FA303020B0002 SOW_Specifications 10-28-19.docx

DOCX document 174 KB Posted

Attached to
Construct Splash Park at Goodfellow AFB Federal contract opportunity
Solicitation number
FA3030
Issued by
Department of the Air Force Air Education and Training Command

About this file

This federal contract opportunity document solicits sealed bids for the construction of a splash park at Goodfellow Air Force Base. Key details include that bids are due no later than 2:00 PM on April 20, 2020 and must be submitted in hard copy to the specified conference room. A base access list must be submitted three days prior for parties interested in attending the public bid opening. The delivery date will be in accordance with FAR 52.211-10. This requirement is being set aside for woman-owned small businesses between $250,000 and $500,000 in magnitude. The NAICS code is 238990 with a size standard of $16,500,000. Only offers from non-debarred or suspended firms will be considered. Verbal explanations given before award will not be binding and changes will be issued in writing via amendment, which offerors must acknowledge. The government reserves the right to cancel the solicitation prior to award if determined to be in its best interest.

View the file

Other files for this federal contract opportunity

Show all 17

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SPECIFICATIONS

FOR

CONSTRUCT SPLASH PARK

PROJECT # 1073123

OCTOBER 2019

PREPARED BY:

17TH CIVIL ENGINEER SQUADRON (AETC)

460 E. KEARNEY BOULEVARD

GOODFELLOW AFB, TX 76908-4104

PROJECT MANAGER: Adrian Reyes Cruz

TABLE OF CONTENTS

Construct Splash Park October 2019

Pages

DIVISION 01 - GENERAL REQUIREMENTS

01 01 00GENERAL REQUIREMENTS3
01 02 00UTILITIES 17
01 40 00ENVIRONMENTAL PROTECTION 20
01 54 00GREEN PURCHASING 36

DIVISION 02 - EXISTING CONDITIONS

Not Used

DIVISION 03 – CONCRETE

03 30 00 CAST IN PLACE CONCRETE 41

DIVISIONS 4 THRU 10

Not Used

DIVISION 11 – EQUIPMENT

11 68 00 WATER PLAY EQUIPMENT 48

DIVISIONS 12 THRU 25

Not Used

DIVISION 26 - ELECTRICAL

26 00 00 ELECTRICAL 59

DIVISIONS 27 THRU 31

Not Used

DIVISION 32 – EXTERIOR IMPROVEMENTS

32 52 00 ARTIFICIAL TURF 66

DIVISIONS 33 THRU 48

Not Used

--- End of Table of Contents ---

DIVISION 1 - GENERAL REQUIREMENTS

SECTION 010100 - GENERAL

1. SCOPE: The work covered by this project consists of the Contractor furnishing all layout, survey, plant, labor, supervision, quality control, materials, equipment, machines, tools, appliances, services, supplies, and incidentals and performing all operations in connection with the Construction of Splash Park at Goodfellow AFB, Texas, complete and in strict accordance with the plans and specifications. New Splash Park replaces a swimming pool demolished by others, previously located at the same area.

1.1 PROJECT LOCATION: The Work shall be installed at Facility 123 (Former China Beach Pool); Goodfellow AFB, TX, as described on this project specifications and drawings. The Contractor shall enter through the commercial vehicle entrance area on the South side of base off of South Chadbourne Street. Please see drawings for more details.

2. WORKING CONDITIONS:

2.1 The work shall be performed in three (3) Phases. The total project performance period for Basic CLIN’s without awarded CLIN options is 150 calendar days. See summary of project performance periods below and refer to CLIN schedule for additional information.

1. Phase 1: Work Plan.

1. Phase 2: Work Plan Implementation. Basic CLIN 0001, and if awarded Options CLIN 0002 and Option CLIN 0003.

CLIN 0002: Refer to drawings and CLIN schedules. Provide Mock Aircraft and painted runway to Splash Pad.

CLIN 0003: Refer to drawings and CLIN schedules. Repair and level existing concrete slab. Provide artificial turf over existing concrete slab.

1. Phase 3: Turnover.

2.1.1 PHASE 1 - WORK PLAN SUBMITTAL: The Contractor shall develop and submit in writing a detailed Work Plan to meet specifications summarized in this SOW. Proposed Work Plan shall include specifications and drawings for piping, pumping, recirculating system, electrical, concrete, equipment shed, control center, splash pad features, surfacing, and any other element of this job. The procedures shall provide for safe conduct of the work, protection of property that is to remain undisturbed, coordination with other work in progress, and utility line capping. The procedures shall include a detailed description of the methods and equipment to be used for each operation, and the sequence of operations. Construction of new Splash Park shall not commence until the proposed Work Plan has been reviewed and approved.

2.1.1.1 Pre-Construction Survey: Perform an inspection of conditions at the construction site, in the presence of the Government Construction Inspector, prior to accepting control of the area. Contractor must field-verify all information related to existing conditions including: utilities, dimensions, calculations and code requirements for all elements of work. Verify and record conditions by written description and photographs. Signature of both parties will indicate consensus of understanding.

2.1.1.2 The first Thirty (30) calendar days after the date of the NTP, shall be for the Contractor lead time. This time is allocated solely for the Contractor to perform such tasks as compiling submittals for approval and/or information, ordering materials to be available for the actual construction work for all phases, performing site surveys, materials surveys, ordering long lead-time items, and verifying dimensions. The Contractor shall have full access to the site but no actual work shall be permitted during this period, only site survey work.

