Attachment 1 - Butterfly Garden SOW.pdf
PDF 149 KB Posted
- Attached to
- Fallen Heroes Memorial Butterfly Garden Federal contract opportunity
- Solicitation number
- FA301024R0009
About this file
This document is a Statement of Work (SOW) for the Fallen Heroes Butterfly Garden Fence installation project at Keesler Air Force Base in Mississippi. The contractor will be required to provide all personnel, equipment, materials, and services necessary to purchase, remove, and install an ornate black aluminum fence around the butterfly garden, including transition panels, gates, and concrete pillars. The work is to be performed within 30 days after contract award. The government will provide utilities, but the contractor is responsible for any additional power requirements. The contractor must comply with all federal, state, and local safety regulations and provide manufacturer warranties and a 12-month workmanship warranty. This SOW supports the Federal Contract Opportunity for the Fallen Heroes Memorial Butterfly Garden solicitation, with a site visit scheduled for July 23, 2024.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA301024R00090003 SF 30.pdf | ||
| Solicitation Amendment FA301024R00090003 SF 30.pdf | ||
| Attachment 7 - Questions and Answers - 20240808.pdf | ||
| Attachment 6 - Butterfly Garden Perimeter Drawings.pdf | ||
| Solicitation Amendment FA301024R00090002 SF 30.pdf | ||
| Solicitation Amendment - FA301024R00090002.pdf | ||
| Solicitation Amendment FA301024R00090001 SF 30.pdf | ||
| Solicitation Amendment - FA301024R00090001.pdf | ||
| Attachment 3 - MSS.xlsx | XLSX spreadsheet | |
| Butterfly Garden Fence Past Performance Questionnaire.pdf | ||
| Attachment 5 - Submittal Procedures.pdf | ||
| Butterfly Garden Fence Past Performance Reference List.pdf | ||
| Solicitation - FA301024R0009 Final.pdf | ||
| Attachment 2 - Butterfly Garden Design Layout.pdf | ||
| Attachment 4 - Wage Determination MS20240050.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR
Fallen Heroes Butterfly Garden Fence
WO#14817181
1. INTRODUCTION:
The Contractor shall provide all personnel, transportation, tools, equipment, materials, supervision, administration, labor, and services necessary to purchase, remove, dispose of, and install an ornate black aluminum fence as specified by the government.
2. TASK DESCRIPTION:
2.1 LOCATION: This contract is to be performed near the Outdoor Recreation Marina Park
B6755, Keesler AFB, MS.
2.2 DESCRIPTION OF WORK:
2.2.1 The Contractor is urged and expected to examine the site and make note of all requirements of the work before submitting any proposals. The Contracting Officer (CO) will provide drawings, specifications, and documents relevant to this requirement. The
Contractor shall check all drawings furnished immediately upon receipt and notify the
CO of any discrepancies. The Contractor shall be responsible for any errors that might have been avoided by complying with these procedures set forth. Any accessories or incidental items not specifically shown on the Drawings and detailed in the SOW herein, which are necessary and/or required to complete the work within the intent of these documents, shall be included by the Contractor without additional cost to the
Government. All work shall be performed in strict accordance with the
SOW/Specifications/Drawings, and subject to the terms and conditions of this contract.
2.2.2 Utilities for the work will be provided by the Government unless otherwise noted.
2.2.3 It is not anticipated that hazardous material will be encountered during the course of work. However, should such material be encountered, the Contractor is to immediately stop work and contact the CO.
2.2.3.1 REMOVE EXSISTING:
The Contractor shall free any foreign materials prior to beginning work. The Contractor shall not uproot any existing plants or damage existing trees.
2.2.3.2 MODIFY EXSISTING:
N.A.
2.2.3.3 PROVIDE AND INSTALL NEW:
A. Provide and install ornate black 300 Sterling Series Aluminum, C Series fence (or equal), plus or minus 324 linear feet.
B. Provide and install minimum (2) ornate black 300 Sterling Series C Aluminum (or equal) transition.
C. panels fencing plus or minus 6’ H x 4’ H. Garden has open front. Transition panels lead into fence from both east and west front sides.
