STATEMENT OF WORK

FOR

CLASSROOM MONITOR INSTALL

1. DESCRIPTION:

a. Scope: This statement of work is to remove old 55” Flat panel displays (FPD) and install new 65” FPD in 25 classrooms. Three new FPD are required in each classroom – two mounted in the front of the classroom and one in the rear of the room. FPD inputs will be extended to a HDMI distribution Amplifier located at the instructor desk in each classroom. Power is available at each install location, but will require an installed surge protector for each FPD location.

b. Location: Louis F. Garland Fire Training Academy (Bldg. 3454 and 3453) on Goodfellow AFB, TX.

2. SPECIFIC TASKS:

a. PRIOR TO STARTING: Contractor will contact the 312 TRS project POC 325-654- 1186 to finalize the work schedule, request and process base access letter.

b. Remove and dispose of 40 each old classroom 55” flat panel displays and mounts.

Customer will provide an onsite storage location and will dispose of the old monitors.

c. Install new 65” FPD. Three flat panel display will be installed in each of 25 classrooms. Two displays in the front of the classroom and one in the rear of the classroom. HDMI cables will be extended to a HDMI distribution amplifier located at the instructor desk. HDMI cables will be install in the wall of all gypsum covered walls (estimated 28 walls). HDMI cables will be installed in raceway on all block walls (estimated 30 walls). HDMI wall plates will be used in all gypsum walls, and raceway mounted boxes will be used in all block walls. A three-gang HDMI wall plate will be used at the instructor desk. Install a surge protector to each FDP.

d. Install customer provided sound bar audio attached to one of the front FPD to amplify audio output.

e. Customer provided equipment: 65” Samsung QB65R-N FDPs; sound bars; surge protectors; Instructor desks; diagram of each room orientation.

f. Installer provided equipment: FDP wall mounting bracket to hang Samsung QB65R 3840X 2160, HDMI distribution amplifiers; HDMI Cables; HDMI wall plates, low voltage boxes; raceway, wall anchor hardware; Velcro, cable management.

Additional Information: Classrooms will be available in groups of four at a time to demo and install FPDs. Classrooms to install: Building 3453 – Rooms 102, 103, 111A, 111B, 112A, 112B, 116A, 116B, 133, 134a, 134b, 135, 136a, 136b, 141, and 142. Building 3454 – Rooms 82, 84, 86, 88, 89, 90, 91, 92, and 93.

Wall construction make up is a mixture of drywall and concrete block.

Contractor is responsible to supply necessary mounting hardware for mounting to appropriate wall type.

Room layout example provided below