2.1.2 PHASE 2 – WORK PLAN IMPLEMENTATION: Upon approval of the Work Plan, provide all interior and exterior architectural, civil, fire, mechanical, plumbing, and electrical work to construct the Splash Park as described in CLIN schedules, plans and specifications.

2.1.2.1 The Splash Park facility shall be constructed along with a recirculating type water system that will have a make-up water connection to the base potable water system. The supply water, when drained from the Splash Pad, shall be treated before returned back to the Splash Pad. Drainage system shall provide for emergency disposal of waste water into the existing sanitary sewer system and for diversion of precipitation collected during non-operational hours into the existing storm sewer system. All control and water management equipment shall be contained within a single equipment shed except those that for design needs to be buried.

2.1.3 PHASE 3 – TURNOVER: Contractor shall commission the Splash Park as required on specifications section 116800. The Contractor shall insure that work for this project is performed in accordance with the criteria herein and that all equipment and systems shall be fully operational at the completion of work for this project.

2.2 As shown on the plans, the area north of Splash Park site will be available for Contractor lay down area immediately upon signing the contract NTP. The lay down area shall provide for office space and material storage. New materials shall be secured and protected in this area. This fence shall be minimum 6’-0” high portable chain link with portable interlocking panels (no concrete footings) around limits of construction. The Contractor shall locate the project office and material storage in this lay-down area. Any existing site conditions altered by the presence of the fence shall be restored to their original condition and appearance. If the Contractor requires additional outside storage space, they shall contact the Contracting Officer with a written request to include a single line site plan diagram with specific dimensions. Note there is no existing on-base building storage space.

2.2.1 Temporary fencing used by the Contractor to delineate construction sites shall be securely anchored with tension wires and posts as required to prevent sagging and an unsightly appearance. Fencing shall be maintained by the Contractor in this manner throughout the life of the contract. Due to high winds in West Texas, Contractor shall take every precaution to preclude trash and materials from blowing off site.

2.2.2 All Contractor storage areas shall be maintained including yard/grass regularly cut/trimmed by the Contractor, as required on a daily basis. At all times, all Contractor trailers shall maintain a professional appearance at all times.

2.2.3 All construction debris, trash, dirt, etc. shall be immediately removed, at a minimum daily and as required, at the Contractor’s expense in accordance with all local, state and federal environmental laws and regulations.

2.2.4 At all times, the Contractor shall exercise care to reduce noise and ensure safe construction activities while minimizing disturbances to adjacent facilities. The Contractor shall conduct all work such that means of facility ingress and egress are maintained at all times for all surrounding buildings.

2.2.5 The Contractor shall be responsible for providing suitable, approved signs, barricades, roped barriers, etc., to warn occupants of hazardous areas at the job site for the entire duration of the contract at no additional cost to the Government. Under no circumstances shall the Contractor open cut or block Kearney Blvd.

2.3 If Options CLIN 0002 and CLIN 0003 are awarded, the contractor shall provide a Mock Aircraft, painted runway to Splash Pad, repair and level existing concrete slab, and provide artificial turf over existing concrete.

2.4 Once all work in Phase 2 has been completed the Contractor shall remove all trailers, site storage, temporary fencing, etc. and restore/return site to pre-construction conditions including but not limited to re-establishment of turf, operable landscape sprinklers, and ensuring positive site storm drainage.

2.5 A written notification regarding all water, gas, power or communication outages must be submitted by the Contractor (7) seven calendar days in advance to the Contracting Officer, unless otherwise noted herein. All water, power or communication outages must be scheduled for weekends only so as to not unnecessarily disturb adjacent training facilities.

2.6 Management Plan (GA): The Contractor shall have the responsibility to prevent freezing of utility lines and stoppages in sanitary sewer lines during construction operations. A management plan outlining the Contractor’s methods of achieving this work shall be provided for Government approval within 30 calendar days of NTP notice. Upon completion and prior to final inspection, the Contractor shall flush all lines and prove flow through the lines.

2.7 Notification: The Contractor shall cease work and notify the Contracting Officer upon discovery of any suspected lead based paint, asbestos containing material and regulated waste material, not identified in this contract, thought to be hazardous to workers or personnel in the area.

2.8 The Swimming Pool bathhouse will remain closed during construction.

3. WORK SCHEDULE:

Working hours for the Contractor will normally be between the hours of 7:30 A.M. and 4:30 P.M. excluding Saturdays, Sundays, and Federal holidays. Refer to Section H of the solicitation/contract document for further information on working days. If the Contractor desires to work during periods other than above, a request must be made to the Contracting Officer in writing four (4) calendar days in advance of his/her intention. If the required base personnel are reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days.

NORMAL WORK HOURS: The Contractor shall schedule all work to commence between the hours of 7:30 AM and 4:30 PM, Monday through Friday, except on the Federal holidays and days designated as “Family Days” by Air Education and Training Command (AETC) as listed below. Permission to work outside these normal business hours may be granted by the Contracting Officer. Requests to work outside the normal work hours must be submitted in writing to the Contracting Officer at least 3 working days in advance of the date requested.

Any Holiday falling on a Saturday will be observed the preceding Friday. Any Holiday falling on a Sunday will be observed the following Monday.

