Repair/Replace Roof at, Building 6 TYMX18A318

Section 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals Salvage Plan; G

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work consists of exterior surface improvements at Hangar 6, the project includes the removal of existing paint on glass sections on the northern and south elevations, painting and sealing all windows, and the painting of concrete and aluminum surfaces on all four elevations of the building.

1.2.1.2 New Work

All new work produced by the contractor shall comply with UFC 1-200-01 "General Building Requirements", UFC 3-190-06 "Protective Coatings and Paints", the "Joint Base San Antonio Lackland Installation Facilities Standards", JBSA Environmental Specifications, and any other applicable Federal, State, or local regulations as required.

1. Contractor shall pull all required TCEQ Toxic permits, air quality permits and Hazardous materials permits to be in compliance with State and Federal regulations prior to starting work.

2. Contractor shall cordon off work area. Contractor shall ensure no Foreign Object Debris (FOD) is released from B6 on to the airfield or allowed to enter into any storm or industrial drains. All drains will be covered to prevent the entry of any debris that may be released from the hangar.

3. Contractor shall lay down plastic liner within work area to prevent infiltration of dust.

4. Contractor shall implement the wet scrape method utilizing a surfactant to remove any loose and flaking paint on the North and South walls/ sides of the building (Hanger 6) in compliance with State and Federal regulations.

The window areas to be wet-scraped on the North and South walls are approximately 2,000 SF each. The East and West sides will not require abatement. Two sides of the building are concrete and aluminum;

approximately 12,000 SF total for both sides. The remaining two sides of

Section 01 11 00 Page 2 the building are comprised of windows; approximately 8,000 SF for both sides. Power washing is not authorized.

5. Contractor shall periodically and throughout the day, vacuum entire work with HEPA vacuum area to pick up paint chips and dust.

6. Contractor shall dispose of lead based material and chips in accordance with State and Federal regulations.

7. Contractor shall ensure area to be painted is free of dust and existing paint chips prior to beginning new work.

8. Contractor shall ensure all materials will be manifested as per the results of the Toxicity Characteristic Leaching Procedure (TCLP) to an approved landfill. A Waste profile shall be submitted to area specific JBSA Environmental Office, for review and signature, for the disposal of any Class I or II Waste by the Contractor. NOTE: The Contractor shall not sign any documentation regarding waste disposal. The Contractor shall provide an unsigned waste profile through the Contracting Officer to the area specific Environmental Office. NOTE: The Contractor shall not sign any documentation regarding waste disposal. The waste profile, if required based on the TCLP analysis, will be signed by the area specific Environmental Office.

9. Contractor shall apply one coat of acrylic primer. Thickness cannot be less than 1 mil thickness when dry.

10. Contractor shall seal all windows with sealant; approximately 1,500 LF total.

11. Contractor shall apply two coats of paint on all four sides of the building with acrylic paint. Each coat shall be allowed to dry a minimum of 8 hours. Contractor shall notify 502d CES Project Manager for inspection when first coat has been applied. After a minimum of 8 hours, 502d CES Project Manager shall be notified for inspection prior to beginning second coat of paint.

12. Contractor shall clean any spilled paint or paint markings on and around Building (Hanger) 6.

13. Contractor shall provide a safety plan, abatement work plan and a schedule to the JBSA Randolph Environmental Office and CES/CENMP Project Manager to review prior to the start of work.

14. The Contractor shall maintain the site as clean as possible, the contractor shall conduct a daily clean-up operations. At the conclusion of the project, the contractor shall clean any spilled paint or paint markings on and around Building.

15. Contractor shall ensure access to Building 6 is available at all times.

16. Contractor must be EPA- Lead-Safe certified.

The contractor is responsible for complying with all necessary federal, State and local regulations as required by JBSA Randolph. The contractor shall be responsible for all work, equipment, and labor necessary to accomplish the requirements of this SOW.

