Attachment 13 MAHG 211127 Questions and Answers Amendment 2 20230823.pdf
PDF 1 MB Posted
- Attached to
- MAHG 21-1127 Repair Apron #3
- Solicitation number
- FA301023R0032
About this file
This document package includes plans and specifications for a federal contract opportunity to repair an aircraft apron at Keesler Air Force Base in Mississippi. The project involves demolishing and replacing sections of concrete apron, installing new mooring anchors, and applying new airfield markings to match existing. Work must be completed within 150 days. A stormwater pollution prevention plan and airfield driving licenses for contractors are required. The Air Force reserves the right to suspend work during lightning within 5 miles and contractors must follow OSHA and Air Force safety regulations. Coordination will be needed for any cranes required on site.
View the file
Other files
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
MAHG 21-1127 Repair Apron 3 Amendment 2 Questions and Answers
1. Sheet 7 of the plan set shows a typical mooring eye detail. This detail appears to be for a static grounding rod. Please advise if this correctly depicts the materials to be used for mooring eyes.
Yes, the detail on the page 7 of 7 shows the details of typical Apron Mooring eye, however the final installation on the surface shall be identical to the existing one.
Please refer to the Aircraft Tiedown section, attached for the detail specification of the mooring eye details.
2. Sheet 3 of the plan set shows construction fencing to be installed around the work site. Typically, we see airfield approved low-profile barricades utilized for sectioning off work areas on an airfield. Please confirm that we are to use construction fencing.
Construction Fencing will be acceptable.
3. Please advise if crushed concrete that meets the required gradation can be used in lieu of crushed limestone.
Yes, if the required compaction can be achieved.
4. We are concerned with project POP. The newly installed concrete will need to be cured, which will be best achieved by curing compound rather than a visqueen or burlap covering (due to the logistics of keeping the covering wet and keeping it in place on the airfield). The airfield marking paint cannot be applied over the concrete curing compound until it has had sufficient time to dissipate (30-45 days). POP will be extended from 120 days to 150 days.
5. Are there any permits (other than the Dig Permit) and/or training required to complete this work on the airfield?
Yes, A SWPPP will also be required for this project, because of the proximity of the project site to the storm drains.
6. Are there any specific requirements regarding dust control while demolishing the existing concrete?
Dust and Debris Control: Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in the surrounding area. Do not use water if it results in hazardous or objectionable conditions such as, but not limited to, flooding, or pollution. Vacuum and dust the work area daily or as needed. Sweep pavements as often as necessary to control the spread of debris. Keep site wet in a manner to prevent ponding but prevent the spreading of dust.
7. What is the exact square footage of slabs to be demolished and replaced?
Contractors are responsible for verifying the dimensions of the slabs.
MAHG 21-1127 Repair Apron 3 Amendment 2 Questions and Answers
8. What is the exact number of new mooring anchors to be installed?
The updated Page 7 of 7 shows 6 mooring anchors installed.
9. Will the contractor be permitted use of the gate adjacent to the project site?
No, to use any other gates than the gate on Phantom Street, an escort is required. No escort is available for this project.
How To Install 3490 Type Aircraft Tie Down
1) Place the mooring eyes on sub grade and fill with sand to exclude concrete (6000 psi concrete recommended) . Pour the concrete and finish operation. Sand is easily washed out when paving is completed.
The mooring points, 3490 and 3490-A have ½” holes on the sides for reinforcing rebar rods. The 3490-B has 1-1/8” holes. Rebar can be threaded thru these holes if desired.
2) Bring to grade using a wood or metal stake inserted into the socket opening at bottom of Mooring Eye. Square socket design prevents displacement while concrete is being poured and, if required, the hole provides drainage to the subgrade after Mooring Eye is in place.
SECTION 34 73 13 Page 1
MAHG 21-1227- Apron3
SECTION TABLE OF CONTENTS
DIVISION 34 - TRANSPORTATION
SECTION 34 73 13
AIRCRAFT TIEDOWNS
11/19
PART 1 GENERAL
1.1 REFERENCES
1.2 SUBMITTALS
1.3 AS-BUILT DRAWINGS
PART 2 PRODUCTS
2.1 MATERIALS
2.2 MOORING DEVICES
2.3 CONCRETE
2.4 REINFORCING STEEL
PART 3 EXECUTION
3.1 MOORING POINTS IN NEW RIGID PAVEMENTS OR CONCRETE PADS
3.2 SAFETY
-- End of Section Table of Contents --
SECTION 34 73 13 Page 2
SECTION 34 73 13
AIRCRAFT TIEDOWNS
11/19
PART 1 GENERAL
This specification for mooring be coordinated with UFC 3-260-01, Airfield planning and Design.
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN WELDING SOCIETY (AWS)
AWS D1.4/D1.4M (2011) Structural Welding Code -
Reinforcing Steel
ASTM INTERNATIONAL (ASTM)
ASTM A615/A615M (2022) Standard Specification for Deformed and Plain Carbon-Steel Bars for Concrete Reinforcement
ASTM C94/C94M (2022a) Standard Specification for
Ready-Mixed Concrete
ASTM C309 (2019) Standard Specification for Liquid Membrane-Forming Compounds for Curing Concrete
ASTM C536 (1983; R 2018) Standard Test Method for
Continuity of Coatings in Glassed Steel Equipment by Electrical Testing
NATIONAL INSTITUTE FOR OCCUPATIONAL SAFETY AND HEALTH (NIOSH)
NIOSH 81-123 (1981) Occupational Health Guideline for
Chemical Hazards, (Vols. I, II, and III)
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are [for Contractor Quality Control approval.][for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.] Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-02 Shop Drawings
As-Built Drawings;
SD-06 Test Reports
SECTION 34 73 13 Page 3
Concrete;
SD-07 Certificates
Mooring Devices
Reinforcing Steel
1.3 AS-BUILT DRAWINGS
Submit as-built drawings that provide current factual information, including deviations from and amendments to the drawings and changes in the work, concealed and visible.
PART 2 PRODUCTS
2.1 MATERIALS
Do not use a combination of materials that forms an electrolytic couple, which accelerates corrosion in the presence of moisture, unless moisture is permanently excluded from the junction of such metals.
2.2 MOORING DEVICES
Cast mooring devices in ductile iron 80-55-06 in accordance with ASTM C536, unless otherwise indicated. Show the device in the contract drawings.
Submit certificates of compliance on the devices stating that the mooring devices meet the specified requirements.
2.3 CONCRETE
Submit complete concrete mix design including all cement, aggregate, and concrete tests and compliance certificates. Use concrete in accordance with the Section 32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER HEAVY-DUTY PAVEMENTS, ASTM C94/C94M. Use air entrained concrete having a minimum compressive strength of 6000 psi. Use concrete with the following properties: nominal maximum aggregate size of 1 in, air content of 6 percent, and a maximum slump of 4 in for drilled piers and 2 in for all other applications.
2.4 REINFORCING STEEL
Use reinforcing steel in accordance with ASTM A615/A615M Grade 40 or 60 for #4 tie bars and Grade 60 for #6 vertical bars. Weld steel into cages in accordance with AWS D1.4/D1.4M and insert securely in the piers, in position and alignment, as shown in the drawings, prior to concrete placement. Submit certificates of compliance stating that the reinforcing steel meets the specified requirements.
PART 3 EXECUTION
3.1 MOORING POINTS IN NEW RIGID PAVEMENTS OR CONCRETE PADS
Install the mooring device within plus or minus 2 in of the location shown on the contract drawings. Set the top of the mooring device within 1/4 in of the plan pavement surface elevation, but not higher than the pavement surface. Install the mooring device prior to placement of the concrete pavement. Place concrete and reinforcement in accordance with Section 03 30 00 CAST-IN-PLACE CONCRETE. Keep hand finishing of the concrete around the mooring devices to a minimum.
SECTION 34 73 13 Page 4
3.1.1 Cleanup
Control all operations to minimize the amount of dust, dirt, debris and laitance in the work area. Clean all dirt, dust, debris, or laitance from coring or concreting operations, from the pavement surfaces prior to final acceptance.
3.2 SAFETY
In addition to Safety Requirements contained in the Contract Clauses;
prevent employee respiratory, eye or skin contact with Portland cement.
Provide and require employees to use and dispose or clean the following in accordance with the provisions of the National Institute for Occupational Safety and Health NIOSH 81-123:
a. Impervious clothing, boots, and gloves.
b. Splash-proof safety goggles and face shields.
c. Respiratory protection equipment.
-- End of Section --
G. REED
J. BERGERON G. REED
MAHG21-112720 APRIL 2023K.PAHLAVAN
Repair Apron 3
N / A
N / A
PLAN VIEW LAYOUT
SCALE: 1" = 20'-0"
GENERAL NOTES
1. CONTRACTOR ENCOURAGED TO FIELD VERIFY ALL DIMENSIONS AND CONDITIONS PRIOR TO BID
AND START OF CONSTRUCTION. NOTIFY CONTRACTING OFFICER OF ANY CONDITIONS
DETRIMENTAL TO THE COMPLETION OF THE WORK AS DESIGNED.
2. PROTECT ALL ELEMENTS TO REMAIN SUCH AS EXISTING UTILITIES, FACILITY, ROADS, CURBS, DRIVES, SIDEWALKS, METAL CARPORTS, SOLID SOD, ETC. CONTRACTOR TO RESTORE ANY
DAMAGED ELEMENTS TO THE ORIGINAL CONDITIONS.
3. CONFINE ALL WORK TO SPECIFIC AREAS AS DESIGNATED IN THE SCOPE OF WORK AND
SCHEDULE.
4. REFER TO MATERIAL SPECIFICATIONS IN SCOPE OF WORK FOR REQUIREMENTS AND
APPLICATIONS.
5. PRIOR TO CONSTRUCTION THE CONTRACTOR SHALL LOCATE ALL UTILITIES, ANY UTILITY
ADJUSTMENTS, EXISTING OR PROPOSED, REQUIRED TO COMPLETE CONSTRUCTION IS THE
RESPONSIBILITY OF THE CONTRACTOR. THIS ITEM INCLUDES, BUT IS NOT LIMITED TO; THE
TEMPORARY RELOCATION OF EXISTING OVERHEAD POWER LINES. ALL WORK IN THE VICINITY
OF OVERHEAD POWER LINES SHALL CONFORM TO OSHA REQUIREMENTS AND ANY OTHER
APPLICABLE (LOCAL) SAFETY REQUIREMENTS. THE CONTRACTOR IS TO REPAIR ANY DAMAGES
TO EXISTING UTILITIES THAT ARE TO REMAIN IN SERVICE IMMEDIATELY AT NO ADDITIONAL
COSTS OR EXPENSE TO THE GOVERNMENT.
6. CONTRACTOR SHALL COORDINATE ACTIVITIES THROUGHOUT THE PROJECT IN A MANNER THAT
ALLOWS EMERGENCY ACCESS TO ALL EXISTING ROADWAYS AT ALL TIMES WITHOUT DELAYS TO
EMERGENCY VEHICLES RESPONSE TIMES.
7. CONTRACTOR IS REQUIRED TO GPS LOCATE ALL UTILITY LINES AND APPURTENANCES
IMMEDIATELY AFTER INSTALLATION FOR UPDATING RED-LINE AS-BUILT DRAWINGS MAINTAINED
ON-SITE BY CONTRACTOR.
8. ALL CRANES COMING ON BASE MUST BE FIRST COORDINATED WITH WITH COE/BASE TO GET
FULL EXTENSION AND EXPECTED DURATION. THIS MUST BE SUPPLIED TO THE AIRFIELD 6
WEEKS PRIOR TO CRANE'S ARRIVAL. CONTRACTOR MUST HAVE FAA TEMPORARY CRANE PERMIT
IN HAND PRIOR TO ANY CRANE ACTIVITY.
9. CONTRACTOR SHALL APPOINT A CONSTRUCTION SUPERINTENDENT, SUBJECT TO THE
APPROVAL OF THE CONTRACTING OFFICER, WHO SHALL BE PRESENT ON THE
CONSTRUCTION SITE AT ALL TIMES DURING WORKING HOURS WHILE JOB IS IN PROGRESS. THE
SUPERINTENDENT SHALL BE DESIGNATED THE RESPONSIBLE CONTRACTOR'S REPRESENTATIVE
WHO SHALL BE AVAILABLE ON A 24-HOUR BASIS. WHEN THE CONTRACTOR'S REPRESENTATIVE
IS NOT AVAILABLE ON THE CONSTRUCTION SITE, AN ALTERNATIVE REPRESENTATIVE SHALL BE
PROVIDED.
10. EROSION CONTROL DEVICES SHALL BE USED FOR THE STAGING AREA AND ANY MATERIAL
STOCKPILES WHEN NECESSARY TO CONTROL EROSION AND STORMWATER RUNOFF.
11. LIMITS OF CONSTRUCTION IS DEFINED AS THOSE AREAS AFFECTED BY THE CONTRACTOR'S
OPERATIONS INVOLVING EXCAVATION, EMBANKMENT AND FINAL GRADING REQUIRED TO
COMPLETE THE WORK IN ACCORDANCE WITH THE ELEVATIONS, GRADES AND SECTIONS SHOWN
IN THESE DRAWINGS.
12. CONTRACTOR SHALL UTILIZE EROSION CONTROL DEVICES AND PROCEDURES AS SET FORTH IN
MDOT STANDARD DETAILS, 2018 EDITION.
13. BE ADVISED THAT CONTRACTOR'S WORK MAY BE SUSPENDED WHEN LIGHTNING IS WITHIN 5
MILES.
14. CONTRACTOR SHALL MAINTAIN SAFETY PRACTICES THAT CONFORM TO OCCUPATIONAL SAFETY
AND HEALTH ADMINISTRATION (OSHA) REGULATIONS AND USACE SAFETY MANUAL EM385-1-1.
15. ANY VEHICLE BEING DRIVEN ON AIRFIELD APRON MUST BE DRIVEN BY AN AIRFIELD LICENSED
DRIVER. AIRFIELD DRIVING CLASSES MUST BE SCHEDULED AND TAKEN THROUGH AIRFIELD
OPERATIONS BEFORE AIRFIELD DRIVING LICENSE WILL BE ISSUED.
BUILDING 4278
Project AreasProject Area
K.PAHLAVAN C2
3 7
XX
Project Area
MOORING POINTS
NEW MARKINGS
MATCH EXISTING
MARKINGS
B-
AutoCAD SHX Text E
AutoCAD SHX Text D
AutoCAD SHX Text C
AutoCAD SHX Text B
AutoCAD SHX Text
APPROVED
AutoCAD SHX Text
DRAWN
AutoCAD SHX Text
AIR EDUCATION AND TRAINING COMMAND
AutoCAD SHX Text
DATE
AutoCAD SHX Text
REVISION
AutoCAD SHX Text
UNITED STATES AIR FORCE
AutoCAD SHX Text A
AutoCAD SHX Text
MISSISSIPPI
AutoCAD SHX Text
FACILITY NUMBER:
AutoCAD SHX Text
AutoCAD SHX Text
SHEET OF
AutoCAD SHX Text
DRAWING NUMBER:
AutoCAD SHX Text
BILOXI
AutoCAD SHX Text
RECOMMENDED:
AutoCAD SHX Text (Chief of Engineering)
AutoCAD SHX Text
SUBMITTED:
AutoCAD SHX Text (Chief of Contracts Design)
AutoCAD SHX Text
SCALE:
AutoCAD SHX Text
PROJECT NUMBER:
AutoCAD SHX Text
CHECKED:
AutoCAD SHX Text
DATE:
AutoCAD SHX Text
DESIGNED:
AutoCAD SHX Text
DRAWN:
AutoCAD SHX Text
AutoCAD SHX Text
OFFICE OF CIVIL ENGINEERS
AutoCAD SHX Text
KEESLER AIR FORCE BASE
AutoCAD SHX Text G
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text F
AutoCAD SHX Text
AutoCAD SHX Text C1.0
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text D
AutoCAD SHX Text E
AutoCAD SHX Text B
AutoCAD SHX Text C
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text G
AutoCAD SHX Text F
AutoCAD SHX Text
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Rectangle
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Pencil
1602600625E Pencil
1602600625E Pencil
1602600625E Pencil
1602600625E Pencil
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Typewritten Text Approximate Location of Construction Fencing
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
1602600625E Line
| MAHG211127_Repair Apron 3_Mooring Eyes Location.pdf |
| Sheets and Views |
| Apron_Repair_Redesign-Transverse |
| Apron_Repair_Redesign-Longitudinal |
| Apron_Repair_Redesign-Construction |
| Apron_Repair_Redesign-Additional_Details |
| Apron 3 Drawing new.pdf |
| T-1.pdf |
| Sheets and Views |
| T1.0 |
| C-1.pdf |
| Sheets and Views |
| C1.0 |