The base could be closed because of security problems, adverse weather, or other events. Unless otherwise notified by the Government, the Contractor should monitor local television stations, radio stations, or Goodfellow’s Facebook page for notification of a possible base closure or late opening. The Contractor may not receive any other form of notification of a base closure from the Government, unless contacted by the Contracting Officer (CO) or the COR. The Contractor is responsible for notifying his/her employees. Contractor(s) do not report when the base is closed due to security problems and/or adverse weather.

3.1 TOBACCO USE IN AETC FACILITIES

Contractors are advised that the Commander has placed restrictions on the smoking of tobacco products in AETC facilities. AFI 40-102, Tobacco Use in the Air Force, outlines the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as government personnel. Smoking is permitted only in designated smoking areas. Additional information, to include locations of designated smoking areas, will be provided to the contractor at the pre-performance conference.

3.2 OPERATIONS SECURITY (OPSEC) REQUIREMENTS

Not Used

3.2.1 SPECIFIC REQUIREMENTS:

a. Contractor personnel will receive OPSEC Awareness Education and Duty-Related Training within 90 days of contract start date and annually thereafter.

b. OPSEC Awareness Education and Training will be provided or coordinated through government channels.

c. The contractor is susceptible to OPSEC assessments, surveys or any other evaluation tool available for the Wing OPSEC Program Manager or subordinate OPSEC Coordinator to use in order to gauge the effectiveness of the overall program.

3.3 UTILITY CONSERVATION

The Contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the contractor. Long distance and Defense Switched Network (DSN) telephone services will not be provided.

4. SAFETY AND HEALTH:

4.1 All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 and 29 CFR 1926, Air Force Instruction 91-203, AFOSH standards including but not limited to ANSI, NFPA, ASTM, and CPSC as applicable, and handbooks, and the Corps of Engineers (COE) Safety Manual 385-1-1 all editions in effect on the date of the solicitation. The Contractor shall comply with all mandatory requirements for lockout/tag out, confined space, hazard communication, fall protection, personnel protection equipment, scaffolding, powered construction equipment, and all project related safety and health requirements.

4.2 All companies who conduct business within the state of Texas must, in accordance with Texas Worker’s Compensation laws (Texas House Bill 62), have an approved company safety policy and an Accident Prevention Plan. The plan, approved by the Texas Worker’s Compensation Commission (TWCC) and meeting all of the requirements of the COE Safety Manual, shall be submitted For Information Only (FIO) in accordance with paragraph 16, SUBMITTAL REQUIREMENTS.

4.3 All holes/pits/trenches/manway openings, etc, that are to be left open shall be surrounded with a 48 inch high mesh fence with highly visible orange plastic coating with warning signs posted “Keep Out” and blinking light from dusk to dawn. Guardrails, fences, barricades, and warning lights or other illumination shall be provided in roadwork construction or near vehicular traffic areas. Fence shall be securely anchored with tension wires and posts as required to prevent sagging and located a minimum of 3 feet from the opening so as to prevent an individual, should they fall across the fencing, from falling into the opening. All exposed trenches/Holes shall also be covered, when not being worked in, with three quarter inch plywood or a metal grating that will prevent anyone from entering the trench/hole.

4.4 Radiation Permits and Authorizations: Civilian Contractors or any other agency bringing a radioactive device, e.g., soil or asphalt density meter, on Goodfellow AFB must have prior approval from the Base Radiation Safety Officer (RSO). An application to bring a radioactive device on Goodfellow AFB shall be forwarded to the Base RSO through the Contracting Officer at least 7 days prior to the anticipated use. The application package shall include:

a. Copy of the appropriate Nuclear Regulatory Commission License or State Permit to operate or own a radioactive device.

b. Copy of the operator’s qualifications and radiation safety training.

c. Radiation dosimetry results for the operator for the prior calendar year, if applicable.

d. Statement of the expected storage and security requirements or other particular needs of the Contractor.

e. Copies of the last two leak tests, as required.

f. Under no circumstances shall an unlicensed radioactive device be used on Goodfellow AFB. Any questions on Contractor’s responsibilities regarding this requirement should be directed to the Base RSO, 17 MDOS/SGOAB, 325-654-3126, prior to the Contractor starting work.

4.5 Confined Space Entry:

Not Used

4.6 Welding, Cutting, and Brazing: Inspection of all welding, cutting, and brazing operations shall be completed by Fire Protection prior to any operation. The Contractor shall provide the appropriate operable fire extinguisher. Fire extinguishers shall comply with NFPA 10. Contractor shall comply be with OSHA STD29 CFR 1910.252 Welding, Cutting, and Brazing (General Requirements) and AFOSH 91-5 Welding, Cutting, and Brazing, which may be viewed at the following website: http://www.e-publishing.af.mil/. Air Force Form 592 USAF Welding, Cutting, and Brazing permit will be issued prior to any operation and shall be kept on site till completion of operation or permit expires. Contact Fire Protection at 325-654-3532/33/34 for issuance of permit.

4.7 Base Fire Regulations: The Contractor shall comply with Base Fire Regulations as set forth in GAFB Instruction 32-2001, titled “Base Fire Prevention Program” in effect as of the date of this solicitation. All work shall be in strict compliance with NFPA-101. The Contractor shall use no explosives or fire in performing the work.

