See Attachment 1 - Maintain Exterior Various Facilities SOW R1.

View the file

Other files for this federal contract opportunity

Show all 16

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

2 July 2019

STATEMENT OF WORK FOR W/O 82021

MAHG19-1042

Repaint Exterior Wall of Various Facilities BUILDING # - 4605, 4231, 6005, 6006 Carwash, 4002, 6965, 7404, 7420

1.0 INTRODUCTION:

Keesler AFB has a requirement for a Contractor to provide services to repaint the Exterior Walls of Various Facilities; Building # - 4605, 4231, 6005, 6006 Carwash, 4002, 6965, 7404, and 7420. The Service provider shall furnish all necessary equipment, labor, supervision and materials specified in this Contract. All work is to be performed in accordance with this specification and is subject to the terms and conditions of this contract and as specifically cited in the Contractor’s Proposal to the Contracting Officer.

2.0 ACRONYMS/DEFINITIONS:

CO – Contracting Officer KW- Kilowatts

BAS - Building Automation System MDEQ - MS Dept. of Environmental Quality

BTUH - BTU per Hour PM - Project Manager CEV- Civil Engineering Environmental SOW - Statement of Work CPG - Comprehensive Procurement Guide CM - Contract Monitor

GPM - Gallons per Minute TAB - Test, Adjust and Balance HWR -Hot Water Return USDA - US Department of Agriculture HWS -Hot Water Supply 81 CES/CEN - Civil Engineering

3.0 TASK DESCRIPTION:

3.1 LOCATION: This contract is to be performed at:

Building 4605: Contracting, Pass Registration & Visitor Reception Center Building 4231: Training Center Chiller Plant Building 6005: Auto Hobby Shop Building 6006: Carwash at Auto Hobby Shop Building 4002: Taylor Logistics Building Building 6965: Foster Manor - Triangle Student Dormitory Building 7404: Winter Manor– Triangle Student Dormitory Building 7420: Erwin Manor – Triangle Student Dormitory

* Building should be cleaned according to Keesler AFB Standards for each particular building material.

29 May 2019

3.2 DESCRIPTION OF WORK:

3.2.1 Contractor is required to examine the site and make note of all requirements of the Work before submitting any bids. Any accessories or incidental items not specifically shown on the Drawings and detailed in the Statement of Work herein, which are necessary and/or required to complete the work within the intent of these documents, shall be included by the Contractor without additional cost to the Government. All work shall be performed in strict accordance with the SOW/specifications/plans and drawings and subject to the terms and conditions of the contract.

3.2.2 Utilities for the work will be provided by the Government unless otherwise noted.

3.2.3 It is anticipated that hazardous material will be encountered during the course of work. However, should such material be encountered, the Contractor is to immediately stop work and contact the Contracting Officer. All hazardous material will be dealt with according to paragraphs 4.6, 4.7, 4.8 of this Statement of Work.

Building 4605 – LBP – metal hand-railing and metal door casings (brown) were positive for LBP.

3.2.4 SCOPE: Repaint Exterior Walls of Various Facilities

• Building 4605: Contracting, Pass Registration & Visitor Reception

Center

• Building 4231: Training Center Chiller Plant

• Building 6005: Auto Hobby Shop

• Building 6006: Carwash at Auto Hobby Shop

• Building 4002: Taylor Logistics Building

• Building 6965: Foster - Triangle Student Dormitory

• Building 7404: Winter – Triangle Student Dormitory

• Building 7420: Erwin Manor – Triangle Student Dormitory

REMOVE EXISTING:

Building 4605 – Contracting, Pass Registration & Visitor Reception Center

1. Remove mold, dirt, mildew, and/or algae from building exterior surfaces – all walls (brick, EIFS, CMU), windows, bollards, doors, louvers, lights, signs, ramps, handrails, sidewalks, and roof.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Building should be cleaned according to Keesler AFB Standards for each particular building material.

a. Pressure wash exterior surface with water only. Use care to prevent damage, or further damage from occurring to exterior surfaces.