1.2.2 Location

The work is located at the 10800 E. Fifth St, Randolph AFB, TX, approximately as indicated. The exact location will be shown by the Contracting Officer. Hangar 6 is located in the vicinity of an active airfield, any work that could potentially affect airfield operations must be coordinated with all applicable parties as required. NOTE: Prior to entering the airfield area, the Contractor must attend a one day airfield training provided by the government to obtain an airfield license. Training will be coordinated after award.

Section 01 11 00 Page 3

Hangar 6 is considered to be part of the Randolph Historic District, the contractor shall take careful consideration of the building and the general vicinity while preforming work, selecting building component replacements, and any other incidental events. The State Historic Preservation Officer and Cultural Resources Managers will be kept abreast by the CES Project Manager of any issues as required. If there are any SHPO or CRM related questions the contractor shall inform the CES Project Manager.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Before work is started, arrange with the Contracting Officer Representative a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways. Please notify the CES Project Manager if any relocation or movement of personnel will be required.

[1.4 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the CES Project Manager. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

Section 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

11/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section01 33

00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contract Personnel; G

Installation Access

1.2 SPECIAL SCHEDULING REQUIREMENTS

All medical and mission critical areas will remain in operation during the entire construction period. The contractor shall conduct his operations so as to cause the least possible interference with normal operations of the activity.

Permission to interrupt any Activity roads, railroads, and/or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and cleared for such entry. Mark all Contractor equipment for identification

1.3.1.1 Not Used

1.3.1.2 Installation Access

Non DOD persons (Contractors, vendors, etc) requiring entry to JBSA installations shall be sponsored by an authorized DBIDS registered DOD ID card holder.

Sponsors must notify the Security Forces Visitor Control Center for the installation that access is required no later than 10 days prior to the requested entry date. Sponsors or Authorizing Official must request the permit in writing or via email from a .mil address to the Visitor Control Center. Contractor and vendor companies requiring access to Joint Base San

Section 01 14 00 Page 2

Antonio shall provide the credential information for their employees to the sponsor in order to process the access.

All construction contractor employees shall have:

a. One form of picture identification

b. Provide personal (full name, date of birth, home address, and driver license number) and vehicle information.

1.3.1.3 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines.

1.3.1.4 Government Housing Areas

a. Haul routes to and from constructions sites cannot go through the housing, residential areas.

b. When working inside a housing area, working hours are limited to 0800 (8 am) to 1600 (4 pm) unless otherwise approved by the Contracting Officer.

1.3.2 Emergency Response Requirement

Contractors reporting an emergency should provide the 9-1-1 dispatcher with the following information:

a. Building number, address or general location

b. Name

c. Phone number

d. Emergency information (cause of fire, explosion, natural gas leak, injuries, etc.)

e. Please, do not hang up the phone until directed by the 9-1-1 dispatcher.

IMPORTANT: If calling 9-1-1 from a mobile phone on any JBSA location you will be directed to the local 9-1-1 dispatcher. Advise the local dispatcher of your location (JBSA-Fort Sam Houston, JBSA-Lackland or JBSA-Randolph).

Immediately the local dispatcher will transfer the 9-1-1 phone call to a JBSA emergency dispatcher.

1.3.3 Not Used.

1.3.4 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 14 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours.

Section 01 14 00 Page 3

1.3.5 Permits and Requests

All permit requests must include at minimum the following:

a. Site Map (8" x 11" or 8" x 14") 5 complete copies

b. Project Name and Number

c. Contractor & Subcontractor Name

d. Brief Description of Work - Identify all buildings and/or facilities possibly affected.

e. Desired Date for Work to Begin

f. Estimated Duration of Work

g. Contractor's Representative Contact Information

1.3.5.1 Road Closure Approval Requests

a. Road closings will not be permitted without approval. To get approval for a proposed road closure contractor shall submit a traffic control plan to the 502 CES Construction manager prior to anticipated need for closure

b. The Contractor traffic control plan will include each section of road that will be worked on or impacted as a result of this contract. The traffic control plan shall be in accordance with "Traffic Controls for Street and Highway Construction and Maintenance Operations" of the latest edition of the "Texas Manual on Uniform Traffic Control Devices."

c. Contractor will provide traffic control signs and barricades for all street widening and extensions. At least one lane of traffic must be maintained at all times.

