RFQ FA3016-18-U-0242
Natural Beach Sand-Beach Erosion Repair (Canyon Lake)
Questions and Answers
26 July 2018
Question: Is there a preference on the equipment used to spread sand?
Answer: The government does not have a preference on what equipment is used as long as the results in the SOW are met.
Question: Can the awarded contractor who is not a DoD cardholder, reserve lodging at JBSA Canyon
Lake while contract work is underway?
Answer: No, the government does not require the awarded contractor to be on site 24 hours a day.
Question: Will BBQ grills and signs be removed prior to commencement of work?
Answer: No, the BBQ grills and signs are cemented in to the ground and will not be removed.
Question: Is there a tentative schedule for delivery of aggregate to Canyon Lake and time till completion [or no later than date] for this specific RFQ?
Answer: The schedule for completion of delivery and spreading of sand at Canyon Lake will be 30 Days after award.
Question: Can contractors provide a sample of the sand for evaluation purposes?
Answer: Yes. Please see revised Request for Quote, dated 26 Jul 18. “The contractor shall provide a miniumum two pound sample of the sand being quoted.”