Building 4231 – Training Center Chiller Plant

1. Remove mold, dirt, mildew, and/or algae from building exterior surfaces – all walls (brick, EIFS, CMU), doors, louvers, lights, signs, sidewalks, and roof.

2. Remove rust from overhangs and/or other metal surfaces – railings and door frames, etc.

3. Remove damaged stucco, and repair chips and/or cracks in its entirety.

4. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

5. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 6005 – Auto Hobby Shop walls (brick, EIFS, CMU), windows, bollards, doors, louvers, lights, signs, sidewalks, and roof.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 6006 – Carwash at Auto Hobby Shop walls (brick, EIFS, CMU), bollards, doors, louvers, lights, signs, sidewalks, and roof.

2. Remove rust from overhangs and/or other metal surfaces – door frames, etc.

3. Remove damaged stucco, and repair chips and/or cracks in its entirety.

4. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

5. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 4002 – Taylor Logistics Building walls (precast concrete panels (pebble dashed aggregate), rubbed concrete (bldg.

skirt), CMU), windows, planters, doors, louvers, lights, signs, ramps, handrails, sidewalks, canopy overhangs, drainage grates, and loading docks.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Remove chipped and peeling paint from building exterior and surrounding surfaces (planters, handrails, stairs, etc.)

7. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 6965 – Foster Manor Triangle Student Dormitory walls (brick, EIFS, CMU), windows, planters, doors, louvers, lights, signs, ramps, handrails, and sidewalks.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety. Use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (Cream) not found.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 7404 - Winter Manor Triangle Student Dormitory walls (brick, EIFS, CMU), windows, planters, doors, louvers, lights, signs, ramps, handrails, and sidewalks.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety. Use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (Cream) not found.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Building should be cleaned according to Keesler AFB Standards for each particular building material.

Building 7420 – Erwin Manor Triangle Student Dormitory walls (brick, EIFS, CMU), windows, planters, doors, louvers, lights, signs, ramps, handrails, and sidewalks.

2. Remove dirt and grime from windows.

3. Remove rust from overhangs and/or other metal surfaces – railings, window and door frames, etc.

4. Remove damaged stucco, and repair chips and/or cracks in its entirety. Use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (Cream) not found.

5. Remove dirt from light fixtures (fixtures and lens). Remove fixture (to clean) only as necessary.

6. Building should be cleaned according to Keesler AFB Standards for each particular building material.

a. Pressure wash exterior surface with water only. Use care to prevent damage, or further damage from occurring to exterior surfaces.

MODIFY EXISTING:

Building 4605 - Contracting, Pass Registration & Visitor Reception Center

1. Repair and restore chips and cracks in EIFS/stucco; use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (cream) not found).

2. Fill small cracks and voids in concrete, cinder block, and rough masonry (brick).

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where EIFS/stucco is damaged and lath is exposed, patch with new stucco. If rust is on lath remove and replace with new lath to seal the exposed area and patch with new EIFS/stucco.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean dirty light fixtures (fixture and lens). Remove fixture (to clean) only as needed.

7. Remove mold and mildew from brick and mortar joints, without damage to brickwork and surrounding vegetation, and return to original state. Buildings should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from rollup doors.

9. Remove rust with a wire brush, and repaint handrails at accessible ramps and stairs.

10. Sand and repaint handrails at accessible ramps and stairs.

Building 4231 - Training Center Chiller Plant

1. Repair and restore chips and cracks in EIFS/stucco; use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (cream) not found).

2. Fill small cracks and voids in concrete, cinder block, and rough masonry (brick).

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where EIFS/stucco is damaged and lath is exposed, patch with new stucco. If rust is on lath remove and replace with new lath to seal the exposed area and patch with new EIFS/stucco.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean dirty light fixtures (fixture and lens). Remove fixture (to clean) only as needed.

7. Remove mold and mildew from brick and mortar joints, without damage to brickwork and surrounding vegetation, and return to original state. Buildings should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from rollup doors.