PART 2 PRODUCTS - NOT USED

PART 3 EXECUTION - NOT USED

Section 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

08/15

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section 01 33

00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G

Progress and Completion Pictures; G

1.2 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start and at completion of project. Digital photographs, .jpeg, shall be provided to the CES Project Manager for unrestricted use by the Government.

1.4 MINIMUM INSURANCE REQUIREMENTS

Procure and maintain during the entire period of performance under this contract the following minimum insurance coverage:

Comprehensive general liability: $500,000 per occurrence

a. Automobile liability: $200,000 per person, $500,000 per occurrence for bodily injury, $20,000 per occurrence for property damage

b. Workmen's compensation as required by Federal and State workers' compensation and occupational disease laws.

c. Employer's liability coverage of $100,000, except in States where workers compensation may not be written by private carriers,

d. Others as required by Texas law.

Section 01 30 00 Page 2

1.6 SUPERVISION

1.6.1 Minimum Communication Requirements

Have at least one qualified supervisor capable of reading, writing, and conversing fluently in the English language on the job site during working hours. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

The Project Manager in this context shall be the individual with the responsibility for the overall management of the project and the Project Superintendent shall mean the individual with the responsibility for quality and production.

1.7 PRECONSTRUCTION CONFERENCE

After award of the contract but prior to commencement of any work at the site, a meeting with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal.

Major subcontractors who will engage in the work shall also attend.

1.8 ELECTRONIC MAIL (E-MAIL) ADDRESS

The Contractor shall establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments in Microsoft, Adobe Acrobat, and other similar formats. Within 10 days after contract award, the Contractor shall provide the Contracting Officer and the CES Project Manager an e-mail address for electronic communications from the Contractor related to this contract including, but not limited to contract documents, invoice information, and other correspondence. The Contracting Officer or the CES Project Manager may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes, terrorist threats, etc.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). The Contractor shall promptly notify the Contracting Officer, in writing, of any changes to the email address.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Section 01 31 19.00 44 Page 1

SECTION 01 31 19.00 44

PROJECT MEETING

11/15

PART 1 GENERAL

1.1 PRECONSTRUCTION CONFERENCE

Approximately three weeks after award of the contract and prior to the start of any construction work an authorized representative of the Contracting Officer will schedule and conduct a preconstruction conference.

The Contractor's Project Manager, Superintendent, and Quality Control Manager will attend this meeting. The Contractor is encouraged to have an officer of his company and representation from his sub-contractors at this conference. This conference will be held at the location specified by the Contracting Officer's authorized representative. Minutes of the meeting will be prepared by the Government and signed by both the Contractor and the Contracting Officer. The minutes shall become a part of the contract file.

1.1.1 Start of Construction Work

If the Contractor has submitted the Accident Prevention (Safety) Plan, Quality Control Plan, Environmental Protection Plan and all other required environmental plans for review prior to this meeting, these may be accepted in to or accepted with comments at the conference. Construction work will not proceed until after this meeting has been held, the plans noted above have been accepted, and the Notice to Proceed has been received and acknowledged by the Contractor.

1.2 OTHER MEETINGS

Construction Quality Control meetings and conferences are specified in Section 01 45 00.00 20 QUALITY CONTROL. Other meetings are specified in various Division 1 and technical sections.

PART 2 PRODUCTS NOT USED

PART 3 EXECUTION NOT USED

Section 01 32 01.00 10 Page 1

SECTION 01 32 01.00 10

PROJECT SCHEDULE

02/15

PART 1 GENERAL

1.1 QUALIFICATIONS

The Contractor shall designate an authorized representative who shall be responsible for the preparation of all required project schedule reports.

