Attachment 4 - MAHG235001 Pressed BBEC Conversion Phase 1 MSS.xlsx
XLSX spreadsheet 34 KB Posted
- Attached to
- Pressed BBEC Conversion
- Solicitation number
- FA301023R00001
About this file
This document contains a schedule of material submittals for a federal contract opportunity to convert a pressed brick enlisted barracks and enlisted club (BBEC) facility. The schedule lists 68 items requiring submittals such as shop drawings, samples, warranties, and test reports. Submittals are due within 10 days of contract award and must be provided in both hard copy and digital format, with three copies generally required. The schedule includes requirements for hazardous materials documentation, warranties, and as-built documentation to be provided at the end of the 180-day period of performance.
The related federal contract opportunity is a solicitation between $250,000 and $500,000 to be awarded through full and open competition as a request for proposal. The performance period is 180 days. The solicitation requires pricing to be provided in Section B and acknowledges any amendments. An organized site visit is scheduled for February 8, 2024. The contract will be funded through non-appropriated funds and adhere to NAF guidance and regulations rather than FAR.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| Project Number: | |||
| 235001 | Project Title: | ||
| MAHG235001 Pressed BBEC Conversion Phase 1 | Solicitation / Contract Number: |
FA301024R0001 // Attachment 4
| Line Number | (To be completed by Project Engineer) | (To be completed by Contract Administrator) | ||||||||||||||
| Number of Copies Required (if not electronically submitted) | Remarks | |||||||||||||||
| Item or Description of Item, Contract Reference, Type of Submittal | Certificate of Compliance | Shop Drawings | Samples | Color Selection | Manufacturer's Recommendation | Warranty-Manufacturer and/or Workmanship | Catalog Data | Operating Instructions | Schedules, Listings, Reports, Plans | Technical Data | Test Reports | Field Reports | Required Submission Date |
fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
Submittal Numbers fergusog: Enter the Submittal Number
| Date Contractor | ||
| Notified | Contractor Resubmittal |
fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date
(MM/DD/YY)
Approved fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
| 1 | HazMat Questionnaire | 3 | 3 | 5 Days Prior to Start Date | SOW sect 4.4 |
| 2 | HazMat MSDS | 3 | 3 | 5 Days Prior to Start Date | SOW sect 4.4 |
Must be filled out if Contractor answers YES to ANY HazMat questionnaire items.
3 HazMat Reporting Entry Form 3 3 5 Days Prior to Start Date SOW sect 4.4 Submit Final Quantities
| 4 | HazMat Reporting entry Form | 3 | 3 | End of Contract | SOW sect 4.4 | |
| 5 | Recycling and Landfill Report | 3 | 3 | End of Contract | SOW sect 4.1 | |
| 6 | Asbestos Abatement Report | 3 | 3 | 3 | End of Contract | SOW sect 4.7.3 |
| 7 | 1-Year Warranty (Contractor's) | 3 | 3 | End of Contract | ||
| 8 |
| 9 | Section 061000- Rough Carpentry | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 10 | Section 062000-Finish Carpentry General | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 11 | Section 064020-Interior Architectural Woodwork | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 12 | Section 066500-Solid Surface Fabrications | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 13 | Section 072000-Insulation | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 14 | Section 072400-Exterior Insulation and Finish Systems | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 15 | Section 081113-Steel Frames | 1 | 1 | 1 | 1 | 10 Days Following NTP | NOT USED | |||
| 16 | Section 079200-Joint Sealants | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 17 | Section 081113-Steel Frames | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 18 | Section 082000-Wood Doors | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 19 | Section 084010-Aluminum Doors and Frames | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| Section 085800-Aluminum Sliding Windows | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 20 | Section 087100-Door Hardware | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 21 | Section 092550-Gypsum Board Assemblies | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 22 | Section 093013-Tile and Grout | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 23 | Section 095110-Acoustical Panel Ceilings | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 24 | Section 099100-Paint | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 25 | Section 099323-Stains and Transparent Finishes | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 26 | Section 090170-Repair of Exterior Insulation Finish System | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 27 | Section 062000-Finish Carpentry General | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 28 | Section 079200-Joint Sealants | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 29 | Section 081113-Steel Frames | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 30 | Section 082000-Wood Doors | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 31 | Section 084010-Aluminum Doors and Frames | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 33 | Section 085800-Aluminum Sliding Windows | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 34 | Section 092550-Gypsum Board Assemblies | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 35 | Section 093013-Tile and Grout | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 36 | Section 093050-Tile Setting Materials and Accessories | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 37 | Section 095110-Acoustical Panel Ceilings | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 38 | Section 096500-Resilient and LVT Flooring | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 39 | Section 099100-Paint | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 40 | Section 099323-Stains and Transparent Finishes | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 41 | Section 123600-Countertops | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| 42 | Section 099000-Painting and Coating | 1 | 1 | 1 | 1 | 10 Days Following NTP | ||||
| Section 102600-Wall Protection | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 41.1 | Section 124813-Entrance Floor Mats and Frames | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||
| 43 | Mini-Split AC Set (1-CU, 2-Eus) | 1 | 1 | 1 | 1 | 1 | 1 | Within 30 Days after Issuance Of Award | See DWG M5.0 |
per DIAKUN Applied, McQuay.
| Exhaust Hood, Exhaust Fan | |||||||||||
| GOVERNMENT FURNISHED | |||||||||||
| OA Make-Up Unit, OA Fan, HC, CC, Damper, Filter, Controller | |||||||||||
| GOVERNMENT FURNISHED | |||||||||||
| 44 | HVAC RECT, RECT duct & fittings … | ||||||||||
| Low Pressure | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||||
| 45 | HVAC RECT, RND GREASE duct & fittings … Low Pressure | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 46 | HVAC Duct Insulation | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 47 | MAU HW & CHW Coil Paks | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 48 | HVAC duct accessories |
volume/control/back-draft dampers, SA diffusers, RA grilles, OA & EA Louvers, Smoke Filter 1 1 1 1 10 Days After Issuance Of Award
49 Plumbing Fixtures Drop-In Sink, Faucet, and
| Ice Station | GOVERNMENT FURNISHED | ||||||||||
| 50 | HW Piping, Fittings, & Valves | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 51 | Potable HFW & CFW Piping, | ||||||||||
| Fittings, & Valves | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||||
| 52 | Drain & Vent Piping, Fittings (PVC) | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 53 | HW and HFW Piping Insulation | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 54 | Mini-Split AC Unit | ||||||||||
| Refrigerant Piping | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | ||||||
| 55 | Refrigerant Piping Insulation | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award |
54 HVAC Control VAV box damper set, Exhaust Hood Fan & FP/Alarm System, OA Make-Up Unit Fan, HW & CHW Coils, OA & EA Dampers, OA & EA filter DP sense/alarm 1 3 3 3 3 Days After Test
| 55 | Drain & Vent System | ||||||||||
| Gravity Leak Test | 1 | 3 | 3 | 3 | 3 Days After Test | ||||||
| 56 | HW System P-Test Report | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||||||
| 57 | HW System | ||||||||||
| Balance / Op Test Report | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||||||
| 58 | Potable HFW & CFW System | ||||||||||
| P-Test Report | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | |||||||
| 59 | Potable Water System Disinfection | ||||||||||
| Test & Analyze | 1 | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | |||||
| 60 | CHW System P-Test Report | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||||||
| 60 | CHW System | ||||||||||
| Balance / Op Test Report | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||||||
| 61 | HVAC Air Balance Test |
AHU 1, B6732 1st Floor TU1-7A VAV Box Set SA, RA in corridor
| RA Dining Areas | 1 | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||
| 62 | HVAC Air Balance Test |
Exhaust Hood, OA Make-Up Unit,
| 1st Floor | 1 | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy | ||
| 63 | Exhaust Hood FP & Alarm System | |||||||
| Op Test Report | 1 | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy |
64 Electrical Power Cable, Conduit, Receptacles,
| Breakers, Panels, Safety Switch, Controllers | 1 | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 65 | Electrical Lighting | ||||||||||
| Cable, Conduit, P-Devices, Fixtures | 1 | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award | |||||
| 66 | Fire Alarm Items | 1 | 1 | 1 | 1 | 10 Days After Issuance Of Award |
| 67 | Operation & Maintenance Manuals | 1 | 3 | 3 | 3 | 3 Days After Test | 3-hard copy, 3-digital copy |
| Operation & Maintenance Manuals |
Kitchen Exhaust Hood Make-Up Air Unit
| Kitchen Service Equipment | GOVERNMENT FURNISHED | ||||||
| 68 | Warranty (Manufacturer's) | 3 | 3 | End of Contract | 3-hard copy, 3-digital copy | ||
| Warranty (Manufacturer's) |
Kitchen Exhaust Hood Make-Up Air Unit Kitchen Service Equipment GOVERNMENT FURNISHED