9. Remove rust with a wire brush, and repaint metal gate doors.

Building 6005 – Auto Hobby Shop

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry. Ultra

Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C

#37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing, or equal. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 6005 – Carwash at Auto Hobby Shop

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry. Ultra

Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C

#37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing, or equal. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

b. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 4002 – Taylor Logistics Building

1. Repair and restore chips and cracks in precast concrete panels (pebble dash stucco).

2. Repair small cracks and voids in concrete (bldg. skirt), cinder block, and rough masonry. Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where stucco is damaged, patch with new stucco and seal the exposed area.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

7. Remove mold and mildew from building surfaces, without damage to building surface and surrounding vegetation, and return to original state. Building should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from rollup doors.

9. Remove chipped and peeling paint from building’s exterior surfaces (planters, handrails, stairs, etc.)

10. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

11. Paint exterior doors; color to match existing, or equal. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

Building 6965 – Foster Manor Triangle Student Dormitory

1. Repair and restore chips and cracks in EIFS/stucco; use color-matched exterior acrylic caulk to seal cracks and chips (match similar, or equal, if color (cream) not found).

2. Fill small cracks and voids in concrete, cinder block, and rough masonry (brick).

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where EIFS/stucco is damaged and lath is exposed, patch with new stucco. If rust is on lath remove and replace with new lath to seal the exposed area and patch with new EIFS/stucco.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean dirty light fixtures (fixture and lens). Remove fixture (to clean) only as needed.

7. Remove mold and mildew from brick and mortar joints, without damage to brickwork and surrounding vegetation, and return to original state. Buildings should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from building exterior surfaces – walls, windows, planters, doors, louvers, lights, signs, and overhangs.

Building 7404 - Winter Manor Triangle Student Dormitory

1. Repair and restore chips and cracks in EIFS/stucco; use color-matched exterior acrylic caulk to seal cracks and chips (match similar, or equal, if color (cream) not found).

2. Fill small cracks and voids in concrete, cinder block, and rough masonry (brick).

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where EIFS/stucco is damaged and lath is exposed, patch with new stucco. If rust is on lath remove and replace with new lath to seal the exposed area and patch with new EIFS/stucco.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean dirty light fixtures (fixture and lens). Remove fixture (to clean) only as needed.

7. Remove mold and mildew from brick and mortar joints, without damage to brickwork and surrounding vegetation, and return to original state. Buildings should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from building exterior surfaces – walls, windows, planters, doors, louvers, lights, signs, and overhangs.

Building 7420 – Erwin Manor Triangle Student Dormitory

1. Repair and restore chips and cracks in EIFS/stucco; use color-matched exterior acrylic caulk to seal cracks and chips (match similar if color (cream) not found).

2. Fill small cracks and voids in concrete, cinder block, and rough masonry (brick).

3. Replicate texture of surrounding stucco in damaged areas; in repaired areas, match existing.

4. In areas where EIFS/stucco is damaged and lath is exposed, patch with new stucco. If rust is on lath remove and replace with new lath to seal the exposed area and patch with new EIFS/stucco.

5. Fill all nail holes and patch area so that material adheres and blends in with existing building. Patch up to 250SF of damaged walls, prior to painting. Notify contracting officer if additional patching required exceeds 250 SF.

6. Clean dirty light fixtures (fixture and lens). Remove fixture (to clean) only as needed.

7. Remove mold and mildew from brick and mortar joints, without damage to brickwork and surrounding vegetation, and return to original state. Buildings should be cleaned according to Keesler AFB standards for each particular building material.

8. Remove mold, dirt, mildew, and grime from building exterior surfaces – walls, windows, planters, doors, louvers, lights, signs, and overhangs.

PROVIDE AND INSTALL NEW:

Building 4605 – Contracting, Pass Registration & Visitor Reception

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

7. Paint handrails at accessible ramps and stairs with a heavy duty paint (2 coats);

(Color: Medium Bronze) or equal.