1.2 SUBMITTALS

Government approval(GA) is required for submittals with a "GA" designation;

submittals having a "FIO" designation are for information only (FIO). When used, a designation following the "GA" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 30 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Project Schedule CPM; GA

PART 2 NOT USED

PART 3 EXECUTION

3.1 GENERAL REQUIREMENTS

A Project Schedule as described below shall be prepared. The scheduling of construction shall be the responsibility of the Contractor. Contractor management personnel shall actively participate in its development.

Subcontractors and suppliers, subcontractors and suppliers working on the project shall also contribute in developing and maintaining an accurate Project Schedule. The approved Project Schedule shall be used to measure the progress of the work, to aid in evaluating time extensions, and to provide the basis of all progress payments.

3.2 BASIS FOR PAYMENT

The schedule shall be the basis for measuring Contractor progress. Lack of an approved schedule or scheduling personnel will result in an inability of the 502d Project Manager to evaluate Contractor's progress for the purposes of payment. In the case where Project Schedule revisions have been directed by the Contracting Officer and those revisions have not been included in the Project Schedule, the Contracting Officer may hold retainage up to the maximum allowed by Contract, each payment period, until revisions to the Project Schedule have been made.

3.3 PROJECT SCHEDULE

Section 01 32 01.00 10 Page 2

The computer software system utilized by the Contractor to produce the Project Schedule shall be capable of providing all requirements of this specification. Failure of the Contractor to meet the requirements of this specification shall result in the disapproval of the schedule. Manual methods used to produce any required information shall require approval by the Contracting Officer.

3.3.1 AF IMT 3064

Use of the AF IMT 3064 will be the normal requirement for contractor construction schedules for most of the contract and shall include the required items, submittals, level of detail and contract requirements listed below for critical path method activities (Work Elements), in this paragraph C. through F and as detailed in the Instructions to Contractors on the reverse side of the AF IMT 3064, Form..

3.3.2 [Enter Appropriate Subpart Title Here]

3.3.3 Level of Detail Required

a. Critical Activities: The following activities shall be listed as separate line activities on the Contractor's project schedule:

1. Pre-final inspection.

2. Correction of punch list from pre-final inspection.

3. Final inspection.

4. Construction phasing.

b. Feature of Work: All activities shall be identified in the project schedule according to the feature of work to which the activity belongs. Feature of work refers, but is not limited to, a work breakdown structure for the project.

c. Scheduled Project Completion: The schedule interval shall extend from NTP to the Contract completion date.

d. Project Start Date: The schedule shall start no earlier than the date on which the NTP was acknowledged.

e. Negative Lags: Lag durations contained in the project schedule shall not have a negative value.

3.3.4 Project Schedule Submissions

The Contractor shall provide the submissions as described below. The data reports and network diagrams required for each submission are contained in paragraph SUBMISSION REQUIREMENTS.

Section 01 32 01.00 10 Page 3

3.3.4.1 Preliminary Project Schedule Submission

The Preliminary Project Schedule, defining the Contractor's planned operations shall be submitted for approval within 10 calendar days after the NTP is acknowledged. The approved preliminary schedule shall be used for payment purposes not to exceed the first 30 calendar days after NTP.

3.3.4.2 Initial Project Schedule Submission

The Initial Project Schedule shall be submitted for approval within 30 calendar days after NTP. The schedule shall provide a reasonable sequence of activities which represent work through the entire project and shall be at a reasonable level of detail.

3.3.4.3 Periodic Schedule Updates

Based on the result of progress meetings, specified in "Periodic Progress Meetings," the Contractor shall submit periodic schedule updates. These submissions shall enable the 502d CES Project Manager to assess Contractor's progress.

3.3.5 Periodic Progress Meetings

Progress meetings shall include a monthly on-site meeting or other regular intervals mutually agreed to at the preconstruction conference. During this meeting the Contractor shall describe, on an activity by activity basis, all proposed revisions and adjustments to the project schedule required to reflect the current status of the project. The CES Project Manager will approve activity progress, proposed revisions, and adjustments as appropriate.

3.3.5.1 Meeting Attendance

The Contractor's Project Manager and Scheduler shall attend the regular progress meeting.