1. STREET CLOSINGS:

Not used

6. DISPOSITION OF WASTE AND EXCESS MATERIALS:

6.1 The Contractor shall make waste determinations for all wastes generated in the performance of this contract, in accordance with the provisions set out in 40 Code of Federal Register (CFR) Part 261, at the time and point of generation. The Contractor shall properly sample, analyze, or by use of process knowledge classify all wastes in accordance with Title 30 Texas Administrative Code (TAC), Chapter 335, Subchapter R at no additional cost to the Government. Unless the Contractor can demonstrate that a waste is non-hazardous, the Contractor shall manage the waste as a hazardous waste until sample test results prove otherwise. All non-hazardous wastes, special wastes, and hazardous wastes (including but not limited to construction debris, material containers, material residues, and unwanted excess materials) resulting from the performance of work under this contract shall be removed from and disposed of off Goodfellow AFB by the Contractor at no additional cost to the Government and in accordance with all applicable Federal, State, and local laws, rules, and regulations. Under no circumstances shall the Contractor dispose of wastes or excess material in trash dumpsters, storm sewers, sanitary sewers, creeks, streams, or other property of Goodfellow AFB. The Contractor and the Government will be co-generators of all wastes resulting from the performance of this contract. Refer to Section 014000-Environmental Protection, paragraph 3, DISPOSAL OF WASTES, for special requirements on disposal of waste types.

6.2 Dumping/cleaning out of concrete trucks on Goodfellow AFB is prohibited. Concrete truck chutes only may be rinsed at the construction site. Wastewater and concrete from this rinse shall be collected in a high-density polyethylene (HDPE) plastic-lined box or pit provided by the Contractor at the site. At the end of pouring operations, the Contractor shall excavate all the waste and liner and properly dispose of same. The pit shall be completely backfilled and the site restored to original conditions.

6.3 All equipment and materials to be removed from the project site not specifically identified for turn-in to the Government shall become the property of the Contractor upon issuance of the Notice to Proceed (NTP). The Contractor shall turn-in all materials specifically designated for turn-in to the Government to a location at Goodfellow AFB, as designated by the Contracting Officer. The Contractor shall obtain a receipt from the Government employee responsible for receiving the returned equipment or material as evidence of compliance. A copy of the receipt(s) shall be submitted to the Contracting Officer prior to final inspection of the project.

7. STORAGE AREA (I.E. TEMPORARY FIELD OFFICE, STAGING AREAS, TOOL/JOB SHACKS, AND OTHER CONSTRUCTION FACILITIES):

There are no Government furnished covered or secure storage areas. Limited storage may be permitted at the discretion of the Contracting Officer and on a space available basis. The location on Goodfellow AFB of the Contractor’s temporary field office, storage, and other construction buildings required temporarily in the performance of the work, shall require written approval of the Contracting Officer. Plans showing temporary field office, storage, and other construction buildings shall be submitted for Government Approval (GA). Utilities at the storage area may or may not be available for Contractor use. The Government implies no responsibility for lost or stolen materials, equipment, or tools, the security of which lies solely with the Contractor. Contractor shall keep his storage areas clean, neat, and orderly. Contractor shall mow grass and weedy vegetation when it reaches a height of 6 inches. Mowing shall be to a height of 3 inches. Mowing shall be accomplished with a rotary mower that leaves the clippings evenly distributed on the soil surface. Mowing shall be accomplished during periods and in a manner that the soil and grass will not be damaged. Towed or self-propelled riding mowers shall not be operated within 3 feet of shrubs or trees. Contractor shall mow areas adjacent to shrubs and trees with hand propelled mowers. Temporary fencing used by the Contractor to delineate construction sites shall be securely anchored with tension wires and posts as required to prevent sagging and an unsightly appearance. Fencing shall be maintained by the Contractor in this manner throughout the life of the contract. Due to high winds in west Texas, Contractor shall take every precaution to preclude trash and materials from blowing off site.

8. TOILET FACILITIES:

There are no toilet facilities available for Contractor use. Contractor shall provide his own portable/temporary toilet facilities.

9. CLEAN-UP:

The Contractor shall at all times keep the construction site, construction trailer(s)/building(s), and storage area(s) in a clean, neat, workman like condition, free from accumulation of waste, rubbish, weeds, overgrown grass, or construction debris, to the satisfaction of the Contracting Officer. All loose or lightweight materials shall be secured to prevent blowing or scattering. The burning of trash or construction debris is strictly prohibited on Goodfellow AFB. Prior to final inspection, the Contractor shall remove all construction debris, tools, equipment, and materials not the property of the Government. Upon completion of the work, the Contractor shall leave the work site and storage area(s) in a clean, neat, and workmanlike condition satisfactory to the Contracting Officer. Refer to Section 014000 - Environmental Protection, paragraph 2.4.6, Post-Construction Cleanup or Obliteration.

10. FINAL INSPECTION:

The Contractor shall advise the Contracting Officer in writing of the Contractor’s desired final inspection date seven (7) calendar days in advance of that desired date to permit proper coordination. The date selected shall provide adequate time for Contractor performed corrections of final inspection deficiencies within the contract performance time. The Contracting Officer will be the final authority for determining whether or not the Contractor’s performance is sufficiently advanced to warrant a final inspection.

11. TESTING:

11.1 Costs of all tests, unless specifically indicated as being performed by the Government, shall be at the Contractor’s expense. The Contractor shall schedule all tests and notify the Contracting Officer or his/her representative in a timely manner prior to any required testing. All test results shall be submitted to the Contracting Officer on AF Form 3000, Material Approval Submittal. Where test reports are to be submitted to the Contracting Officer within 24 hours after the tests are performed, the results may be faxed to the Contracting Officer at a number provided at the preconstruction conference.

11.2 Testing laboratories must be licensed to operate in the State of Texas and must meet the following:

· “Recommended Requirements for Independent Laboratory Qualification”, published by American Council of Independent Laboratories

· Basic requirements of latest edition of ASTM E329 “Standard Recommended Practice for Inspection and Testing Agencies for Concrete, Steel, and Bituminous Materials Used in Construction”

· Latest edition of ASTM E 548, “Qualifications for Testing Labs”

12. AS-BUILT DRAWINGS AND REAL PROPERTY DOCUMENTATION:

12.1 As-builts:

a. The Contractor shall maintain two sets of project drawings with red-line “as-built” notations and markings. Prior to the final inspection, the Contractor shall transfer these red-lined changes to a CADD format that is fully compatible with Autodesk’s AutoCAD version 2000 or greater. The Contractor shall submit one full size hard copy set of as-built maps along with electronic copies in pdf and CADD formats. In addition, the Contractor shall develop and submit GIS data sets on all improved areas. The government will provide the contractor with a copy of Goodfellow’s most current data sets. These data sets shall be compatible with ArcGIS v9.3 format and shall have a minimum accuracy of one meter. The coordinate system for both AutoCAD and GIS files shall be in WGS 1984, UTM Zone 14. The Contractor shall submit two copies of electronic files on a CD or DVD under the cover of an AF Form 3000. The CD or DVD label shall contain, at a minimum, the following information: (1) Brand and version of the CADD software used to generate the drawing files; (2) Short description of the contents including a cross reference of the drawing file names on the CD or DVD and the project drawings sheet sequence numbers or sheet titles; (3) Statement marking the CD or DVD as “as-built” drawings; and (4) any directions required to open files.

b. The Contractor shall submit an interim/draft DD FORM 1354 with all relevant data 30 days prior to the final inspection and the final DD FORM 1354 shall be provided at the project final inspection as prescribed in UFC 1-300-08. Additional information/instructions on completing the DD FORM 1354 will provided by the Government at the pre-construction meeting.

12.2 Instruction Manuals:

Required instruction manual(s) shall be provided in three-ring binder(s) with tabs and an index/table of contents. Provide permanent label on front and side with project title, project number, facility number, street address, Contractor/subcontractor name, address, phone number(s), and manual title/contents description. Include all wiring diagrams and parts lists.

13. SECURITY REQUIREMENTS:

13.1 Goodfellow Air Force Base is a closed/controlled access base. As an effort to minimize peak traffic flows at the entry gates, the Contractor, his employees, and his subcontractors are highly encouraged to avoid scheduling deliveries through the entry control gates from 7:00 A.M. to 8:00 A.M. Monday through Friday as there could be significant delays.

The Government will conduct security/background checks on all construction personnel as required. Security requirements will be briefed at the pre-construction conference and handouts outlining specific requirements will be provided. Screening measures are in place and suitability for employees to access the installation will be determined during the conference. Requirements are subject to change dependent upon current world situations, potential threats, and base exercises. Full cooperation by Contractor work forces is required. Contractor should anticipate certain notification and reporting requirements, preparation of forms, and lists for pass and identification of employees and their vehicles, entry restrictions, key/lock control, and compliance with all base traffic rules and regulations. The Jacobson Gate Visitor Control Center 325-654-4122 is the OPR for passes.

13.2 Goodfellow AFB security may be viewed as being one of two broad levels, the level in effect being dependent on the location or area of project.

a. The lowest level of security exists in general access areas. These areas are all of Goodfellow AFB outside of the “USAF Controlled” areas.

b. “USAF Controlled” access areas are the higher-level security areas. Presence within these controlled access areas are by authorization and/or escort. The movement of authorized personnel in and out of these areas may be limited. Contractor personnel are permitted access to these areas on a need basis only. Access to controlled areas will require the Contractor to coordinate all requests through the Government organization occupying the project site. The Contractor is advised there may be delays gaining access to controlled areas. No delay less than one hour in duration will be considered for down time, nor will delays of less than one hour be cumulative over several time periods.

13.3 Referencing the above, the work on this contract will be in a general Access area.

13.4 BASE ACCESS SECURITY REQUIREMENTS: The Contractor shall comply at all times with base law enforcement and security requirements to include base pass requirements.

13.4.1 Contractor Installation Access Pass. Before arrival, a Government identification card-holding person from the sponsoring agency, Base Contracting office/administrator or applicable local project manager will submit a request for base access using the 17 Training Wing’s Base Access List (BAL) memorandum as a form of registration for each credential applicant. The base sponsor/sponsoring agency/Contracting Officer and the contracted management team should establish an accountability process to account for each applicant, to oversee the BAL process, and to retrieve installation passes when access is no longer required. Base sponsors/sponsoring agencies or contract officers will ensure the BAL is accurate, it is signed and forwarded to the 17 SFS Pass & Registration section for completion of the vetting and fitness determination processes. The BAL should be delivered to Pass & Registration, located at the Visitor Control Center (VCC). When delivery is not possible, the BAL may be forwarded to Pass & Registration via a “.mil” email account located on Goodfellow AFB. The BAL will include pertinent visitor information, reason for entry, frequency of entry, destination, times each day requiring entry, and duration of request.

Contractor Initial (and periodic) Installation Access Screening. The Contractor shall provide Pass and Registration with two forms of identification, one of which will be a state issued photo identification. Prior to being allowed access, a minimum of a background/National Crime Information Center (NCIC) check will be completed on all contractors, requesting unescorted access for official business. This screening process will validate the contractor's suitability to visit Goodfellow and certify that the contractor does not pose an increased threat to the base populace. The contractor will then be issued a temporary Defense Biometric Identification System (DBIDS) pass or AF Form 75A through the expiration date on the BAL request. Possession of an authorized access pass does not automatically authorize or guarantee access to the installation. The individual must still have a valid purpose to be on the installation and properly sponsored, as applicable.

13.4.2 Access Denial. If it is determined a Contractor requesting access has been convicted of a felony or pled guilty to a felony charge within the past 10 years, or is considered not fit to obtain authorized access based on the information obtained during the identity vetting, or criminal history indicates the individual may present a threat to the good order, discipline and morale of the installation, Security Forces personnel will deny entry. The contractor will be informed of the access denial, will be issued an Access Denial Letter, and will be informed on how they may appeal this order.

Access Denial Appeal Process. When denied access, contract visitors will be informed to report back their manager. If the contract worker and management are considering an appeal, it will be submitted by letter to the 17 SFS Commander, within 30 days of access denial. The contract manager should first contact the military contract officer/administrator or on-base sponsor for additional guidance and clarification. The appeal may be delivered to the installation Visitor Control Section or mailed to Security Forces, addressed to 17 SFS/CC, 361 Apache Trail, Goodfellow AFB, 76908. The Contractor's appeal should discuss all facts and reasons to support rescinding access denial. The 17 TRW/CC will approve/disapprove all appeals for entry.

13.4.3 For installation access on non-duty hours or down days:

Identify which workers need access on weekends, federal holidays/family days, and down days.

Ensure only workers that are already vetted are on the Extended-Hours request (no new personnel). New personnel require a new BAL and formal vetting.

Complete the “After Hours” BAL for workers requiring down day access to the installation.

Identify the vehicle requirements. If operations cannot support the search procedures for large vehicles/special purpose equipment, the request may be declined unless arrangements are made to deliver the vehicle/equipment prior, during normal duty hours.

During the above-mentioned days, the Contract officering, contract representative sponsoring ID cardholder is required to be present during hours of the work request.

13.4.4 All BALs are accomplished each time employees or personnel change, not to exceed 180 days. Oversight for BAL updates and establishment of procedures to ensure Physical Access Control System (PACS) credentials and locally created access credentials from individuals who no longer require installation access is the responsibility of the contracting officer/contract administrator.

When an employee (regardless of position) is no longer employed by the contractor or subcontractor all DBIDS passes are to be returned to the Contract Officer/Administrator or to the Visitor Control Center. If a local issued access credential/pass is not returned, the contract officer may withhold funds or the Installation Commander may consider permanent debarment to the installation. Immediate access denial may be initiated by Pass & Registration updating the DBIDS database until disposition of the DBIDS pass is resolved.

13.4.5 TRAFFIC LAWS. Contractor and employees shall comply with Texas transportation code, base traffic regulations and posted signs while on the installation.

13.4.6 WEAPONS, FIREARMS, AMMUNITION. Contractor employees are prohibited from possessing weapons, firearms, or ammunition on themselves or within their contractor-owned vehicle or privately-owned vehicles while on base.

14. IDENTIFICATION OF CONTRACTOR VEHICLES:

Contractor vehicles should be marked on each side with company name with either permanent or semi-permanent/magnetic signage to aide the Security Forces in identifying and permitting them exemption from basewide exercises.

15. WARRANTIES:

Any warranties given to the Contractor or subcontractor at any tier from a manufacturer of equipment or other items, which are provided under this contract, shall be transferred to the Government upon final acceptance in accordance with the clause contained in the basic contract, Section I. Contractor shall submit in writing a single listing with all applicable warranties attached. Negative responses are likewise required in writing.

16. SUBMITTAL REQUIREMENTS:

16.1 The submittals listed on the attached AF Form 66 shall be required and shall be submitted for approval or information using AF Form 3000. Where a submittal cannot be provided within the required submission date, Contractor shall submit in writing a letter stating the reasons why and furnishing a new projected submission date.

16.2 Submittal Classification: Submittals are classified as follows and delineated as such on AF Form 66 under the “Remarks” column:

16.2.1 Government Approved - GA: Government approval is typically required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer. Within the terms of the contract clause entitled “Specifications and Drawings for Construction,” they are considered to be “shop drawings”.

16.2.2 For Information Only - FIO:

All submittals not requiring Government approval will be for information only. They are not considered to be “shop drawings” within the terms of the Contract clause referred to above.

16.3 General Requirements:

a. GA and FIO submittal data shall be transmitted under separate AF Forms 3000 and assigned different Submission Numbers.

b. The Contractor shall designate on each AF Form 3000, in the “Submission Number” block, either FIO or GA to show the transmittal type. This procedure allows ready identification of FIO or GA submittals.

c. Submittals transmitted with AF Form 3000 shall be identified by marking it with the same Submission Number appearing in the “Line Number” column on the AF Form 66.