Building 4231 – Training Center Chiller Plant

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing. (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec

500/Latex/High Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

7. Paint handrails at accessible ramps and stairs with a heavy duty paint (2 coats);

(Color: Medium Bronze) or equal

Building 6005 – Auto Hobby Shop

1) Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream) or equal.

2) Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3) Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4) Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze) or equal.

5) Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec

500/Latex/High Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6) Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 6005 – Carwash at Auto Hobby Shop

1) Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2) Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3) Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4) Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5) Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec

500/Latex/High Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6) Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 4002 – Taylor Logistics Building

1) Repair and Paint building skirt/wall below precast concrete panel; Paint color

Medium Bronze, or equal, to match Keesler AFB Standards.

2) Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3) Paint planters, building overhangs, and stairs. Paint color Medium Bronze, or equal, to match Keesler AFB Standards.

4) Sand and Paint overhangs - aluminum window & door frames; Paint color Medium Bronze, or equal, to match Keesler AFB Standards.

7) Paint exterior doors; color to match Medium Bronze, or equal. Use a rust inhibitor primer on metal doors, frames, and overhangs.

d. Do NOT paint roll-up doors; Paint metal frames only.

e. Metal Door Paint color: Benjamin Moore Ultra Spec

500/Latex/High Gloss, or equal.

f. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

8) Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

9) Paint handrails at accessible ramps and stairs with a heavy duty paint (2 coats);

Paint Color Medium Bronze, or equal, to match Keesler AFB Standards.

Building 6965 – Foster Manor Triangle Student Dormitory

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 7404 – Winter Manor Triangle Student Dormitory

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color - US

Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

Building 7420 – Erwin Manor Triangle Student Dormitory

1. Repair and Paint all stucco/EIFS walls; color to match existing. Paint color -

US Govt. Fed Std. 595C #37769 (Cream), or equal.

2. Repair small cracks and voids in concrete, cinder block, and rough masonry.

Ultra Spec Masonry Elastomeric Waterproof Coating Low Lustre (360), or equal.

3. Paint bollards; color to match existing. Paint color - US Govt. Fed Std. 595C #37769 (Cream), or equal.

4. Sand and Paint overhangs - aluminum window & door frames; color to match existing (Color: Medium Bronze), or equal.

5. Paint exterior doors; color to match existing. Use a rust inhibitor primer on metal doors, frames, and overhangs.

a. Do NOT paint roll-up doors; Paint metal frames only.

b. Metal Door Paint color: Benjamin Moore Ultra Spec 500/Latex/High

Gloss, or equal.

c. Exterior Paint – Benjamin Moore Block Seal, or equal, as primer (1 coat) and finish coat(s) (2 coats). All patches to be primed first before receiving finish coats.

6. Clean exterior lighting (fixture and lens). Remove fixture (to clean) only as needed and return fixture to exact location (if removed).

• ATTACHED SPECIFICATIONS AND DRAWINGS:

3.2.5 Reference AF Form 66 Schedule of Material Submittals for submittals that must be approved. The Contractor shall provide all items listed on AF 66 on the AF Form 3000 Material Approval Submittal. Item number on the AF Form 3000 must match the same Item number listed on the AF Form 66.

3.2.5.1 All submittal documents received that do not clearly delineate and display the information which is being submitted will be returned to the Contractor.

3.2.5.2 The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory, to meet the Solicitation and Accepted Proposal. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist.

3.2.6 Material: All material furnished by the Contractor for this job shall be new and unused material of high quality unless otherwise noted. The Contractor is responsible for the proper storage of all material until it is installed.

3.3 PERFORMANCE TIME: 45 Days after the ‘Notice to Proceed’ has been signed.

3.3.1 No Work shall begin until all Submittals related to that work have been received and approved.

3.3.2 Punch list items noted in the closeout process shall be fixed before the end of the

Period of Performance or the project will be considered past due.

3.4 PERFORMANCE OF WORK:

3.4.1 Services shall be conducted in conformity with applicable regulations to contribute maximum satisfaction to responsible base offices. All work shall be done in a neat and workmanlike manner and in keeping with generally accepted standards for similar work. Services shall be made with minimum divergence from schedules once established. All services shall be made with minimum disturbance and maximum protection of property. The CM shall be notified 72 hours prior to work starting.

