Attachment 4 - MAHG235001 Pressed BBEC Conversion Phase 1 MSS.xlsx

XLSX spreadsheet 34 KB Posted

Attached to
Pressed BBEC Conversion
Solicitation number
FA301023R00001
Issued by

About this file

This document contains a schedule of material submittals for a federal contract opportunity to convert a pressed brick enlisted barracks and enlisted club (BBEC) facility. The schedule lists 68 items requiring submittals such as shop drawings, samples, warranties, and test reports. Submittals are due within 10 days of contract award and must be provided in both hard copy and digital format, with three copies generally required. The schedule includes requirements for hazardous materials documentation, warranties, and as-built documentation to be provided at the end of the 180-day period of performance.

The related federal contract opportunity is a solicitation between $250,000 and $500,000 to be awarded through full and open competition as a request for proposal. The performance period is 180 days. The solicitation requires pricing to be provided in Section B and acknowledges any amendments. An organized site visit is scheduled for February 8, 2024. The contract will be funded through non-appropriated funds and adhere to NAF guidance and regulations rather than FAR.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Material Submittals Schedule

Project Number:
235001Project Title:
MAHG235001 Pressed BBEC Conversion Phase 1Solicitation / Contract Number:

FA301024R0001 // Attachment 4

Line Number(To be completed by Project Engineer)(To be completed by Contract Administrator)
Number of Copies Required (if not electronically submitted)Remarks
Item or Description of Item, Contract Reference, Type of SubmittalCertificate of ComplianceShop DrawingsSamplesColor SelectionManufacturer's RecommendationWarranty-Manufacturer and/or WorkmanshipCatalog DataOperating InstructionsSchedules, Listings, Reports, PlansTechnical DataTest ReportsField ReportsRequired Submission Date

fergusog: Enter the due date from the Contractor (MM/DD/YY) Date Received in Contracting fergusog: Enter the date received from the Contractor. (MM/DD/YY) Date to Civil Engineering fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY) Return Suspense Date fergusog: Enter the date the submittal is due back from CE

(MM/DD/YY)

Submittal Numbers fergusog: Enter the Submittal Number

Date Contractor
NotifiedContractor Resubmittal

fergusog: Enter Resubmittal Number Final Approval fergusog: Enter the submittal final approval date

(MM/DD/YY)

Approved fergusog: Enter date the Contractor was notified of submittal approval

(MM/DD/YY)

fergusog: Enter Resubmittal Number Disapproved fergusog: Enter date the Contractor was notified of submittal disapproval

(MM/DD/YY)

fergusog: Enter the submittal final approval date

(MM/DD/YY)

1HazMat Questionnaire335 Days Prior to Start DateSOW sect 4.4
2HazMat MSDS335 Days Prior to Start DateSOW sect 4.4

Must be filled out if Contractor answers YES to ANY HazMat questionnaire items.

3 HazMat Reporting Entry Form 3 3 5 Days Prior to Start Date SOW sect 4.4 Submit Final Quantities

4HazMat Reporting entry Form33End of ContractSOW sect 4.4
5Recycling and Landfill Report33End of ContractSOW sect 4.1
6Asbestos Abatement Report333End of ContractSOW sect 4.7.3
71-Year Warranty (Contractor's)33End of Contract
8
9Section 061000- Rough Carpentry111110 Days After Issuance Of Award
10Section 062000-Finish Carpentry General111110 Days After Issuance Of Award
11Section 064020-Interior Architectural Woodwork111110 Days After Issuance Of Award
12Section 066500-Solid Surface Fabrications111110 Days After Issuance Of Award
13Section 072000-Insulation111110 Days After Issuance Of Award
14Section 072400-Exterior Insulation and Finish Systems111110 Days After Issuance Of Award
15Section 081113-Steel Frames111110 Days Following NTPNOT USED
16Section 079200-Joint Sealants111110 Days After Issuance Of Award
17Section 081113-Steel Frames111110 Days Following NTP
18Section 082000-Wood Doors111110 Days After Issuance Of Award
19Section 084010-Aluminum Doors and Frames111110 Days After Issuance Of Award
Section 085800-Aluminum Sliding Windows111110 Days After Issuance Of Award
20Section 087100-Door Hardware111110 Days After Issuance Of Award
21Section 092550-Gypsum Board Assemblies111110 Days After Issuance Of Award
22Section 093013-Tile and Grout111110 Days After Issuance Of Award
23Section 095110-Acoustical Panel Ceilings111110 Days After Issuance Of Award
24Section 099100-Paint111110 Days After Issuance Of Award
25Section 099323-Stains and Transparent Finishes111110 Days After Issuance Of Award
26Section 090170-Repair of Exterior Insulation Finish System111110 Days Following NTP
27Section 062000-Finish Carpentry General111110 Days Following NTP
28Section 079200-Joint Sealants111110 Days Following NTP
29Section 081113-Steel Frames111110 Days Following NTP
30Section 082000-Wood Doors111110 Days Following NTP
31Section 084010-Aluminum Doors and Frames111110 Days Following NTP
33Section 085800-Aluminum Sliding Windows111110 Days Following NTP
34Section 092550-Gypsum Board Assemblies111110 Days Following NTP
35Section 093013-Tile and Grout111110 Days Following NTP
36Section 093050-Tile Setting Materials and Accessories111110 Days Following NTP
37Section 095110-Acoustical Panel Ceilings111110 Days Following NTP
38Section 096500-Resilient and LVT Flooring111110 Days Following NTP
39Section 099100-Paint111110 Days Following NTP
40Section 099323-Stains and Transparent Finishes111110 Days Following NTP
41Section 123600-Countertops111110 Days Following NTP
42Section 099000-Painting and Coating111110 Days Following NTP
Section 102600-Wall Protection111110 Days After Issuance Of Award
41.1Section 124813-Entrance Floor Mats and Frames111110 Days After Issuance Of Award
43Mini-Split AC Set (1-CU, 2-Eus)111111Within 30 Days after Issuance Of AwardSee DWG M5.0

