B836 RFIS Answered.pdf

PDF 43 KB Posted

Attached to
B836 Replace Electrical in Airfield Lighting Vault
Solicitation number
FA302226R0021
Issued by

About this file

This document is a Requests for Information (RFI) and Answers file for federal contract B836, addressing clarifications on project execution and electrical work requirements.

Staffing and Planning Requirements: The superintendent and QAQC roles must be fulfilled by two separate individuals. General QA/QC and safety plans are acceptable; contract-specific plans are not required. The project is not tax exempt. Electrical and Airfield Operations: CAD files for the Airfield Vault building are available. Electrical outages are permitted during overnight hours (non-night flying) and weekends/federal holidays with advanced coordination, with schedules published weekly; one week per month the base operates night flying. The contractor must provide fault current calculations, an arc flash study, and label all new panels accordingly. Phase rotation and load balancing surveys are required, but peak demand determination for the service and individual panels is not. Megger testing is limited to circuitry within the vault and directly associated with the scope of work; airfield circuitry exiting the vault is excluded. Site Operations: Contractors may place a small non-roll-off dumpster next to the vault on the flight line, provided it is covered. The contractor is responsible for all material remaining in the dumpster.

View the file

Other files

File Type Posted
Solicitation Amendment FA302226R00210001 SF 30 CO Signed.pdf PDF
Appendix A Cost Breakdown.xlsx XLSX spreadsheet
Site Visit Sign in Sheet.pdf PDF
CUI Contractor Training Slides.pptx PPTX presentation
EAL Form.pdf PDF
18 May Wage Determination.pdf PDF
Solicitation - FA302226R0021.pdf PDF
30 May Statement of Work.pdf PDF
CUI Contractor Training Acknowledgment July 2024.pdf PDF
AF Form 66.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B836 RFIs

1. In executing this project, can one superintendent fulfill the supervision, safety, and QAQC roles?

The superintendent and QAQC roles are required to be two separate individuals.

2. Are contractors required to issue a contract specific QA/QC Plan?

General QA/QC plan is acceptable for this project.

3. Are contractors required to issue a contract specific Safety Plan?

General safety plan is acceptable.

4. Is this project tax exempt?

No

5. Are CAD files available for Airfield Vault building?

Available files attached.

6. Please confirm/revise the following guidance provided during the pre-bid site visit for typical electrical/airfield lighting outage times. The airfield operates on a regular schedule, and is not typically 24 hours per day. Subject to specific approval, outages will typically be allowed during overnight hours, and on entire weekends. Weekends with a federal holiday occurring on a Friday or Monday provide an opportunity for an extended outage.

The hours are determined week to week in a published schedule. 1 week per month the base operates night flying. Outages will typically be allowed during overnight hours (non night flying) and on weekends/federal holidays with advanced coordination.

1. Along with the fault current calculations, will the contractor be required to provide an Arc Flash Study, and label all new panels accordingly?

Yes the contractor shall provide an arc flash study and label all panels accordingly.

2. Along with the survey to determine phase rotation and load balancing, will the contractor be required to determine peak demand for the service and for each panel to be replaced?

The contractor will not be required to determine peak demand for the service and each panel.

B836 RFIs

3. Is the megger testing requested in the SOW limited to the circuitry within the vault and directly associated with the scope of work? Is the airfield circuitry exiting the vault excluded from megger testing?

It is limited to within the vault, the circuitry existing the vault is excluded.

4. Will the contractor be allowed to place a small dumpster (non roll-off) next to the vault?

Yes, the dumpster must be covered since it is on the flight line. The contractor shall be responsible for all material remaining in the dumpster.