Attach 10) 2nd Q and A.pdf

PDF 185 KB Posted

Attached to
Protective Coating IDIQ - Solicitation Federal contract opportunity
Solicitation number
FA303022R0010
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to Protective Coating IDIQ - Solicitation, newest first.
File Type Posted
Solicitation Amendment FA303022R00100004.pdf PDF
Solicitation Amendment FA303022R00100003.pdf PDF
Solicitation Amendment FA303022R00100002.pdf PDF
Attach 9) Q and A.pdf PDF
Solicitation Amendment - FA303022R00100001.pdf PDF
Attach 2) SEED Task Order Paint.pdf PDF
Attach 3) AF Form 66.pdf PDF
Attach 5) Seed Proj Drawings Vol 1.pdf PDF
Attach 7) Wage Determination TX20220282.pdf PDF
Solicitation - FA303022R0010.pdf PDF
Attach 6) Seed Proj Drawings Vol 2.pdf PDF
Attach 4) Drawing - Base.pdf PDF
Attach 1) Protective Coating Specifications.pdf PDF
Attach 8) BAL Template Jul 22.docx DOCX document
Show all 14

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers

Number Question Response

1 Will we need a dedicated QCM on site? No

Can Super and QCM be shared as a dual role?

Have no issue with this

Will we have to have a field office on

Post?

No, but may be permitted at the discretion of the Contracting Officer

& on space availability at the time of the TO execution

4 Will we have to have storage on Post?

No, but may be permitted at the discretion of the Contracting Officer

& on space availability at the time of the TO execution

5 Will we have to have temporary fencing?

No, but work areas should be clearly marked

Will we and our subs be held responsible to have a NIST-800-171 assessment and plan on file in SPAR?

No NIST assessment is required.

6.a

OR When will we and our subs be required to have a NIST-800-171 assessment on file?

No NIST assessment is required.

Will we have to have a Traffic Control

Plan in place? What Task Orders will need a TCP?

Only if streets need to be closed

Do we need a silica plan in place? What

Task Orders will need a silica or dust control plan?

As per Sec.02577 Para. 1.3.3.1

Silicon sand (pump jack sand) shall not be used

How much confined spaces will there be?

Will we need a person certified in confined spaces on payroll consistently? Or what

Task Order will we need a certified confined spaces person?

There will be very little if any confined space work. Certified personnel will only be required on

TO with confined space work

Will we need a lift plan? What Task Orders do we need a lift plan?

Must follow OSHA and all references listed in Sec. 01010 Para.

4.1 regulations

Per specs page 37 of 88, section 3.2.1: If it rains, do we have to wait 30 days to paint?

This is for newly installed Concrete, Stucco, & Masonry surfaces

11.a

If we did clean, wait 30 days, it might mean it gets dirty again- having to be cleaned again, thus waiting another 30 days.

This is for newly installed Concrete, Stucco, & Masonry surfaces