This document is an attachment titled "Material Submittals Schedule" for a federal contract opportunity related to the Fallen Heroes Memorial Butterfly Garden project, solicitation number FA301024R0009.

The attachment provides a template for the contractor to submit required materials, including information such as item description, contract reference, type of submittal (e.g., certificate of compliance, shop drawings, samples), required submission date, date received by the contracting office, date sent to civil engineering for review, and final approval date. Key details include the project number, title, solicitation/contract number, and agency (Department of the Air Force Air Education and Training Command). The document indicates this attachment should be printed on legal size paper.

View the file

Other files for this federal contract opportunity

Show all 15

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
Project Title:
Butterfly Garden FenceSolicitation / Contract Number:

FA301024R0009, Attachment 3

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission Date

fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

Submittal Numbers fergusog: Enter the Submittal Number

Date Contractor
NotifiedContractor Resubmittal

fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date

(MM/DD/YY)

Approved fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25

&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).