3.3.5.2 Update Submission Following Progress Meeting

A complete update of the project schedule containing all approved progress, revisions, and adjustments, based on the regular progress meeting, shall be submitted not later than four (4) working days after the monthly progress meeting.

3.3.5.3 Progress Meeting Contents

Update information, including Actual Start Dates, Actual Finish Dates, Remaining Durations, and Cost-to-Date shall be subject to the approval of the Contracting Officer and CES Project Manager. At a minimum, the Contractor shall address the following items on an activity by activity basis during each progress meeting. The Contracting Officer's determination as to the number of allowable days of contract extension shall be based upon the project schedule updates in effect for the time period in question, and other factual information. Actual delays that are found to be caused by the Contractor's own actions, which result in the extension of the schedule, will not be a cause for a time extension to the contract completion date.

Section 01 32 01.00 10 Page 4

3.3.6 Submission Requirements

3.3.6.1 Change Justification

The Contractor shall submit a justification for each request for a change in the Contract completion date of less than two (2) weeks based upon the most recent schedule update at the time of the NTP or constructive direction issued for the change. Such a request shall be in accordance with the requirements of other appropriate Contract Clauses and shall include, as a minimum:

a. A list of affected activities, with their associated project schedule activity number.

b. A brief explanation of the causes of the change.

c. An analysis of the overall impact of the changes proposed.

d. A sub-network of the affected area.

e. Activities impacted in each justification for change shall be identified by a unique activity code contained in the required data file.

3.3.6.2 Additional Submission Requirements

For requested time extension of over two (2) weeks, the Contracting Officer may request an interim update with revised activities for a specific change request. The Contractor shall provide this disk within four (4) days of the Contracting Officer's request.

Section 01 33 00 Page 1

SECTION 01 33 00

SUBMITTAL PROCEDURES

05/11

PART 1 GENERAL

1.1 DEFINITIONS

1.1.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections. Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

Submittals which are required prior to the start of construction

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Network Analysis Schedule (NAS)

Submittal register

Health and safety plan

Work plan

Quality Control(QC) plan

Environmental protection plan

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided

Section 01 33 00 Page 2 has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits.

Text of posted operating instructions.

SD-11 Closeout Submittals

Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).

Special requirements necessary to properly close out a construction contract.

Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.

1.1.2 Approving Authority

Office or designated person authorized to approve submittal.

1.1.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

Section 01 33 00 Page 3

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

1.3 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.3.1 Government Approved (G)

Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.4 PREPARATION

1.4.1 Transmittal Form

Prior to submittal, all items shall be checked and approved by the Contractor and each respective AF Form 3000 shall be signed and dated by the contractor certifying that the accompanying submittal complies with the contract requirements.

1.4.2 Not Used

1.4.2.1 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government. The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic Source Drawing files are not construction documents.

Differences may exist between the Source Drawing files and the corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and

Section 01 33 00 Page 4 coordinate the work of all contractors for the project. If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.4.3 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within.

Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer.

Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/.

Provide hard copies of submittals when requested by the Contracting Officer.

Up to three additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

1.5 QUANTITY OF SUBMITTALS

1.5.1 Number of Copies of SD-02 Shop Drawings

N/A

1.5.2 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions

Submit Two copies of submittals requiring review and approval by CES

Project Manager and the Contracting Officer.

1.5.3 Number of Samples SD-04 Samples

a. Submit two samples, or two sets of samples showing range of variation, of each required item. One approved sample or set of samples will be retained by approving authority and one will be returned to Contractor.

b. Submit one sample panel or provide one sample installation where directed. Include components listed in technical section or as directed.

c. Submit one sample installation, where directed.

https://safe.amrdec.army.mil/safe

Section 01 33 00 Page 5

d. Submit one sample of non-solid materials.

1.5.4 Number of Copies SD-05 Design Data and SD-07 Certificates

Submit Two copies of submittals requiring review and approval by CES Project Manager and the Contracting Officer.

1.5.5 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports

Submit Two copies of submittals requiring review and approval by CES Project Manager and the Contracting Officer, other than field test results that will be submitted with QC reports.

