO

Description

REPLACE CHILLER UNIT BLDG 3311

Work will include the removing old chiller, pipe, fittings, electrical, and refrigerant and install the new chiller with new base, pipes, pipe fittings, electrical in accordance with the statement of work.

REPLACE CHILLER UNIT BLDG 3311

Work will include the removing old chiller, pipe, fittings, electrical, and refrigerant and install the new chiller with new base, pipes, pipe fittings, electrical in accordance with the statement of work.

The contractor will have a total of 475 Calendar Days including an estimated 55 weeks for Trane Lead Time and 90 calendar days for installation.

Deliveries or Performance

The delivery information for the following CLIN(s) / SLIN(s) / ELIN(s) were modified:

Ship To - F1Z312 - 17 CES CERF RA

INFORMATION FROM TO

Delivery 180 Calendar Days, From Date of Award to delivery 475 Calendar Days, From Date of Award to delivery

List of Attachments

The following attachments were added:

Attachment 1 - B3311 Chiller Replacement Statement of Work (SOW)_v05_Revised February 2023

The following attachments were deleted:

Attachment 1 - B3311 Chiller Replacement Statement of Work (SOW)_v04_Revised January2023

FA303023Q00020002

IDCode:
Page: 1
Pages: 2
AmendNo: 0002
EffDate: 24 Jan 2023
ReqNo:
ProjNo:
IssCode: FA3030
AdmCode:
IssuedBy: FA3030 17 CONS CC

210 SCHERZ BLVD

ADMINISTRATIVE ONLY NO REQUISITIONS

GOODFELLOW AFB, TX 76908-4705

UNITED STATES

Samuel Reynolds, Email: samuel.reynolds.5@us.af.mil Telephone: 477-3809

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA303023Q0002
SolDate: 24 Jan 2023
AwardChg: Off
AwardNo:
AwardDate:
Amended: 1
OffrExt: Off
OffrNoEx: 1
NoCopies: 1
ApprData: See Section G - Contract Administration Data
ChgeOrd: Off
ChgeOrder:
Modify: Off
SuppAgre: Off
SuppAuth:
ModOthr: Off
OthrSpec:
NoReq: Off
Require: Off
Copies:
Descript: The purpose of this amendment is to:

1.) Modify the Period of Performance based on internal research conducted in regards to (C) Trane Manufacture Lead Times.

2.) Update Version 5 of Attachment 1 - B3311 Chiller Replacement Statement of Work (SOW)

ContNameTitle:
CoNameTitle:
ContDate:
CODate: