Attachment 12 - Questions and Answers.pdf
PDF 154 KB Posted
- Attached to
- Fire Alarm Systems Replacement Federal contract opportunity
- Solicitation number
- FA301022R0009
About this file
This document contains questions and answers related to a solicitation for fire alarm system replacement services at Dolan Hall on Keesler Air Force Base. The solicitation is a Service-Disabled Veteran-Owned Small Business set-aside between $500,000 and $1,000,000. An organized site visit will be held on March 15, 2022 at 10:00 am CST, requiring valid identification and vehicle documentation to enter the base. The work includes core drilling corridor and penthouse walls, which can be done during normal work hours, and allowing the contractor to work a 10-hour, 4-day schedule. Existing conduit and 120V circuits powering the current system can be reused, but the existing panels must be located in Room 150, not Room 114 as previously stated. While a NICET Level IV certification is the highest for fire alarm systems, a fire protection engineer is required rather than NICET for this project.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment FA301022R00090001 SF 30.pdf | ||
| Replace Fire Alarm Systems Sign In Sheet.pdf | ||
| Attachment 9 - SF 1444.pdf | ||
| Attachment 2 - Specifications_UFCs 20190510.pdf | ||
| Attachment 4 - MSS 20220217.xls | XLS spreadsheet | |
| Attachment 11 - Notice of Compliance.pdf | ||
| Solicitation - FA301022R0009.pdf | ||
| Attachment 5 - Submittal Procedures 20220217.pdf | ||
| Attachment 6 - Wage Det MS20220050 20220218 Rev1.pdf | ||
| Attachment 7 - Past Performance Reference List.pdf | ||
| Attachment 10 - Brand Name JA 20220225.pdf | ||
| Attachment 3 - DWG 20220217.pdf | ||
| Attachment 8 - Past Performance Questionnaire.pdf | ||
| Attachment 1 - SOW 20220217.pdf |
Show all 14
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replace Fire Alarm Systems
MAHG20‐1109
Q&A’s Solicitation # FA301022R0009
1. This building will require a great deal of core drilling to penetrate the extra thick walls in the corridors and the six penthouses: Core drilling can be very noisy and disruptive: Can this task be done during normal work hours? YES
2. Will we be able to work this building on a 10hr. 4‐day week? YES
3. Can the existing conduit be reused for the new system? NO
4. Can we use the existing 120V circuits powering the existing system? YES THAT WILL BE DISCUSS
AT THE TIME OF THE TEST
5. Can cover plates be used to cover the back boxes in the walls where the old horns and strobes were located in lieu of patching the drywall? YES, BUT IF IT DOES NOT COVER COMPLETELY
THEN YOU MUST PATCH
6. In the SOW, under 3.2.4.3 PROVIDE AND INSTALL NEW:, #11 states, “The new panels to be located in Room 114”. During the site visit, it was discovered that room 114 was not an acceptable area to install new panels. Please provide correct room number for which the panels are located. RM 150 WHERE THE EXISTING PANEL IS
7. Would a NICET Level IV Engineer would be acceptable in lieu of a “Fire Protection Engineer (FPE).” NICET is the Global leader in providing qualified technology professionals who reliably apply engineering principles and practices for fire and life safety systems. A NICET Level IV is the highest level NICET certification for fire alarm systems, requiring a minimum of 10 years in fire detection systems and management, demonstrating a senior responsibility for fire alarm projects of substantial complexity. Please confirm if a NICET IV will be accepted in lieu of the
FPE. NO