Q A 10 Apr 08.doc

DOC document 26 KB Posted

Attached to
Simplified Acquisition of Base Engineer Requirements (SABER) IDIQ
Solicitation number
FA3030-08-R-0003
Issued by

About this file

Questions and Answers for 10 Apr 08

View the file

Other files

File Type Posted
Site Visit Meeting Minutes 4 Apr 08.pdf PDF
Attachment4-TX51Building.doc DOC document
FA3030-08-R-0003.doc DOC document
Attachment7-Specifications.doc DOC document
Attachment6-PastPerformanceQuestionnaire.doc DOC document
Attachment1-SampleInsuranceCert.doc DOC document
Attachment2-TX50Residential.doc DOC document
Attachment5-SFLLL.pdf PDF
Attachment3-TX28HeavyandHighway.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Simplified Acquisiton of Base Engineer Requirements (SABER) Solicitiation: FA3030-08-R-0003

Subject: Questions and Answers

Date: 10 Apr 08

Question 1: In Tabe 1 Proposal Organization – Volume II is the Cost/Price Proposal. However, in Table 1 it lists Section B – Bid Schedule to be placed in Volume I (Chapter 2). Does the bid schedule go in Volume I or Volume II?

Answer 1: The bid schedule is to be placed in Volume I. Volume I consists of a complete solicitation package which is comprised of the SF1442, Section B – Bid Schedule, Representations and Certifications – Section K, SF LLL, and the Completed Insurance Certificate. The bid schedule is also used as a quick reference for general overviews of offeror’s proposed coefficients.

Question 2: In Table 1 Proposal Organization – Volume II Cost/Price – states a 30 page limit. If Section B does in fact belong in this Volume, does the 30 page limit include the 22 pages for Section B? That would only leave 8 pages for all other documentation.

Answer 2: Since Section B- Bid Schedule is still required to be submitted with Volume I, the 30 page limit of the price proposal, Volume II, still applies.

Question 3: In Table 1 Proposal Organization, it indicates Original plus 4 copies of Volume II – Cost/Price. However, the text under “Price Proposal” indicates original and two copies, plus an electronic copy of documents submitted, including Schedule B. Please advise how many copies are required of Volume II.

Answer 3: In order to follow suit of the other volumes being submitted under Table 1, the Price Proposal should be submitted with the Original + 4 copies.

Question 4: Pre-Proposal Minutes reflect an incorrect date for the deadline for questions of 25 April 06.

Answer 4: The date of 25 April 06 is listed under the heading of “3. The following questions were previously asked at the site visit for the current contract FA3030-06-D-0001”. This list of questions and answers were listed to provide additional information to prospective offerors to help in the preparation of proposals.