Questions and Answers.docx_safe.docx

DOCX document 22 KB Posted

Attached to
Safety Office Furniture
Solicitation number
FA301624Q0101
Issued by

About this file

This document contains Questions and Answers related to a federal contract opportunity for Safety Office Furniture at JBSA Lackland, TX. The solicitation number is FA301624Q0101 and the contract will be awarded by the Department of the Air Force, Air Education and Training Command.

The key details are:

  • The contract is for the design and installation of office furniture
  • There are 11 questions and responses covering topics such as drawings, floor location, delivery logistics, electrical/data requirements, and existing furniture removal
  • The government provided clarification on the furniture specifications, noting an attachment titled "37 TRW Safety Office Furniture, Salient Characteristics"
  • The government indicated an alternate manufacturer similar to the one specified in the solicitation can be quoted
  • The solicitation cut-off date for contractor questions is 10:00 AM CST on July 11, 2024

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

502 CONS/JBKAEFA301624Q0101
JBSA Lackland, TXSafety Office Furniture

QUESTIONS & ANSWERS: Cut-off date for contractor questions is 10:00 AM CST, 11 July 24.

Question 1: Can you please provide Attachment 2, 737 TRG IT and Scheduling Section Office Presentation

Government Response: N/A

Question 2: Can you please provide and drawings available for the office spaces and breakroom, preferably in AutoCAD format if available.

Government Response: Attached, AutoCad unavailable, refer to document B2484_Basement_Floor_Plan_with_Room_Numbers_jyd'_20220414 Question 3: What floor(s) is this installation on?

Government Response: Basement floor Question 4: Approximately how far is it from the truck offload site to the install location?

Government Response: 250 feet Question 5: Are there any stairs that the product will need to go up or down to reach the install location?.

Government Response: There are stairs but there is an elevator.

Question 6: Will we use a passenger or freight elevator for delivery to the install location?

Government Response: See answer 5 Question 7: Are any electrical or data cabling services required by the contractor, or will the Government be providing those services with the contractor provided parts?

Government Response: No Question 8: Do we need to provide an electrician to attach the systems furniture to building power? If so, do we need to pull new circuits from the electrical panel or will we attach to existing power at walls/columns?

Government Response: No Question 9: Regarding the existing product that needs removal/disposal, what is the quantity and type of furniture needing to be removed/disposed of? Will it all fit in the dumpster(s) provided.

Government Response: None, only trash you generate from installing furniture.

Question 10: Please provide further description of furniture listed only with manufacturer specific terms. “ H-A-Mech”, “HA L Taper Pen”, “H-A-L Shaped Worksurface”, “20” D-Low Secondary Desk”… Government Response: See attachment, 37 TRW Safety Office Furniture, Salient Characteristics

Question 11: What manufacturer is used for the solicitation? Can an alternate manufacturer, similar to this be quoted?

Government Response: Workspace Solutions