16.4 Specific Requirements for FIO Submittals:

a. A single fully coordinated FIO submittal shall be made for each technical section listed/required on the AF Form 66. Each FIO submittal listed on the AF Form 66 shall be submitted as a separate item on the AF Form 3000 in the order they appear on the AF Form 66. Technical data provided with the AF Form 3000 shall conform to the requirements in each Technical Section. Submittals involving colors and interior design shall all be transmitted concurrently.

b. Items such as mill certificates or other test data that are usually unavailable until the equipment/material is actually manufactured/fabricated must still be identified on the initial AF Form 3000. An explanation stating this data shall be submitted later by Submittal Number (fill in Submission Number) after materials are manufactured / fabricated (or other explanations as appropriate) shall be included with this identification. A separate submittal for long lead-time equipment or material may be made if sufficient data is furnished to show contract compliance. (An explanation shall be provided on a separate sheet, if necessary, explaining why a partial submittal is being made. Explanation shall include the estimated delivery date of the equipment/material and the Submission Number of the submittal that shall contain data required by the particular specification section for the remaining equipment/materials.) Samples of materials must be submitted along with technical data, not under separate transmittals.

16.5 FIO Submittal Review:

a. The Contractor has full responsibility for reviewing and certifying that all FIO submittal data and all equipment and/or materials fully comply with the contract. FIO Submittals are for the Government’s information and real property record purposes; they will not be approved/disapproved nor returned to the Contractor.

b. The Government may perform quality assurance reviews and re-reviews of FIO submittals at any time during the contract. If the Government determines submittal data is incomplete or not in compliance with contract, comments will be provided. Comments will state, “Disagree with Contractor’s Certified Compliance” and list items not in compliance or not provided as required by the contract. The Contractor shall respond to all comments by return FIO resubmittal on a new AF Form 3000.

16.6 Specific Requirements for Government (GA) Approved Submittals:

a. The Contractor is responsible for controlling and ensuring all data submitted is complete and in full compliance with contract requirements.

b. A separate submittal shall be made for each technical section with GA submittals. FIO submittal data shall not be mixed with GA submittal data.

c. The Government will provide written comments and/or approval/disapproval action as appropriate. One (1) copy of the submittal, along with any comments, will be provided to the Contractor. The Contractor shall provide a resubmittal with all data necessary to show compliance with Government comments on all disapproved submittals.

16.7 Variations/Deviations/Departures from the Contract Drawings or Specifications:

a. Contractor proposed variations, deviations, or departures from the contract requirements shall be noted/marked in red on the face/cover of each copy of the submittal data and shall be provided with a letter attachment to the AF Form 3000 summarizing the proposed variation, deviation, or departure. For FIO submittal deviations an asterisk “*” shall be placed in the block under “Submission Number” next to the “FIO.” These submittals will then be automatically redesignated GA. Variations, deviations, or departures will be processed and approved the same as GA submittals. Variations, deviations, or departures shall contain sufficient information to permit complete evaluation. Additional sheets may be used to fully explain why a variation, deviation, or departure is requested. The Government reserves the right to disapprove or rescind inadvertent approval of submittals containing unnoted/unmarked variations, deviations, or departures.

b. Any submittal annotated by a supplier/vendor with “Field Verify,” “Select Color,” and the like must be accompanied by the Contractor’s written response to the supplier’s query.

16.8 Government approval of submittals indicates only that the general method of construction, materials, detailing, and other information appear satisfactory. Approval does not relieve the Contractor of the responsibility for any error which may exist. The Contractor remains responsible for the dimensions and design of adequate connections, details, material compatibility, and satisfactory construction of all work necessary to fulfill the intent of this project.

16.9 Preconstruction Submittals

a.Construction Progress Schedule: AF Form 3064.
b.Submittal Register: Form 66.
c.Pre-Construction Survey Report
d.Samples of colored Splash pad rubber, artificial turf, and toy features used on splash pad.
e.Detailed drawings for equipment shed, electrical work, recirculating system and piping system.

16.10 Contract Closeout

All approved submittal data in PDF format. Submit on RW-CD with protective cover and affixed label identifying project number, project name, date, and contents.

END OF SECTION

SECTION 010200 - UTILITIES

1. SCOPE: This section covers identification, interruption, and use of utilities.

2. IDENTIFICATION: The Government does not know the exact location of all utilities in the work area. The Contractor shall take reasonable precautions in determining the exact location of all existing utilities within the contract work area prior to any excavating, trenching, backfilling, or disturbance. Upon request by the Contractor, the Government shall furnish all available information in its possession concerning utilities in the contract work area. However, the accuracy of the information provided by the Government is not guaranteed and is only intended to provide some measure of assistance to the Contractor. The Government does not have, nor will it provide, record drawings of Frontier telephone cable plant and Suddenlink cable. The Contractor shall call 17 CS/SCMP at 325-654-3010 a minimum of five (5) calendar days in advance to have underground communications cable routes marked. In addition, the Contractor shall also notify 1-800-DIG-TESS. In the event the Contractor identifies utilities in the contract work area, which interfere with the newly proposed construction, the Contracting Officer shall be immediately notified and the Government will take necessary corrective action at no cost to the Contractor. The Contractor shall furnish to the Contracting Officer as-built drawings clearly identifying the exact location of all utilities identified in the work area prior to project final inspection.

