This document outlines a federal contract solicitation for cured-in-place pipe (CIPP) rehabilitation of sewer lines at Goodfellow Air Force Base in San Angelo, Texas. The contractor will be required to clean and inspect approximately 3,165 linear feet of 6-, 8-, and 10-inch sewer mains using closed-circuit television and then rehabilitate the lines using CIPP. Additional requirements include bypass pumping during inspection and installation, as well as post-installation television inspection. The solicitation is set aside for small businesses with a NAICS code of 237110 and size standard of $36.5 million. The period of performance is 120 calendar days. The anticipated bid opening is November 26, 2019. Interested parties should register at FedBizOpps and subscribe to receive announcements. Questions must be submitted in writing to the points of contact provided by the specified date. Environmental and small business compliance are required.

SOW - Sewer CIPP

View the file

Other files for this federal contract opportunity

Other files attached to Sewer Lines CIPP, newest first.
File Type Posted
Amendment 0001 - Questions and Answers.pdf PDF
Amendment 0001 - FA303020B00010001 SF 30.pdf PDF
Amendment 0001 - Site Visit Attendance.pdf PDF
Attachment_4_-_AF_Form_66.pdf PDF
Attachment_1_-_Drawings.pdf PDF
Solicitation_-_FA303020B0001.pdf PDF
Attachment_5_-_Wage_Determination.pdf PDF
Attachment_2_-_BAL_Request.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ABBREVIATED STATEMENT OF WORK

FOR

REPAIR SANITARY SEWER OUTFALLS

PROJECT #

JCGU 09-1007 (100 - 200 Areas)

October 2019

PREPARED BY:

17TH CIVIL ENGINEER SQUADRON (AETC)

460 E. KEARNEY BOULEVARD

GOODFELLOW AFB, TX 76908-4104

TABLE OF CONTENTS

STATEMENT OF WORK (SOW)

I. Part 1.0 – Scope of Work Page - 3

Part 2.0 – Products Page - 8

Part 3.0 – Execution Page - 18

Part 4.0 – Utility Outages and Special Conditions Page - 25

Part 5.0 – Environmental Requirements Page - 26

Part 6.0 – Site Maintenance and Cleanup Page - 30

Part 7.0 – Energy Conservation Page - 30

Part 8.0 – Responsibility Page - 30

Part 9.0 – Storage and Parking Page - 30

Part 10.0 – Completion of Work Page - 31

II. Drawings/Technical Exhibits Refer to Drawing Index

III. AF Form 66 Submittal Register

STATEMENT OF WORK

FOR

REPAIR SANITARY SEWER OUTFALLS

Project JCGU 09-1007 (100 - 200 Areas)

PART 1.0 – SCOPE OF WORK:

1.1 GENERAL: The work to be performed under this contract and in accordance with this Statement of Work shall consist of furnishing all necessary parts, labor, tools, transportation, supplies, supervision, equipment, materials, and incidentals necessary for providing all work as shown on the plans (Technical Exhibits), statement of work, and all applicable codes, regulations, standards and criteria in effect at the date of solicitation. The work outlined below shall consist of, but not be limited to the following:

1.2 PROJECT DESCRIPTION: Refer to Drawing Cover Sheet for Schedule of Quantities Refer to Section IV, Attachments ‘A’: For a summary of facilities that are connected to the sanitary sewer outfalls in the building 100 - 200 areas.

a. Flush and clean sanitary sewer pipelines, as required to remove debris and blockages.

For additional information on line flushing and obstructions, refer to para 3.1.2 thru 3.1.5.

b. Provide CCTV video/Pre-TV inspection of existing conditions for all sanitary sewer pipes.

c. Submit CCTV video (Pre-TV) inspection for Government review and approval. Do not proceed with any new sanitary sewer work until results of the CCTV video have been approved by the Government.

d. Rehabilitate sanitary sewer pipelines by the installation of Fold-and-Form Pipeliners (FFP) a Cured-in-Place Pipe (CIPP) liner.

Refer to para 3.1.3 for sanitary sewer bypass operations.

e. Submit CCTV video (Post-TV) inspection of the new CCIP for all sanitary sewer pipelines.

1.3 LOCATION: Goodfellow Air Force Base is located in Tom Green County, on the southeast side of San Angelo, TX. and is bounded to the north by Highway #388 (Paint Rock Rd.), to the west by Fort McKavitt Rd and Bell Street/Christoval Road, to the south by Highway #1223 (San Antonio Hwy.) and to the east by the eastern city limits. Work location is as shown on the drawings at building areas 100 – 200 area.

1.4 WORK AND MECHANICS: The work for this project shall be executed in the best and most workmanlike manner, by qualified and efficient mechanics/tradesmen, skilled in their respective trades. Only certified journeymen in each respective trade, or apprentices under the direct supervision of certified journeymen, shall be permitted to install and/or supervise installation for this project. Individual trade work for this project shall be performed and quality maintained by the applicable trade, only. All trades shall coordinate their work with that of other trades. The Contractor shall coordinate and perform all operations in a manner that will result in a professional and expeditiously completed project. The work shall be in strict accordance with prevailing industry standards and manufacturer’s instructions.

Work and materials shall comply with this Statement of Work and the editions in effect at the time of this solicitation for all applicable criteria, regulations, guidelines and codes, all of which are made a part thereof.

1.5 PERFORMANCE PERIOD: The Contractor shall have One Hundred & Twenty (120) calendar days to perform all work associated with this project.

1.6 WORK AREA ACCESS: Government escorts are not needed for this project.

1.7 WORKING CONDITIONS:

1.7.1 At the beginning of the contract following NTP, the Contractor shall have Forty Five (45) calendar days to complete CCTV (video) and flush of all existing sanitary sewer conditions for the buildings in the 100 - 200 areas as described in the plans. No CCIP work shall occur until all CCTV video has been completed, results of the CCTV video submitted to the Government on DVD’s and subsequently reviewed/approved by the Government to ensure all existing conditions have been identified.

1.7.2 All base facilities will remain occupied during the entire performance period. The Contractor shall ensure the sanitary sewer outfall(s) are active at all times. The Contractor shall coordinate the work of all activities whereby both the Government and the Contractor can continue operations with the least possible interference and inconvenience. The Contractor shall provide sewage bypass pumping between sanitary sewer manholes to enable continuous sewage flow without interruptions.

1.7.3 A written notification regarding all water, gas, power or communication outages must be submitted by the Contractor (7) seven calendar days in advance to the Contracting Officer, unless otherwise noted herein. All water, power or communication outages must be scheduled for weekends only.

1.7.4 The Contractor shall provide and maintain portable restroom (porta potties) at all times at facilities affected by construction operations, refer to Attachments ‘A’. Minimum 4 porta potties units located adjacent to the affected facilities in the 100 and 200 areas.

1.7.5 All work on sanitary sewer laterals requiring disconnection and subsequent reconnection shall be completed within/not exceed 4 hours. All sewage interruptions shall be coordinated 7 calendar days in advance with written notifications.

1.7.6 All work requiring open cutting/or disturbing asphalt pavements shall be immediately repaired with cold patching before close of the business day then followed by permanent hot mix asphalt repair. New asphalt to match existing pavement.

1.7.7 There are no toilet facilities available for Contractor use. Contractor shall provide his own portable/temporary toilet facilities for his personnel.

1.7.8 Refer to para 3.3 below for additional information on temporary sanitary sewer bypass operations. Note, the Contractor shall immediately notify the Government of any sewage spills.

1.7.9 Traffic Control Plan: Submit traffic control plan.

a. Utilize manholes in the project area as installation access points, at the direction of the

Contracting Officer.

b. When a street must be closed to traffic because of the location of the sewer access point, submit a detailed Traffic Control Plan to the Contracting Officer at least 10 calendar days in advance.

c. Provide labor, signs, barricades, cones, arrow boards, flaggers and any additional equipment necessary to complete the work.

1.8 CONCRETE TRUCKS: Cleaning out of concrete trucks on Goodfellow AFB is prohibited.

Concrete truck chutes, only, may be rinsed at the construction site. Wastewater and concrete from this rinse shall be collected in a high-density polyethylene (HDPE) plastic-lined box or pit provided by the Contractor at the site. At the end of pouring operations, the Contractor shall excavate all the waste and liner and properly dispose of same. The Contractor shall dispose of all concrete debris to an authorized off base site and shall remove any and all concrete debris and residue at the end of the project at no additional cost to the Government. The pit shall be completely backfilled and the site restored to original conditions.

1.9 REFERENCES: All publications listed herein shall be the most current editions in effect at the time of solicitation and form a part of this Statement of Work. The publications are referred to in the text by basic designation only and include the following:

GAFB INSTRUCTION

GAFBI 32-2001 Goodfellow AFB Base Fire Protection Program GAFBI 31-102 Installation Security Instruction

AMERICAN STANDARD TESTING METHODS

ASTM D790 Standard Test Methods for Flexural Properties of Unreinforced and Reinforced Plastics

ASTM C923-79 Standard Specification for Resilient Connectors between Reinforced Concrete Manhole Structures, Pipes and Laterals

ASTM F1216 Standard Practice for Rehabilitation of Existing Pipelines and Conduits By the Inversion and Curing of a Resin Impregnated Tube

ASTM F1504 Standard Specification for Folded Polyvinyl Chloride (PVC) Pipe for Existing Sewer and Conduit Rehabilitation

ASTM F1505 Standard Specification for Folded Polyvinyl Chloride (PVC) Pipe for Existing Sewer and Conduit Rehabilitation

ASTM D1533 Standard Specification for Deformed Polyethylene (PE) Liner

ASTM D1743 Standard Test Methods for Determining Corrosion Preventing Properties of Lubricating Greases

ASTM F1867 Standard Practice for Installation Folded/Formed Poly (Vinyl Chloride) (PVC) Pipe Type A for Existing Sewer and Conduit Rehabilitation

ASTM F1871 Standard Practice for Installation Folded/Formed Poly (Vinyl Chloride) (PVC) Pipe Type A for Existing Sewer and Conduit Rehabilitation

ASTM F2019 Standard Practice for Rehabilitation of Existing Pipelines and Conduits by the Pulled in Place Installation of Glass Reinforced Plastic (GRP) Cured- In-Place Thermosetting Resin Pipe (CIPP)

ASTM D2990 Standard Test Methods for Tensile, Compressive and Creep Rupture of Plastics

ASTM D5813 Standard Specification for Cured-In-Place Thermosetting Resin Sewer Piping Systems

US ARMY CORPS OF ENGINEERS HEALTH AND SAFETY MANUAL: EM 385-1-1

OCCUPATIONAL HEALTH AND SAFETY ADMINISTRATION (OSHA)

OSHA STD 29 CFR 1910 and 1926 OSHA STD 29 CFR 1910.252 Welding, Cutting and Brazing (General Requirements)

1.10 SUBMITTALS: The Contractor shall provide submittals in the form of manufacturer’s data, certificates of compliance and samples for all items provided and installed per the attached AF Form 66. The Contractor will not be permitted to perform any work on site without approved submittals. The submittals listed on the attached AF Form 66 shall be required and shall be submitted for Government Approved (GA) or For Information Only (FIO). Use AF Form 3000 to process submittals. Submit four copies of submittals to Contracting Officer. Execute DD Form 1354 Checklist and submit to Contracting Officer before final payment is issued.

1.11 MANUFACTURER’S CATALOG DATA: Data composed of catalog cuts, brochures, circulars, specifications and product data, and printed information in sufficient detail and scope to verify compliance with requirements of the contract documents.

1.12 MANUFACTURERS WARRANTY: The Contractor shall identify all items being installed that are covered by a manufacturers guarantee or warranty and provide validated copies of such.

The identification shall list the name of the company and the expiration date of the guarantee or warranty.

1.13 PRODUCT DATA: Manufacturer's products, installation and maintenance instructions, refer to AF Form 66.

1.14 AS BUILT DRAWINGS: Following the project completion or turnover, within 14 days the Contractor shall furnish 2 redline sets of mark up as built drawings to the Contracting Officer.

1.15 DELIVERY AND STORAGE: All equipment and materials delivered and placed in storage shall be stored with protection from the weather, humidity and temperature variation, dirt and dust, and any other contaminants. Store all materials in a secure, clean and dry location.

1.16 SAFETY: All Contractor operations shall be conducted and performed in accordance with Department of Labor, OSHA requirements found in 29 CFR 1910 (1910.146 and 1910.147) and 29 CFR 1926, and Air Force Occupational Safety & Health (AFOSH) standards including AFI 91-203, Air Force Consolidated Occupational Safety Instruction. The Contractor shall also ensure that all work is performed in accordance with project identified national standards, military manuals, instructions, pamphlets, standards, and handbooks, and with the edition in effect on the date of this solicitation of the Corps of Engineers (COE) Safety Manual 385-1-1. All job sites are subject to inspections by the Department of Labor.

1.16.1 Resolution of Department of Labor citations for violations of Occupational Safety and Health Standards is a Contractor responsibility and shall provide for no basis of a claim against the Government.

1.17 TEMPORARY FENCE: Prior to the start of any work for this project, the Contractor shall provide temporary orange warning fencing around the site perimeter.

1.18 DEMOLITION: The Contractor shall recycle or divert construction wastes from landfill disposal to the maximum extent practicable. Contractor shall track recycling and waste disposal and submit the report on the provided Construction Waste Management Form for Government Approval at the end of the project, and prior to final acceptance of the work. The Contractor shall take all necessary precautions to prevent damage to property to remain in place. Any damage to the aforementioned shall be repaired or replaced by the Contractor at no additional cost to the Government.

1.19 UTILITY CONSERVATION: The Contractor will be required to participate in government energy conservation programs. For the purpose of this contract, utilities such as water, electricity, etc., will be furnished by the government at no cost to the Contractor. Long distance and Defense Switched Network (DSN) telephone services will not be provided.

1.20 WORK SCHEDULE: Working hours for the Contractor will normally be between the hours of 7:30 A.M. and 4:30 P.M. excluding Saturdays, Sundays, and Federal holidays. Refer to Section H of the solicitation/contract document for further information on working days. If the Contractor desires to work during periods other than above, a request must be made to the Contracting Officer in writing four (4) calendar days in advance of his/her intention. If the required base personnel are reasonably available, the Contracting Officer may authorize the Contractor to perform work during periods other than normal duty hours/days.

1.21 NORMAL WORK HOURS: The Contractor shall schedule all work to commence between the hours of 7:30 AM and 4:30 PM, Monday through Friday, except on the Federal holidays and days designated as “Family Days” by Air Education and Training Command (AETC) as listed below. Permission to work outside these normal business hours may be granted by the Contracting Officer. Requests to work outside the normal work hours must be submitted in writing to the Contracting Officer at least 3 working days in advance of the date requested. If weekend work is required Contractor shall submit request in writing to Contracting Office a minimum of 72 hours in advance.

Federal Holiday New Year’s Day 01 Jan 01 Jan Martin Luther King’s 3rd Monday in January 21 Jan President’s Day 3rd Monday in February 18 Feb Memorial Day Last Monday in May 27 May Independence Day 4 Jul 04 Jul Labor Day 1st Monday in September 02 Sept Columbus Day 2nd Monday in October 14 Oct Veterans Day 11 Nov 11 Nov Thanksgiving Day 4th Thursday in 28 Nov Christmas Day 25 Dec 25 Dec

While AETC Family Days have not been identified past calendar year 2019 it is anticipated that the same number of AETC Family days will be declared each year.

Any Holiday falling on a Saturday will be observed the preceding Friday. Any Holiday falling on a Sunday will be observed the following Monday.

The base could be closed because of security problems, adverse weather, or other events. Unless otherwise notified by the Government, the Contractor should monitor local television stations, radio stations, or Goodfellow’s Facebook page for notification of a possible base closure or late opening. The Contractor may not receive any other form of notification of a base closure from the Government, unless contacted by the Contracting Officer (CO) or the COR. The Contractor is responsible for notifying his/her employees. Contractor(s) do not report when the base is closed due to security problems and/or adverse weather.

1.22 TOBACCO USE IN AETC FACILITIES: Contractors are advised that the Commander has placed restrictions on the smoking of tobacco products in AETC facilities. AFI 40-102, Tobacco Use in the Air Force, outlines the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as government personnel. Smoking is permitted only in designated smoking areas. Additional information, to include locations of designated smoking areas, will be provided to the Contractor at the pre-construction conference.

PART 2.0 – PRODUCTS:

2.1 REFERENCES TO MATERIALS, MANUFACTURERS AND PRODUCTS: Materials shall be the standard product of manufacturer’s regularly engaged in the manufacture of such products.

The products furnished shall meet the quality and specifications indicated herein.

2.2 Site Visits: Prior to NTP, the Contractor may visit the work areas to become thoroughly familiar with details of the work and working conditions, verify dimensions in the field, and shall advise the Contracting Officer of any discrepancies before starting the work.

2.3 Closed Circuit TV Camera (CCTV) System: Provide audio with narrative commentary and evaluations describing in detail the conditions of the pipeline and manhole interior.

Identify and record locations of flat grades, dips, deflected joints, open joints, broken pipe, protrusions into pipeline, and points of infiltration.

Locate and record service/lateral connections.

Record locations of pipeline defects and connection horizontal distance, in feet and direction from manholes.

Video with pipe section plugged as to view 100 percent pipe diameter, use flow control methods as specified for bypass pumping system, to eliminate surcharging and reduce flow.

Utilize cameras specially designed and constructed for closed-circuit sewer line inspection.

Utilize camera equipment with pan and tilt capability to view each lateral connection at multiple angles.

Utilize camera capable of moving both upstream and downstream; minimum 1,000 feet horizontal distance with one setup; direct reading cable position meter.

2.4 FFP CIPP SYSTEM DESCRIPTION: Submittal Required

a. Rehabilitate sewer pipelines by the installation of Fold-and-Form Pipeliners (FFP) and a Cured-in-Place Pipe (CIPP) liner. Provide a continuous and tight-fitting liner throughout the entire length of the original pipe. Extend the FFP CIPP the full length of the original pipe, from entry point to exit point, and provide a structurally sound and water-tight new pipe within a pipe.

b. Cleanup, restore existing surface conditions and structures, and repair portions of the FFP CIPP system determined to be defective. Conduct installation operations and schedule cleanup in a manner to minimize obstruction and inconvenience to traffic, pedestrians, and tenants.

2.4.1 Structural Requirements:

c. The physical properties, wall thickness and characteristics of the finished FFP will vary according to the material installed. Provide a FFP system which meets or exceeds the minimum properties specified herein:

(1) The FFP in accordance with the applicable ASTM Standard, depending on the material being installed.

(2) The installed FFP material shall meet or exceed the structural properties, as listed below.

As a minimum, base the required structural FFP wall thickness on the physical properties of the manufactured FFP and in accordance with ASTM F1504 and ASTM F1533.

Design Safety Factor 2.0

Modulus Retention Factor As submitted and specific to type of pipe material

Ovality 2% or as measured by field inspection

Constrained Soil Modulus Per AASHTO LRFD Section 12 and AWWA M45

Soil Depth (above the crown) As specified or indicated on the Plans

Live Load Roadway as applicable

Soil Load (assumed)

120 lb/cu. ft.

Minimum service life 50 years

MINIMUM PHYSICAL PROPERTIES

Property Test Method Per Applicable ASTM

Flexural Modulus of Elasticity

AST

M

D790 HDPE -

PVC -

MPa118,000 psi

MPa280,000 psi Flexural Strength AST M

D790 HDPE -

N/A PVC

- 34.5

PVC Type

MPa5,000 psi

- 28.3 MPa4,100 psi

LINER REQUIREMENTS: Submittal Required.

d. The liner thickness for the CIPP shall be in accordance with the applicable provisions of ASTM F1216 and ASTM D2412 for fully deteriorated gravity pipe conditions.

e. The minimum installed, cured liner thickness is as follows, regardless of what the calculations indicate as the required minimum thickness:

4 inch and 6 inch sewer: 0.18 inches 8 inch sewer: 0.24 inches up to 17 feet deep 8 inch sewer: 0.30 inches up to 25 feet deep 10 inch sewer: 0.236 inches up to 11 feet deep 10 inch sewer: 0.30 inches up to 18 feet deep 10 inch sewer: 0.36 inches up to 25 feet deep

f. The physical properties and characteristics of the finished liner will vary considerably, depending on the types and mixing proportions of the materials used, and the degree of cure executed. Control these variables and provide a CIPP system which meets or exceeds the minimum properties specified herein:

(1) The CIPP shall meet or exceed ASTM F1216 Appendixes. No bonding to the original pipe wall.

(2) The CIPP Creep Retention Factor shall comply with ASTM D790 test method.

Use this value unless long term test data (ASTM D2990) substantiates a higher retention factor is required.

(3) At a minimum, the CIPP is to meet or exceed the structural properties, as listed below:

MINIMUM PHYSICAL

PROPERTIES

Property Test Method Cured Composite (ASTM F1216)

Flexural Modulus of Elasticity

(Short Term) (Felt Tubes)

Felt/Fiberglass, Fiberglass meeting manufacturer's specifications

ASTM D790 250,000 psi

Flexural Strength

(Short Term) (Felt Tubes)

Felt/Fiberglass, Fiberglass meeting Manufacturer's specifications

ASTM D790 4,500 psi

(4) Prior to installation of the lining materials, submit certification of compliance with these specifications or the requirements of the pre-approved CIPP system.

Include certified material test results that confirm materials conform to these specifications.

(5) Materials not complying with these requirements will be rejected.

2.4.2 Performance Requirements:

2.4.2.1 Provide continuous and jointless FFP from manhole to manhole, free of defects that will affect the long term life and operation of the pipe.

2.4.2.1.1 The FFP is to fit sufficiently tight within the existing pipe so as to not leak at the manholes, at the service connections, or through the wall of the installed pipe.

2.4.2.1.2 Seal these areas to stop leakage using a material compatible with the FFP.Repair or replace the liner if leakage occurs through the wall of the pipe. Final approval of the liner installation will be based on a leak tight pipe.

2.4.2.1.3 The installed FFP is to have a 50 year corrosion resistance to the typical chemicals found in domestic sewage.

2.4.2.1.4 Provide a continuous and jointless CIPP from manhole to manhole or access point to access point, free of defects that will affect the long term life and operation of the pipe.

2.4.2.1.5 Fit the CIPP sufficiently tight within the existing pipe so as to not leak at the manholes, at the service connections or through the wall of the installed pipe. Seal leaks at the manholes or the service connections using a material compatible with the CIPP. If leakage occurs through the wall of the pipe, repair or replace the liner.

2.4.2.1.6 The CIPP shall have a life expectancy of 50 years or greater and to have a 50 year corrosion resistance to the typical chemicals found in domestic sewage.

2.4.2.1.7 CIPP shall conform to the original circular pipe shape and to a minimum of 90 percent of original sewage flow capacity. Repair over-cut service connections to meet the requirements of these specifications. Re-establish the service openings utilizing a remotely controlled brushing device to smoothly cut and remove jagged edges, material and shavings resulting in the cutting operation.

2.4.2.1.8 Hydrophilic Seals:

Submit Hydrophilic Seal information that specifically indicates that the seal material is compatible with the liner material being utilized and the hydrophilic seal will produce a tight fitting, waterproof seal between the liner and the host pipe at the manhole location.

2.5 ASSEMBLY: Submittal Required.

2.5.1 Not Used

2.5.2 Tolerances:

2.5.2.1 Measure the installed CIPP thickness for each line section installed. The installed CIPP liner thickness tolerance is minus 5 percent to plus 10 percent. Submit a minimum of one CIPP liner sample for every line section of installed CIPP liner to be used to check the liner thickness.

Replace sections where the liner thickness does not fall within the approved design thickness.

2.5.3 Equipment: Provide sufficient equipment to stop or by-pass sewer flow, clean and CCTV mains, install and cure liners, and re-instate service connections as indicated in the Contract documents.

2.5.4 Manhole Connections

2.5.4.1 Form a tight seal between the rehabilitation (lining) material and the host pipe at the pipe penetration of the manhole wall. Apply the seal consisting of a resin mixture or hydrophilic seal compatible with the installed liner at the manhole-wall interface in accordance with the liner system manufacturer's specifications. Seal annular spaces greater than 13 mm 1/2 inch with manhole wall repair material. Finish off the seal with non-shrink grout or cementitious liner material placed around the pipe opening from the inside of the manhole in a band at least 100 mm 4 inches wide. Provide an epoxy coating over the repair on the manhole walls.

2.5.4.2 Provide a continuous and smooth invert through manholes. If a liner is installed through a manhole, the bottom portion of the liner is to remain. Grout and shape the bench of the manhole as necessary to support the liner.

If the liner terminates on either side of the manhole, build up the invert to remove flow restrictions and to form a continuous invert through the manhole.

2.5.5 Assembly of Fabric Tube

2.5.5.1 Provide a fabric tube manufactured of one or more layers of absorbent non-woven felt fabric, felt fiberglass composite or fiberglass and meet the requirements of ASTM F1216, ASTM F1743, ASTM D5813, and ASTM F2019 that is capable of absorbing and carrying resins, constructed to withstand installation pressures and curing temperatures and have sufficient strength to bridge missing pipe segments, and stretch to fit irregular pipe sections.

Submit certified information from the felt manufacture of the nominal void volume in the fabric tube that will be filled with resin.

2.5.5.2 The wet-out fabric tube is to have a uniform thickness and excess resin distribution that, when compressed at installation pressures, will meet or exceed the design thickness after cure.

2.5.5.3 Manufacture the fabric tube to a size and length that when installed will tightly fit the internal circumference of the host pipe. Allowance for circumferential stretching during installation. Size the tube to the diameter of the existing pipe and the length to be rehabilitated, and be able to stretch to fit irregular pipe sections and negotiate bends. Prior to ordering, measure in the field the minimum tube length necessary to effectively span the designated run between manholes to ensure that the tube will have sufficient length to extend the entire length of the run. Measure the inside diameter of the existing pipelines in the field prior to ordering liner so that the liner can be installed in a tight-fitted condition.

2.5.5.4 Coat the outside or inside layer of the fabric tube (before inversion or pull-in, as applicable) with an impermeable, flexible membrane that contains the resin and facilitates, if applicable, vacuum impregnation and monitoring of the resin saturation during the resin impregnation (wet out) procedure.

2.5.5.5 Do not include material in the fabric tube that may cause delamination in the cured CIPP.

Dry or unsaturated layers are not acceptable upon visual inspection as evident by color contrast between the tube fabric and the active resin containing a colorant.

2.5.5.6 Use a light reflective interior pipe surface color so that a clear detailed examination of the CIPP can be made with closed circuit television inspection equipment. Provide a hue of the color dark enough to distinguish a contrast between the fully resin saturated felt fabric and dry or resin lean areas.

2.5.5.7 When seams in the fabric are required, sew them so that the seams are stronger than unseamed felt.

2.5.5.8 Spirally form and sew where the length requires joining.

2.5.5.9 Mark the outside of the fabric tube every 5 feet with the name of the manufacturer or CIPP system, manufacturing lot and production footage.

2.5.5.10 The Contractor shall determine the minimum length of the fabric tube to effectively span the distance from the starting manhole to the terminating manhole or access point, plus that amount required to run-in and run-out for the installation process.

2.5.5.11 As a minimum, provide the fabric tube wall thickness manufactured to the nearest 0.02 in increment, rounded up from the design thickness for that section of installed CIPP. Wall thickness transitions, in 0.02 in increments or greater as appropriate, may be fabricated into the fabric tube between installation entrance and exit access points. Provide a sufficient quantity of resin used in the impregnation to entirely fill the felt voids for the nominal felt thickness.

2.5.6 Resin:

2.5.6.1 Provide a corrosion resistant polyester or vinyl ester resin and catalyst system or epoxy and hardener system that, when cured within the tube composite, meets the requirements of ASTM F1216, ASTM F1743, or ASTM F2019. The resin is to produce CIPP which will comply with or exceed the structural and chemical resistance requirements of this specification.

2.5.6.2 Provide the polyester or vinyl ester resin that is PREMIUM, NON-RECYCLED resin only. Do not use Polyethylene Terephthalate (PET) resins, or those containing fillers, additives or enhancement agents. Old resin or reworked resin is not permitted.

2.5.6.3 Do not use Quick-cure or accelerated resin systems that cure in half the specified time or substantially quicker than the minimum three hours.

2.5.6.4 Do not change resins, catalysts, resin/catalysts, or mixing ratios during this Contract unless specifically approved by the Contracting Officer in writing in advance.

2.5.6.5 Ship the resin directly from the resin manufacturer's facility to the CIPP wet-out facility. Submit copies of the shipping documents from the resin manufacturer to the Contracting Officer showing dates of shipment, the originating location and the receiving location.

2.5.6.6 Use the resin to manufacture the CIPP as shipped. Do not add fillers or additives at the wet-out facility except for the required catalyst.

2.5.6.7 Apply the resin to the felt tubing (wet-out) under factory conditions. Protect the materials against ultraviolet (UV) light, excessive heat and contamination at all times.

2.5.7 Materials: Submittal Required

2.5.7.1 Manufacturer's Technology Data:

2.5.7.2 Submit manufacturer's technology data for FFP CIPP products and associated technologies.

2.5.7.3 Include infrared spectrum (IR) analysis for proposed resin and confirmation that the resins meet ASTM D5813.

The IR analyses will be used to verify that the resin and the resin catalyst composition and mixture being used is the approved resin and resin catalyst system.

2.5.7.4 Submit results of IR analyses of the proposed resin and resin catalyst mixture, performed and certified by the resin manufacturer, prior to manufacturing CIPP.

2.5.7.5 The results of these analyses (the resin's chemical fingerprint) will be used as the standard for verifying the resin and resin catalyst mixture being used throughout construction.

2.5.8 Manufacturing Certifications: Submittal Required.

Submit manufacturing certifications that the CIPP was manufactured in accordance with these specifications and ASTM D5813 with each shipment. The certifications are to include:

A signed statement by the wet-out manager/supervisor that no fillers were added to the resin system during manufacture of the CIPP.

Wet-out forms documenting the wet-out for each section of CIPP manufactured without delay or claim to any confidentiality.

The wet-out forms are to document the date and time of wet-out, the wet-out supervisor, the wet-out facility address, the location where the CIPP will be installed (by work order and manhole numbers), the CIPP diameter, the length of wet-tube and dry-tube, the thickness of the CIPP, the roller gap setting for establishing the liner thickness, the felt manufacturer, the resin used (by product name and batch or shipment number) and quantity, the catalyst(s) used (by product name) and quantity, quality control samples taken, and other information pertinent to the wet-out process.

2.5.9 Catalyst: Submittal Required.

Catalyst product data and quantity. Include a Certificate of Authenticity from the resin manufacturer for each shipment to the wet-out facility as part of the Catalyst product data submittal. Include the date of manufacture and the Heat Distortion Temperature.

2.5.10 Raw Resin Data:

Submit Raw Resin Data, including the manufacturer and description of product components.

2.5.11 Flexible Membrane:

Submit product data for the Flexible Membrane (coating) material including the manufacturer's recommended repair (patching) procedure.

2.5.12 Lubricant:

Submit detailed description of the lubricant proposed for the insertion or inversion process.

Ensure that the lubricant is compatible with the wastewater treatment plant operations and pre-treatment program.

2.5.13 Resin Dye:

Submit certification that the Resin Dye quantity and type is compatible with the components of the lining system.

PART 3.0 EXECUTION

3.1 PREPARATION: Submitted Required.

3.1.1 Set-Up and Sequence:

Submit a Sequence of Liner Installation plan. Include proposed set-up locations in the plan that are coordinated with the Traffic Control Plan, refer to para 1.7.9 above.

3.1.2 CLEANING OF PIPE LINES:

Clean/water jet all sanitary sewer pipelines.

Remove internal debris from the existing pipe line that will interfere with the installation of the liner as required in these specifications. For additional information, refer to para 3.4.

Legally dispose of solid debris and deposits removed from the system. Moving solid material from manhole section to manhole section is not permitted.

As applicable, either plug the pipe to be cleaned, or install a flow bypass pumping system to facilitate the proper cleaning the pipe lines. Immediately clean up raw sewage spills caused by the Contractor's operations and disinfect the spill area using methods and materials approved by the Contracting Officer. In the event of a spill, notify the Contracting Officer immediately and take appropriate actions to stop and contain the spill.

Exercise care and caution in the use of cleaning equipment in order to avoid damage to the existing pipe.

Provide backflow prevention on fire hydrants if used to obtain water as required for temporary utilities.

3.1.3 Bypassing Existing Sewage Flows: Submittal Required

Provide for the flow of existing mainline and service connection effluent around the section or sections of pipe designated for liner installation.

Plug service connections only after proper notification to the Contracting Officer. Service connections are not to remain plugged overnight.

Begin work after plugs or a sewage bypass system and pumping facilities have been installed and tested under full operating conditions, including the bypass of mainline and side sewer flows.

Once the lining process has begun, maintain existing sewage flows until the resin/felt tube composite is fully cured, cooled down, fully televised and the CIPP ends finished.

Coordinate sewer bypass and flow interruptions with the Contracting Officer at least 14 days in advance.

Provide pump(s) and bypass line(s) of adequate capacity and size to handle peak flows.

Submit a detail of the sewer bypass plan to the Contracting Officer before proceeding with liner installation. To include written description of plan and addressing quantity, capacity, and location of pumping equipment. Submit spill plan to address any spills that might occur.

3.1.4 PRE-TV INSPECTION: Submittal Required

Perform cleaning Pre-TV video inspections of the pipelines. PACP certified personnel are to perform the TV inspection.

Flush (water jet) and clean pipeline interiors to remove sludge, dirt, sand, stone, grease, and other materials from pipe to ensure clear view interior conditions.

Intercept flushed debris at next downstream manhole by use of weir or screening device, remove, and dispose of debris off-site.

Submit the Pre-TV videos on CD or DVD and corresponding written logs prior to installation of the liner and for later reference by the Contracting Officer.

Submit cleaning and inspection logs for each section of sewer line to be rehabilitated. Include the following as minimum information: stationing and location of lateral services, wyes or tees, pipe joints, infiltration/inflow defects, cracks, leaks, offset joints, and other information required to assess condition of the sewer.

3.1.5 LINE OBSTRUCTIONS:

Using water jetting, flush and remove obstructions as required. Immediately notify the Contracting Officer of any obstructions or blockages that cannot be removed by water jetting.

Immediately notify the Contracting Officer of any misalignments, broken or collapsed sections and sags that will prohibit the installation or will interfere with the long-term performance of the lining materials by performing a point repair.

3.1.6 LATERAL LOCATIONS:

Confirm the locations of branch service connections prior to installing and curing the liner material.

3.2 INSTALLATION OF CIPP LINER: Submittal Required

Prior to the installation of the liner, place temperature sensors in the host pipe in order to monitor the temperature of the liner wall and to verify correct curing. Place temperature sensors between the host pipe and the liner in the bottom of the host pipe (invert) throughout its length and monitor the temperature on the outside of the liner during the curing process.

Place the temperature sensors at intervals as indicated in the sensor manufacturer's written specifications. Place additional sensors where significant heat sinks are likely or anticipated.

Monitor the sensors by a computer using a tamper proof data base that is capable of recording temperatures at the interface of the liner and the host pipe.

Install the liner in accordance with ASTM F1216 and ASTM F1743 with the following modification: Position the wet-out tube in the pipeline using the method indicated in the manufacturer's instructions. Do not damage the tube as a result of installation.

Pull-in or invert through an existing manhole or access point and fully extend to the next manhole or termination point.

Install and cure the CIPP Liner in the host pipe as indicated in the manufacturer's specifications and as described in the approved submittals.

Accomplish curing by utilizing the medium in accordance with the cure schedule.

Continuously monitor the curing source, or input and output temperatures and log the temperatures during the cure cycles. Use the manufacturer's recommended cure method and schedule for each line segment installed. Take the liner wall thickness and the existing ground conditions with regard to temperature, moisture level, and thermal conductivity of soil into account during the curing process.

For heat cured liners, if one or more temperature sensor(s) do not reach the temperature as specified by the manufacturer to achieve proper curing or cooling, the Contractor will make necessary adjustments to comply with the manufacturer's specifications.

Compile and submit Curing Logs from the system computer that specifically identifies each installed sensor station in the length of pipe, indicates the maximum temperature achieved and the sustained temperature time. Each sensor is to record both the maximum temperature and the minimum cool down temperature and comply with the manufacturer's written product data.

For UV Cured Liners, record all light train sensor readings along the entire length of the installed liner into a tamper proof computer. Follow the cure procedure in accordance with the manufacturer's written product data.

3.3 INSTALLATION OF FFP LINER:

Install and process the FFP in the host pipe according to these specifications, ASTM F1867 and the manufacturer's specifications.

Prior to installation of the FFP liner, place temperature sensors in the host pipe to monitor the temperatures during the processing of the FFP. Monitor and log temperatures during processing and cool down. Submit temperature logs.

Position the FFP in the pipeline using the method specified by the manufacturer. Pull-in the FFP through an existing manhole or access point and fully extend the FFP liner to the next designated manhole or termination point.

Complete the processing of the FFP by utilizing the appropriate medium in accordance with the manufacturer's instructions. Use ASTM F1867 and the manufacturer's recommended processing procedure for each line segment installed.

Consider the FFP wall thickness and the existing ground conditions with regard to temperature, moisture level, and thermal conductivity of the host pipe and soil, during the installation of the FFP. Adjust pressures according to site conditions to ensure a tight expansion out against the host pipe.

3.4 DISPOSAL OF SUPERHEATED WATER:

Submit a procedure for the disposal of superheated water for approval by the Contracting Officer.

3.5 COOL DOWN:

Cool the FFP CIPP in accordance with the approved FFP CIPP product specifications.

Monitor and record temperatures and curing data throughout the installation process to ensure that each phase of the process is achieved in accordance with the FFP CIPP system product specifications.

3.6 CURING LOGS:

Submit completed curing logs for each pipe segment.

3.7 FINISH (CIPP):

Provide CIPP that is continuous over the entire length of a sewer line section, is free from visual defects such as foreign inclusions, dry spots, pinholes, major wrinkles and de-lamination, and is impervious and free of leakage from the pipe to the surrounding ground or from the ground to inside the lined pipe.

Repair defects in accordance with the Repair or Replacement Procedures which may affect the structural integrity or strength of the linings.

Seal the beginning and end of the CIPP to the existing host pipe utilizing a hydrophilic end sealing material compatible with the existing (HOST) pipe and the liner.

Provide water tight service connections.

3.8 FINISH (FFP):

Provide FFP that is fully expanded and continuous over the entire length of a sewer line section, is free from visual defects such as foreign inclusions, dry spots, pinholes, major wrinkles, is impervious and free of any leakage from the pipe to the surrounding ground or from the ground to inside the lined pipe.

Repair any defect, in accordance with the Repair or Replacement Procedures which may affect the structural integrity or strength of the linings.

Seal the beginning and end of the FFP to the existing host pipe using a hydrophilic end sealing material compatible with the existing (host) pipe and the FFP.

Provide watertight service connections.

If the wall of the FFP leaks, remove and replace the section of FFP with a watertight pipe.

3.9 FIELD QUALITY CONTROL:

All costs for the collection, transportation and testing of samples are the responsibility of the Contractor.

3.10 Testing of Installed FFP: Submittal Required

3.10.1.1 Verify the physical properties of the installed FFP through field sampling and laboratory testing. Submit FFP Samples for testing to the Contracting Officer by a qualified, independent laboratory that specializes in material testing; testing shall be at the Contractor's expense.

Test in accordance with ASTM F1871 and ASTM F1504 test methods to confirm compliance with the requirements specified in these Contract documents.

3.10.1.2 Submit FFP liner sample test results.

3.10.1.3 Chemical resistance - The FFP system installed is to meet the chemical resistance requirements for a typical domestic sewage environment. Use materials proposed for actual construction for FFP testing.

3.10.1.4 Maintain the hydraulic capacity as large as possible. At a minimum the installed FFP is to equal the full flow capacity of the original pipe before rehabilitation. Measure the installed FFP thickness for each line section installed. Use non-destructive methods for confirming the thickness of the installed FFP.

Remove the FFP if the FFP thickness does not meet the specified Contract requirements. The FFP thickness has a tolerance of minus 5 percent and plus 10 percent.

3.11 Testing of Installed CIPP: Submittal required.

3.11.1.1 Verify the physical properties of the installed CIPP through field sampling and laboratory testing. Submit CIPP Liner Samples for testing by an independent third party laboratory. Test in accordance with ASTM F1216, ASTM F1743, and ASTM D5813 for chemical resistance. Test methods to confirm compliance with the requirements specified in these Contract documents.

3.11.1.2 Collect samples from the actual installed CIPP liner. At a minimum, one sample for each size of CIPP Liner installed.

3.11.1.3 Cut the samples from a section of cured CIPP that has been inverted or pulled through a like diameter pipe which has been held in place by a heat sink, such as sandbags.

3.11.1.4 Process, cut, and label test samples in the presence of the Contracting Officer.

Immediately package the samples in a pre-addressed, postage paid, pre-labeled, unsealed packing, addressed for delivery to the testing laboratory. Seal packages in the presence of the Contracting Officer; and ship or transport to the testing lab.

3.11.1.5 Submit CIPP liner sample test results.

3.12 RECONNECTIONS OF EXISTING SERVICES:

Make reconnections of existing services after the liner has been installed, fully cured, and cooled down.

Make external reconnections with a tee fitting in accordance with the lining system manufacturer's written specifications. Seat and seal saddle connections to the new CIPP using grout or resin compatible with the CIPP. FFP following manufacturer's specifications.

Utilize a CCTV camera and remote cutting tool for internal reconnections. The machined opening must be at least 90 percent of the service connection opening and the bottom of both openings are required to match. The opening cannot be more than 100 percent of the service connection opening. Smooth the edges of the opening and remove pipe or liner fragments, which may obstruct flow or snag debris. Cut the invert of the sewer connection flush with the invert entering the mainline.

Collect coupons of pipe material resulting from service tap cutting at the next manhole downstream of the pipe rehabilitation operation prior to leaving the site. Account for all pipe coupons and do not allow them to pass through the system.

3.13 POST-TV INSPECTION: Submittal Required

Perform a detailed closed-circuit Post-TV inspection in the presence of the Contracting Officer after installation of the liner and reconnection of the side/lateral sewers. Utilize a radial view (pan and tilt) TV camera.

A post-TV video inspection is to confirm that the finished liner is continuous over the entire length of the installation, free of significant visual defects, damage, deflection, holes, leaks and other defects. Submit unedited digital video documentation of the inspection (Post-TV video inspection) to the Contracting Officer within 10 working days of the liner installation.

Include the following data on the Post-TV video: Inspection date, manhole identification numbers, size of pipe, direction of flow, location of reconnected side sewers, debris, as well as defects in the liner, such as gouges, cracks, bumps, or bulges.

Clean the newly installed liner removing accumulated debris and build-up immediately prior to conducting the Post-TV inspection.

3.14 REPAIR OF CIPP DEFECTS: Submittal Required.

Locate and succinctly define/identify defects in the installed CIPP that could affect the operation and long term life of the product.

Locate and succinctly define/identify repairable defects that occur in the installed CIPP based on approved product specifications, including a detailed step-by-step repair procedure.

Clearly locate and define un-repairable defects in the CIPP based on the approved product specifications, including a recommended procedure for the removal and replacement of the

CIPP.

Re-TV repairs to CIPP.

3.15 REPAIR OF FFP DEFECTS: Submittal Required.

Repair or replace any defects which, in the judgment of the Contracting Officer, will affect the integrity or strength of the lining. Prior to the repair of defective work, submit a Shop Drawing indicating the FFP Repair Method. Provide field or workshop demonstration of the method of repair if requested by the Contracting Officer. Make the repairs in full compliance with the FFP manufacturer's specifications. Re-TV repairs to FFP.

3.16 SITE CLEANUP:

Cleanup and restore existing surface conditions and structures. Repair any of the FFP system determined to be defective. Schedule cleanup in a manner to cause the least possible obstruction and inconvenience to traffic, pedestrians, and property occupants.

3.17 CLOSEOUT ACTIVITIES: Submittal Required

3.17.1 Demonstration: Complete Post-TV inspections and repairs to the installed liner before acceptance. Complete Pre-TV, Post-TV, and Re-TV inspections as described in this Statement of Work.

Submit post installation inspection documentation within 10 working days of the liner installation.

3.17.2 Submit as-built drawings for the portions of the sanitary sewer system that were rehabilitated showing complete detail with dimensions, both above and below grade, including invert elevations at the manholes.

Include the identification of the work completed on one set of Contract Drawings. Keep legible as-built drawings on the project site at times and maintain them as the work progresses.

Continuously update the…