per DIAKUN Applied, McQuay.

Exhaust Hood, Exhaust Fan
GOVERNMENT FURNISHED
OA Make-Up Unit, OA Fan, HC, CC, Damper, Filter, Controller
GOVERNMENT FURNISHED
44HVAC RECT, RECT duct & fittings …
Low Pressure111110 Days After Issuance Of Award
45HVAC RECT, RND GREASE duct & fittings … Low Pressure111110 Days After Issuance Of Award
46HVAC Duct Insulation111110 Days After Issuance Of Award
47MAU HW & CHW Coil Paks111110 Days After Issuance Of Award
48HVAC duct accessories

volume/control/back-draft dampers, SA diffusers, RA grilles, OA & EA Louvers, Smoke Filter 1 1 1 1 10 Days After Issuance Of Award

49 Plumbing Fixtures Drop-In Sink, Faucet, and

Ice StationGOVERNMENT FURNISHED
50HW Piping, Fittings, & Valves111110 Days After Issuance Of Award
51Potable HFW & CFW Piping,
Fittings, & Valves111110 Days After Issuance Of Award
52Drain & Vent Piping, Fittings (PVC)111110 Days After Issuance Of Award
53HW and HFW Piping Insulation111110 Days After Issuance Of Award
54Mini-Split AC Unit
Refrigerant Piping111110 Days After Issuance Of Award
55Refrigerant Piping Insulation111110 Days After Issuance Of Award

54 HVAC Control VAV box damper set, Exhaust Hood Fan & FP/Alarm System, OA Make-Up Unit Fan, HW & CHW Coils, OA & EA Dampers, OA & EA filter DP sense/alarm 1 3 3 3 3 Days After Test

55Drain & Vent System
Gravity Leak Test13333 Days After Test
56HW System P-Test Report333 Days After Test3-hard copy, 3-digital copy
57HW System
Balance / Op Test Report3333 Days After Test3-hard copy, 3-digital copy
58Potable HFW & CFW System
P-Test Report333 Days After Test3-hard copy, 3-digital copy
59Potable Water System Disinfection
Test & Analyze13333 Days After Test3-hard copy, 3-digital copy
60CHW System P-Test Report333 Days After Test3-hard copy, 3-digital copy
60CHW System
Balance / Op Test Report3333 Days After Test3-hard copy, 3-digital copy
61HVAC Air Balance Test

AHU 1, B6732 1st Floor TU1-7A VAV Box Set SA, RA in corridor

RA Dining Areas13333 Days After Test3-hard copy, 3-digital copy
62HVAC Air Balance Test

Exhaust Hood, OA Make-Up Unit,

1st Floor13333 Days After Test3-hard copy, 3-digital copy
63Exhaust Hood FP & Alarm System
Op Test Report13333 Days After Test3-hard copy, 3-digital copy

64 Electrical Power Cable, Conduit, Receptacles,

Breakers, Panels, Safety Switch, Controllers1111110 Days After Issuance Of Award
65Electrical Lighting
Cable, Conduit, P-Devices, Fixtures1111110 Days After Issuance Of Award
66Fire Alarm Items111110 Days After Issuance Of Award
67Operation & Maintenance Manuals13333 Days After Test3-hard copy, 3-digital copy
Operation & Maintenance Manuals

Kitchen Exhaust Hood Make-Up Air Unit

Kitchen Service EquipmentGOVERNMENT FURNISHED
68Warranty (Manufacturer's)33End of Contract3-hard copy, 3-digital copy
Warranty (Manufacturer's)

Kitchen Exhaust Hood Make-Up Air Unit Kitchen Service Equipment GOVERNMENT FURNISHED

&"Verdana,Bold"&12Schedule of Material Submittals &12Print on Legal size paper ( 8 x 14 ).

&P of &N