D. Provide and install fence specifications: Posts: 2 ½” sq; Rails: 1-1 ½” x 1”;
Pickets: ¾” sq.
E. Provide and install 2 ½” sq. ball cap upgrades on all fence posts.
F. Provide and install .8” in black metal butterfly scroll for aluminum fence or equal on all pickets.
G. Provide and install (1) 8 ft double arched black aluminum or equal walking gate with standard latch.
H. Provide and install (1) 5 ft single arched black aluminum or equal walking gate with standard latch.
I. Provide and install (4) 18” wide squared x 84” concrete pillars with brick finish.
J. Brick finish is general Shale Providence Thin Brick Stillwater 2-in x 8-in
Tumbled Natural Stone Ledgestone finish or equal.
2.3 PERFORMANCE TIME: Performance will begin 10 days after Award and end 30 days after contract award.
2.4 PERFORMANCE OF WORK: Services shall be conducted in conformity with this SOW.
All work shall be done in a neat and workmanlike manner and in keeping with generally accepted standards for similar work.
3. GENERAL INFORMATION:
3.1 COMPLETED WORK: The Contractor shall inform the Contracting Officer (CO) when work is complete and ready for inspection. In the event that the work is not acceptable IAW the SOW, the CO will record a list of items to be corrected and schedule a date for re-inspection. The contractor shall ensure all corrections are made no later than the scheduled date for reinspection. Any damages caused by the Contractor shall be repaired or replaced at the Contractor’s expense.
Commented [TA1]: The performance of the contract shall be completed 30 days after contract award.
3.2 WARRANTY: The Contractor shall provide all manufacturer warranties and provide a 12-month warranty on all workmanship under normal use from date of final acceptance by the government.
3.3 GOVERNEMENT FURNISHED FACILITIES AND SERVICES: There are no government furnished supplies and equipment available for this contract.
3.4 GOVERNMENT FURNISHED UTILITIES: The government will furnish electricity, water, and sewage service where existing for accomplishment of work IAW this contract. If adequate power supply is not available, it is the Contractor’s responsibility to provide generators, power/extension cords, spider boxes, and/or etc.
3.5 HOURS OF OPERATION: The Contractor will be able to accomplish this work between the hours of 7:00 AM and 5:00 PM. The Contractor will not normally be permitted to work on weekends or on the following Federal holidays (or the day the Federal Government observes these holidays) unless approved by the CO. To be approved by the CO, the Contractor shall provide documentation showing work performed outside the hours of work will benefit the project’s mission. If approved by the CO, the Contractor shall coordinate such work with the
CS:
New Year’s Day Labor Day
Martin Luther King, Jr.’s Birthday Columbus Day
President’s Day Veteran’s Day
Memorial Day Thanksgiving Day
Juneteenth Christmas Day
Independence Day
3.6 JOBSITE SAFETY: The Contractor shall perform work in a safe manner IAW all Federal, State, and local safety regulations and all OSHA Safety and Health Requirements. The
Contractor shall display the appropriate caution signs when work operations might pose a risk to injury for any personnel that are present. Provide a written notification to the CO as soon as possible of each occurrence of damage to Government property and/or an accident resulting in death, injury, occupational disease, or adverse environmental impact. The
Contractor shall provide a copy of accident investigation reports to the CO within five (5) calendar days of each occurrence.
3.7 COMPLIANCE WITH LAWS AND REGULATIONS: The Contractor shall be knowledgeable of and comply with all applicable Federal, State, and local laws, regulations, and requirements covering the work required under this contract. In the event the applicable laws, regulations, and requirements change during the term of this contract, the Contractor shall be required to comply with such changes when they come into effect.
3.8 SUPERVISION: Contractor shall provide competent supervision familiar with the project and are on-site at all times when work is in progress. Contractor is responsible for scheduling and coordinating various trade activities. Contractor is also responsible for assuring that all work accomplished, and materials used are in accordance with industry standards. The Contractor shall provide a primary and alternate point of contact that shall be responsible for the performance of services. The Contractor Point of Contact shall be available via telephone for service request and will provide the names and telephone numbers in writing to the Contracting Officer before the contract start date.
File details come from the government source that posted it. Updated .