3.4.2 The Contractor must within 24 hours of notice that a delay will be incurred notify the Contracting Officer in writing. This letter must identify why there will be a delay, and how long. Also the Contractor shall take any actions in his control to prevent delay from occurring.

3.4.3 In order to complete the work on this job, certain Government -owned facilities may have to be removed or altered in some way and others may be inadvertently damaged. It is the responsibility of the Contractor to return these facilities to a condition acceptable to the Contracting Officer.

3.4.3.1 Damage to located underground utilities will be repaired at the Contractor’s expense. Repairs shall replace the damaged section “in kind” for storm, sanitary, gas, and water; or replace the entire run to the current standard in the case of communication or electrical.

3.5 JOBSITE MAINTENANCE AND STORAGE AREAS: The Contractor shall maintain the jobsite and staging areas in conformance with Keesler standards.

3.5.1 Lay down/staging areas shall be kept neat and free of loose debris at all times.

Grass shall be cut and maintained regularly. Height and maintenance shall be consistent with normal Base standards and consistent with the immediate area.

3.5.2 Jobsites and lay down/staging areas shall be enclosed with a 6’ chain link fence with brown fabric screening unless otherwise noted. Materials and equipment may be stored inside storage units. Items stored in the lay down area shall be arranged neatly.

3.5.3 All temporary storage trailers and storage containers shall present a neat and clean appearance and shall be in a state of good repair and shall be located within the fenced area described in paragraph above.

3.5.4 If allowed by the contract and if approved by the Contracting Officer, an office mobile unit may be located outside of a fenced area. At a minimum, this unit shall be in a paved area and shall present a neat, professional appearance. Unit shall be of Keesler standard colors, shall have presentable skirting and access stairs.

Ancillary items, such as porches and canopies, shall be neat and painted Keesler brown. Contractor shall submit a picture of the proposed unit for approval and before unit is moved to Base.

3.5.5 Execution of work may require excavation or other type of work both at and away from primary work area. These areas shall be secured and work times shall be kept to a minimum. Open excavations shall be directly in progress or shall be covered directly after work complete. Open excavations requiring extended period of inactivity shall be temporarily backfilled. In no case shall an excavation be open for more than 72 hours. Barricades, fences and other warning devices shall be maintained neatly at all times.

3.5.6 The Contractor shall maintain the premises, including any staging area or storage areas, free from accumulations of waste, debris, and rubbish caused by the Contractor’s work and shall minimize the spread of dust and flying particles. As work is completed, or at the end of each day, the site shall be cleaned and all waste material shall be properly disposed of properly.

3.5.7 Should warnings of winds of gale force or stronger be issued, the Contractor shall take every practical precaution to minimize danger to persons and damage to property. These precautions shall be coordinated through the Contracting Officer and shall include closing all openings; removing all loose materials, tools, and equipment from exposed locations; as well as removing or securing scaffolding and other temporary work. Contractor will follow Keesler AFB requirements for Hurricane Conditions in force.

3.6 SUPERVISION: Contractors shall provide competent supervision familiar with the project and within 15 minutes of the project site at all times when work is in progress.

Contractor is responsible for scheduling and coordinating various trade activities.

Contractor is also responsible for assuring that all work accomplished and materials used are in accordance with industry standards.

3.7 ACCESS: The Contracting Officer shall have access at any and all times to the Contractor's equipment, materials, supplies, assigned areas and sites of operation for inspection purposes.

3.8 HOURS OF OPERATION: The Contractor will be able to accomplish this work between the hours of 7:00 AM and 5:00 PM. The Contractor will not normally be permitted to work on weekends or on the following legal holidays (or the day the Federal Government observes these holidays) unless he has coordinated such work with the sub-contract representative at least seventy-two (72) hours in advance:

New Year's Day Labor Day Martin Luther King, Jr.'s Birthday Columbus Day Washington's Birthday Veteran's Day

Memorial Day Thanksgiving Day Independence Day Christmas Day

The following days are not legal holidays but may require work stoppage:

Special Olympics- Thursday through Sunday of First NON-Training weekend in May

3.9 PERMITS:

3.9.1 Contractors will be required to obtain permits as required by Keesler in the performance of their work. Contractors shall post or have readily available all permits before work is commenced

3.9.1.1 The following permits must be obtained anytime referenced work is required.

DIG PERMIT, Vectrus Customer Service BURN PERMIT, Keesler AFB Fire Department CONFINED ENTRY PERMIT, (certified personnel only)

Obtain permit from Vectrus CM or Safety Office. Notification to Fire Department of actual day and time work is accomplished.

3.10 INTERRUPTION OF SERVICES:

3.10.1 If interruption of any building utility services such as but not limited to the following, chilled water, electrical power, domestic water, fire protection water supply, or communications etc. Are required, the Contractor shall perform the work on normal work week hours after receiving approval, during the weekend, or on non-training Fridays. The Contractor shall coordinate the interruption of the utilities 14 days in advance with the SM and user regardless of the option chosen.

The Contractor shall include any additional cost of performing the work in their original bid.

3.10.2 The Contractor shall fill out a “utility service outage request form” and submit it to the contracting officer. The contracting officer may require the Contractor to attend a coordination meeting to assess the purpose, intent, and impact of the outage request with the facility and any or all operations departments. Contractor s shall not shut-down or start-up any mechanical, electrical and/or plumbing system without the coordination and/or permission of the contracting officer.

3.11 JOBSITE SAFETY:

3.11.1 The Contractor shall take all necessary and prudent safety precautions to ensure the safety of the workforce and other exposed personnel. The Contractor shall observe all Safety, Security, Traffic and Fire regulations presently enforced at Keesler Air Force Base and comply with latest issue of OSHA requirements.

Contractors shall comply with the Occupational Safety and Health Act (OSHA, Public Law 91-596) and the resulting standards, OSHA Standards 29 CFR 1910 and 1926. The detailed provisions of the act for accident prevention are directly applicable to all Contractor operations. Prime Contractors are also responsible for ensuring any Contractors also adhere to OSHA Guidance. OSHA compliance officers can visit Contractor worksites on the installation.

3.11.2 Contractors are responsible for ensuring all industrial safety provisions are followed. Take immediate corrective action to comply with safety regulations if informed of a violation by the contracting officer.

3.11.3 Contractors must report all accidents involving Air Force people, property, or equipment damage, and any Contractor personnel injured in the performance of the air force contract to the contracting officer.

3.11.4 Contractor shall comply with all aspects of the National Fire Protection Association (NFPA) Standard 241, "Standard For Safeguarding Construction, Alteration, And Demolition Operations," current edition, and United Facilities Criteria (UFC) 3-600-01, “Fire Protection Engineering For Facilities,” current edition.

3.11.5 Provide safety protection and precautions for any electrical exposure. Temporary lighting shall have metal cages around the lamp and shall be turned off when not in use and no fire watch is present.

3.11.6 Ground Fault Circuit Interrupters: Whenever Contractor uses portable electrical tools or equipment in an outside location where operator will be in contact with a grounded surface or in an interior wet location where floor is conductive such as concrete, Contractor shall provide and use a portable ground fault circuit interrupter (GFCI). This shall apply wherever electric power is supplied through government-owned facilities. Contractor shall be responsible for maintaining the GFCI in operating condition and testing it before each use.

3.12 PASSES:

3.12.1 Contractor Notification Responsibilities: The Contractor shall provide a written notification to the Contracting Officer. The notification shall include the names and contact information (address, phone number, and email) of a minimum of two Contractor representatives (preferably the contracting agent and the project supervisor) that will be responsible for this project and have 24 hour contact availability to answer any questions or address any issues that may arise that are related to this project.

3.12.2 Passes for Contractor employees may be requested through the assigned CM.

Requests shall include full name of employee as it appears on their identification, length of pass needed (up to 30 days), and days needed (if other than standard working hours).

