B2250 Site Visit QA.docx

DOCX document 12 KB Posted

Attached to
Stabilize Lead-Based Paint Building 2250 Federal contract opportunity
Solicitation number
FA301621Q0126
Issued by
Department of the Air Force Air Education and Training Command

View the file

Other files for this federal contract opportunity

Other files attached to Stabilize Lead-Based Paint Building 2250, newest first.
File Type Posted
FP_JBSF-2250-3.pdf PDF
FP_JBSF-2250-2.pdf PDF
Solicitation Amendment FA301621Q01260001 SF 30.pdf PDF
SOW Stabilize Lead-Based Paint Building 2250.pdf PDF
JBSF02250 - JBSA LBP Containing Materials Inventory Report.pdf PDF
Environmental_Spec_01 57 20.pdf PDF
FP_JBSF-2250-1.pdf PDF
Solicitation Amendment - FA301621Q01260001 Conformed Copy.pdf PDF
Atch 3 Unescorted Access Request Form.pdf PDF
Atch 5 Contractor Responsibility Questionnaire B2250.docx DOCX document
Atch 2 Wage Determination Rev 14.pdf PDF
Atch 6 HAZMAT Letter_B2250.docx DOCX document
Atch 4 Financial Information Questionnaire B2250.docx DOCX document
SOW Capsulate Lead Paint Bldg 2250.pdf PDF
Solicitation - FA301621Q0126.pdf PDF
Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

B2250 Joint Base San Antonio - Fort Sam Houston, Texas Site Visit Questions & Answers

1. How can we obtain a copy of the lead survey?

Attached: JBSA LBP Containing Materials Inventory Report

2. Where are the quantities listed; we cannot locate them in the SOW?

Attached: JBSF-2250–1, JBSF-2250–2, JBSF-2250–3

3. On the second level, the green areas and white soffit appear to have already been abated and/or encapsulated. Please clarify if these areas are included in the SOW.

The SOW covers the entire building.

4. Are there building measurements available?

Facility Height- 42’ Facility Length- 146’ Facility Width- 55’

14,478 SF

5. Are any areas on top of the roof to be abated? If so, does this include any metal components (specifically which ones)?

Nothing on the roof. Gable ends of the Roofs, Soffit, Fascia, and Porch Ceilings.

6. Would it be possible to abate one side of the building at a time and personnel to use only one entrance on the opposite side of the building during each abatement?

Yes, that way the building is still operational. Signs will need to be put in place of all exit doors to the abated areas working before work begins. So no personnel use the doors. If doors can be blocked some way from the inside it be best.