2.1 Contractor must initiate and process for approval a Work Clearance Request AF Form 103 through 17 CES/CEPM a minimum of fourteen (14) calendar days prior to the start of any construction work. Excavation is not authorized without issuance of a completed and approved AF Form 103. After initial issue, it is the Contractor’s responsibility to keep the Work Clearance Request coordinated and up-to-date/current through the remainder of the contract.

2.2 Any removal/relocation/reconnection of any communication device shall be coordinated in advance with 17 CS/SCMP at 325-654-3010. Any removal/relocation/reconnection of any Cable TV device shall be coordinated in advance with 17 CS. Communications and Cable TV devices to remain shall be protected as required when work proximity dictates.

3. INTERRUPTIONS:

3.1 Planned Utility Outages: The Contractor shall coordinate all requests for utility outages with the Contracting Officer in writing fourteen (14) calendar days prior to date of requested outage. Water, gas, sewer, and electrical outages shall be held to a maximum duration of 2 hours unless otherwise approved in writing.

3.2 Unplanned Utility Outages (Accidental Disruption of Utilities): In the event of accidental disruption of any utility, the Contractor shall immediately notify the Contracting officer of the unplanned outage. The Contractor shall immediately take every reasonable step to repair the damage in a manner acceptable to the Government and shall restore the utility to full use as soon as practicable. Additionally, if the unplanned interruption affects Military Family Housing (MFH) areas, the Contractor shall provide verbal or written notice to each affected family. If the Contractor so desires, and the Government agrees, the Government will complete necessary repairs to the damaged utility and withhold from payments due to the Contractor the necessary amount to defray all costs associated with the repair of the utility.

3.3 For all drinking water disruptions and new construction, the Contractor shall adhere to 30 TAC 290 Subchapter D paragraph 290.46(g and j). Submit Drinking Water Analysis Report and a “Drinking Water Customer Service Inspection checklist” via an AF Form 3000 for Government Approval. Contact Bioenvironmental Engineering at 325-654-3126 prior to restoring drinking water service.

4. USE AND AVAILABILITY: All reasonable quantities of existing utilities will be made available to the Contractor without charge. Proposed temporary connections must be coordinated with the Civil Engineering Utilities Shop at 325-654-5186 in advance of any connection. Any temporary connections or lines required will be installed by the utility owner. The Contractor shall provide all metering as well as maintain meters as required. Any damage associated with the use of these utilities shall be repaired and/or replaced in a manner satisfactory to the Contracting Officer at Contractor’s expense. Prior to using any fire hydrant on Goodfellow AFB, the Contractor must complete the Contractor Request for Use of Goodfellow AFB Fire Hydrants (a copy of which is attached at page 01020-3) and submit to the Contracting Officer and notify the Fire Dept. at 325-654-3532. Contractor shall take appropriate measures to prevent backflow into the base’s potable water supply system. Contractor shall always strive to conserve the electric, natural gas, and water utilities at Goodfellow Air Force Base.

END OF SECTION

The following information must be prepared and forwarded, on AF Form 3000, Material Approval Submittal, to the 17th Contracting Squadron for approval and coordination with Civil Engineering’s Fire Dept and Utilities Element prior to use of base fire hydrants.

Contractor Request for Use of Goodfellow AFB Fire Hydrants.

1. The . Company requests the use of fire hydrant number for the purpose of filling used in the performance of the contract to . Period of hydrant use will be to . I understand approval is contingent on:

a. The company providing a suitable connection with a Class III Back Flow Preventer (reduced pressure principle device) and screw type globe valve to be attached to the hydrant. The connection will be 2½” National Standard fire thread. The backflow device and valve shall be properly supported to prevent damage to fire hydrant threads.

b. Leaving the connection in place during approval period.

c. Ensuring the hydrant is fully opened and left in that position during approval period, except in periods of freezing weather.

d. Ensuring an approved fire hydrant wrench is used to open/close the hydrant.

e. Ensuring all servicing from the hydrant is done at the top of the vehicle or tank. No bottom servicing will be permitted.

f. Using no quick opening valves causing excess water hammer in the main.

g. Discontinuing hydrant use if there is any hydrant malfunction or leakage from underground and reporting same to the fire department, 654-3532.

2. I understand and agree that Company assumes full responsibility for any damage to the hydrant, water mains, adjacent grounds, vegetation, buildings, or streets resulting from filling operations.

(Signature) (Date)

(Print Name) (Print Title)

SECTION 014000 - ENVIRONMENTAL PROTECTION

1. APPLICABLE ENVIRONMENTAL REGULATIONS, LAWS, AND PUBLICATIONS: The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. All publications shall be the latest version/edition/revision of the documents listed below, in effect on the date of this solicitation, except where a date is given.

1.1 Code of Federal Regulations (CFR):

29 CFR, Part 1910 Hazardous Waste Operation and Emergency Response

40 CFR 61, Subpart M National Emissions Standard for Hazardous Air Pollutants

40 CFR, Part 82 Protection of Stratospheric Ozone

40 CFR, Part 117 Determination of Reportable Quantities for Hazardous Substances

40 CFR, Part 122 National…