3.12.3 Paperwork required for passes:

3.12.3.1 For vehicle operators: 1] Current driver license for each employee in support of work on Keesler AFB. Individuals will no longer be able to access Air Force installations with a state-issued identification card or driver’s license from Minnesota, Missouri, Washington or American Samoa. 2] Vehicle Registration and Proof of Insurance.

3.12.3.2 For non-vehicle operators: Current driver license, official ID card, or passport. Individuals will no longer be able to access Air Force installations with a state-issued identification card or driver’s license from Minnesota, Missouri, Washington or American Samoa.

3.13 REPORTING REQUIREMENTS: The Contractor shall comply with AFI 71-l0l, Volume1, Criminal Investigations and Volume-2, Protective Service Matters, requirements. Contractor personnel shall report to an appropriate authority, any information or circumstances of which they are aware may pose a threat to the security of DOD personnel, Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment and as required thereafter.

3.14 PHYSICAL SECURITY:

3.14.1 Areas controlled by Contractor employees shall comply with Base Operations Plans/instructions for THREATCON procedures, Random Antiterrorism Measures (RAMS) and local search/identification requirements. The Contractor shall safeguard all government property, including controlled forms, provided for Contractor use. At the close of each work period, government training equipment, ground aerospace vehicles, facilities, support equipment, and other valuable materials shall be secured.

3.14.2 The Contractor shall not employ persons for work on this contract if such employee is identified by the government or BOS Contract officials as a potential threat to the health, safety, security, general well-being or operational mission of the installation and its population.

3.15 VEHICLE SAFETY AND TRAFFIC LAWS:

3.15.1 The Contractor and its employees shall comply with base traffic laws and regulations.

3.15.2 The Contractor shall ensure employees have a current and valid driver’s license and commercial permits/licenses for the type of vehicle operated, before allowing the employee to operate a Contractor-owned or rental vehicle on Keesler AFB.

3.15.3 The Contractor shall provide all vehicles to perform the requirements of the contract. All vehicles shall be in operable condition and meet local, state and federal safety requirements, and be specifically designed for the purpose intended for use. Vehicles shall have, clearly visible on each side, the Contractor company name, a unique vehicle identification number, in addition to all required Department of Transportation (DOT) markings and information.

3.15.4 Air Field Driving: All Contractors must receive airfield drivers training prior to receiving notice to proceed or prior to driving on the airfield IAW (AFI 13-213, 2.1.3.39.7.) This training will be provided by Airfield Management at B0233 PH:

228-377-2215.

3.15.5 Cellular Phones: The use of cellular phones while operating a vehicle is prohibited while on Keesler AFB property.

3.16 FREEDOM OF INFORMATION ACT PROGRAM (FOIA): The Contractor shall comply with DOD5400.7-R_AFMAN 33-302, Freedom of Information Act Program (FOIA), and requirements. The regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding For Official Use only (FOUO) material.

4.0 ENVIRONMENTAL:

4.1 RECYCLED CONTENT AND BIO BASED PRODUCTS: Executive Order 13514 dated 5 Oct 09, outlines the federal government’s special responsibility to lead the way in building markets for recycled goods. Green procurement is the name given by the Air Force to this buy-recycled purchasing program. The intent of the program is to stimulate recycling by providing a market for new products manufactured with bio-based or recycled materials. The legal authority for the Green Procurement Program comes from the Resource Conservation and Recovery Act (RCRA) Section 6002. It requires federal agencies to give preference in their purchasing programs to products and practices conserving and protecting natural resources and the environment. If applicable, material and product submittals for all recycled-content items should list the recycled and recovered materials used and the percentage content (by weight).

Submittals for bio-based products should describe the bio-based materials used and the percentage content (by weight). This data is required to be submitted by the Contractor on an AF Form 3000 (Material Approval Submittal) to the Contracting Officer upon completion of performance (construction).

