Questions_and_Answers_(2).docx
DOCX document 18 KB Posted
- Attached to
- Shower and Locker Room Trailers Federal contract opportunity
- Solicitation number
- FA3016-18-U-0151
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions_and_Answers_(1).docx | DOCX document | |
| Response_to_Initial_Questions.docx | DOCX document | |
| Statement_of_Work_-_Shower_Trailers.pdf | ||
| Questions_and_Answers_Template_(Q_&_A).docx | DOCX document | |
| FBO_Attachment_Redacted.pdf | ||
| RFQ_-_Shower_Trailers.pdf | ||
| Lackland_AFB_MAP.pdf | ||
| Short_Term_Pass_Request_Format.docx | DOCX document | |
| Salient_Characteristics_for_Shower_Trailers.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
| 502 CONS/JBKAE | FA3016-18-U-0151 |
| JBSA Lackland, TX | Shower and Locker Rm Trailers |
QUESTIONS & ANSWERS: Cut off date for contractor questions is 2:00 pm CDT, May 18, 2018. Questions 1 - 10
Question 1: Is there a preference to have gender entrance opposite each side for entry/exit of trailers?
Government Response: If doors are on the length of the trailer (per the submitted diagram), customer recommends having doors open outwards away from each other (hinges are on inside of each door, closest to each other). The intent was to have the doors and stairway on the length of the trailer, in order to maximize the changing space that is separate from the showers.
Question 2: Is there a preference to have secondary water source tank for fresh water storage? If so, what are the specs? Per the standard equipment requirement listed Grey/Black Combo Waste Tank 1600 gal
Government Response: A secondary tank for fresh water storage is not required, as the trailers will be connected to the building water supply. The waste tank will either be directly connected to the sewer line or the trailers
Question 3: Will they need the trailers before September?
Government Response: Trailers are desired as soon as possible, as summer is the prime season f/exposure to high temperatures. The lack of an effective changing room or showers is a constant impact on welfare and morale of personnel. The initial intended date of receipt was NLT 30 May 18. Based on the current timelines, delivery is desired immediately upon completion and certification of construction to specifications.