1.5.6 Number of Copies of SD-10 Operation and Maintenance Data

N/A

1.5.7 Number of Copies of SD-01 Preconstruction Submittals and SD-11 Closeout Submittals

Unless otherwise specified, submit two sets of administrative submittals.

1.6 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals. The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.7 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Section 01 33 00 Page 6

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.7.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.7.2 Contractor Use of Submittal Register

Update the following fields with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.7.3 Approving Authority Use of Submittal Register

Update the following fields.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.7.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

Section 01 33 00 Page 7

1.8 DEVIATION

All requests for deviations shall be clearly identified by the Contractor on AF Form 3000. The Contractor shall set forth in writing the reason for any deviations and annotate such deviations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.9 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.9.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.9.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

1.9.3 Warranting that Variations are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.9.4 Review Schedule Extension

In addition to normal submittal review period, a period of 10 working days will be allowed for consideration by the Government of submittals with variations.

1.10 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

Section 01 33 00 Page 8

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.11 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date submittals. One copy of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.

1.11.1 Review Notations

Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.

c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.

Section 01 33 00 Page 9

d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

1.12 DISAPPROVED OR REJECTED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR clause entitled CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.13 APPROVED/ACCEPTED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.14 APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to

Section 01 33 00 Page 10 disapprove any material or equipment which previously has proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Contractor to replace such materials or equipment to meet contract requirements.

Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

Section 01 35 29 Page 1

SECTION 01 35 29

OCCUPATIONAL SAFETY AND HEALTH

12/02

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "GA" designation;

submittals having a "FIO" designation are for information only. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Accident Prevention Plan (APP);GA

Lead Hazard Control Plan (for description see spec section 13281);

GA.

Activity Hazard Analysis (AHA); G

Crane Critical Lift Plan; G

Proof of qualification for Crane Operators; G

SD-06 Test Reports

Reports: Submit reports as their incidence occurs, in accordance with the requirements of the paragraph entitled, "Reports."; GA.

Submit reports as their incidence occurs, in accordance with the requirements of the paragraph, "Notifications and Reports."

Accident Reports; G

Crane Reports; GA

Monthly Exposure Reports; GA

Crane Reports; GA

Regulatory Citations and Violations; GA

Section 01 35 29 Page 2

SD-07 Certificates

Confined Space Entry Permit

Hot work permit

1.3 REGULATORY REQUIREMENTS

In addition to the detailed requirements included in the provisions of this contract, work performed shall comply with USACE EM 385-1-1, and the State of Texas laws, ordinances, criteria, rules and regulations. Submit matters of interpretation of standards to the appropriate administrative agency for resolution before starting work. Where the requirements of this specification, applicable laws, criteria, ordinances, regulations, and referenced documents vary, the most stringent requirements shall apply.

1.4 SITE QUALIFICATIONS, DUTIES AND MEETINGS

1.4.1 Personnel Qualifications

1.4.1.1 Site Safety and Health Officer (SSHO)

Site Safety and Health Officer (SSHO) shall be provided at the work site at all times to perform safety and occupational health management, surveillance, inspections, and safety enforcement for the Contractor. The Contractor Quality Control (QC) person can be the SSHO on this project. The SSHO shall meet the following requirements:

Level 2: A minimum of 3 years safety work on similar project. 30-hour OSHA construction safety class or equivalent within last 3 years.

1.4.2 Preconstruction Conference

Contractor representatives who have a responsibility or significant role in accident prevention on the project shall attend the preconstruction conference. This includes the project superintendent, site safety and health officer, quality control supervisor, or any other assigned safety and health professionals who participated in the development of the APP (including the Activity Hazard Analyses (AHAs) and special plans, program and procedures associated with it).

The Contractor shall discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting Officer's representative as to which phases will require an analysis. In addition, a schedule for the preparation, submittal, review, and acceptance of AHAs shall be established to preclude project delays.

Deficiencies in the submitted APP will be brought to the attention of the Contractor at the preconstruction conference, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance.

Work shall not begin until there is an…