This document provides questions and answers to an amendment for Request for Quote FA301622U0086 for Nurse Residency Program Services from the 502d Contracting Squadron at Joint Base San Antonio Lackland. The amendment clarifies that the successful contractor must provide an all-inclusive nurse residency program curriculum that is already developed for that purpose. It also makes minor administrative changes to the evaluation criteria to reference nurse residency program services rather than continuing education operations. The amendment requires that past performance examples provided by offerors must be relevant to the efforts described in the performance work statement for providing nurse residency program services.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

502d Contracting Squadron

Question and Answers

Request for Quote # FA301622U0086

Amendment 1

Nurse Residency Program Services

Joint Base San Antonio (JBSA) Lackland

16 May 2022

TITLE: The purpose of this Amendment to RFQ FA301622U0086 Nurse Residency

Program Services is to provide the Governments response to vendor’s questions and to make minor administrative corrections to the RFQ.

1. Contractor Question:

We are a content solutions provider. Can the successful vendor offer independent product silos with nurse residency-applicable curricula materials that can conjunctively provide a comprehensive curricula to meet the Nurse Residency Program Service’s needs?

Government Response:

No, the contractor needs to provide a nurse residency program curriculum that is all inclusive and that is already developed for the purpose of a nurse residency program. The information in the PWS Section 1.1.1. stands as written.

2. Contractor Question:

For Volume 5 - Clauses and provisions. What is required for completion in this document? Some sections have an "X" in front of them and some have a __ in front.

Please clarify

No action required. For informational purposes only.

3. Contractor Question:

Is there a specific location to place the date/signature of the submission? Is at the end of

Volume 3 acceptable?

Reference: Submission of Quotes, page 4 of RFQ solicitation document.

Date/signature of submission can be placed at end of Volume 2 –Price (Bid Schedule).

4. Contractor Question:

Is there a specific location required to place "The offeror agrees to hold the prices in its offer firm for 60 Calendar days…" statement? Is end of volume 3 acceptable?

Reference: Volume 5 section c, page 10 of solicitation document.

Vendor can place their confirmation to hold the prices in its offer firm for 60 Calendar days at the end of Volume 2- Price (Bid Schedule).

5. Reference RFQ FA301622U0086 Nurse Residency Program Services - the following

Administrative changes are made:

See Page 15 Section: 5. Evaluation Process D. FACTOR 3 – TECHNICAL

APPROACH.

Change as follows:

FROM:

D. FACTOR 3- TECHNICAL APPROACH: The criteria for Factor 3 has been met when the quoter adequately demonstrates a sound, comprehensive, realistic, effective, and efficient technical approach to provide and manage the appropriate qualified workforce to achieve consistent and efficient operations in accordance with the entire scope of the requirements of the PWS with no disruption in current

CPE operations. At a minimum, the plan shall include all of the following:

TO:

D. FACTOR 3- TECHNICAL APPROACH: The criteria for Factor 3 has been met when the quoter adequately demonstrates a sound, comprehensive, realistic, effective, and efficient technical approach to provide and manage the appropriate qualified workforce to achieve consistent and efficient operations in accordance with the entire scope of the requirements of the PWS with no disruption in current

NRP services. At a minimum, the plan shall include all of the following:

6. Reference Attachment 4- Past Performance Reference List.

The following notation has been added at the bottom of the table:

Past Performance Reference list needs to reflect contracts awarded that are categorized within the same performance efforts as stated within the PWS (Attachment -1).