4.2 ENVIRONMENTAL PROTECTION: Contractor personnel shall, at all times, perform all work and take such steps required to prevent any interference or disturbances to the ecological balance of the environment. All work must be performed in accordance with applicable Federal, State, Local, and Air Force environmental regulations. Use good management practices to protect air, water, land and wildlife and to prevent noise, solid waste, radiant energy, dust and radioactive pollutants. In the event of a chemical or hazardous material spill, the Contractor must immediately notify the Keesler Fire Department at 911 (identify that you are located on Keesler AFB) and the Keesler BOS Contractor environmental representative at 228-377-1262.

4.3 WASTE MATERIALS: Unless otherwise specified, all waste materials, excess dirt and rubble, empty containers, etc., shall be disposed of at an approved off-base location in accordance with all applicable Federal, State, County and Municipal laws.

4.3.1 Solid Waste Management:

4.3.1.1 Designate individuals on the Contractor’s staff who are responsible for Construction and Demolition (C&D) waste prevention and management.

4.3.1.2 Develop procedures for collecting and storing C&D waste on project sites, including designating locations for waste containers, sorting or separating methods, handling and transporting of wastes, special handling requirements, and scheduling for waste and recycling collection.

4.3.1.3 Develop descriptions of how the C&D materials will be recycled or reissued. The information should include any on-site storage and processing areas and a description of the processing and equipment.

4.3.1.4 Records shall be maintained for all C&D projects to document the quantity of waste generated; the quantity of waste diverted through sale, reuse, or recycling; and the quantity of waste disposed by land filling or by incineration.

4.3.1.5 Contractors shall provide these records to the Contracting Officer in accordance with contract requirements.

4.3.1.6 In accordance with Executive Order 13514, Keesler AFB will divert 60% of all C&D waste.

4.3.1.7 Manage solid waste in accordance with the Keesler AFB Integrated Solid Waste Management Plan.

4.3.1.8 For any questions regarding solid waste, please contact VECTRUS/ CEV at 228-377-1262.

4.4 HAZARDOUS MATERIALS: In the event that hazardous materials will be used in the execution of this contract, the Contractor will be required to provide a list of materials, quantities, and Safety Data Sheets (SDS) to the Contracting Officer before work begins.

The hazardous materials must be approved through the Keesler Hazardous Materials Management Program prior to being brought onto Keesler AFB. This approval process may take up to two weeks, which should be considered in the performance period of this contract. Unless otherwise specified, all unused hazardous materials should be removed from the base at the end of the project.

4.5 STORM WATER MANAGEMENT: If ground disturbing activities will take place as part of this project, the following items must be completed:

4.5.1 For any construction activity greater than 5,000 square feet of ground disturbance, the Contractor shall comply with all provisions of the Energy Independence and Security Act (EISA) concerning storm water run-off from Federal development projects.

4.5.2 The construction Contractor shall complete all paperwork necessary, including the Storm Water Pollution Prevention Plan (SWPPP) to apply for the appropriate Large (>5 acres) or Small (>1 acre but <5 acres) Construction Storm Water General Permit (Permit) from the Mississippi Department of Environmental Quality (MDEQ).

4.5.3 The Contractor shall furnish Vectrus/CEV copies of the Permit application, SWPPP, Permit, confirmation letter from the MDEQ and any other pertinent storm water information related to the project.

4.5.4 The initial storm water permit application and original SWPPP shall be submitted to Vectrus/CEV for review and comment prior to or at the time of submittal to the

MDEQ.

4.5.5 The Contractor shall comply with all provisions of the Permit throughout the duration of the project.

4.5.6 Any construction site/land disturbance activity greater than 20,000 sq/ft, but < 1 acre shall have a SWPPP prepared and approved by Vectrus/CEV prior to construction or implementation of the land disturbance activity.

4.5.7 Any construction site/land disturbance activity greater than 20,000 sq/ft, but < 1 acre shall have a SWPPP prepared and approved by Vectrus/CEV prior to construction or implementation of the land disturbance activity.

4.5.8 The Keesler AFB Small Municipal Separate Storm Sewer System (MS4) Permit requires Keesler AFB to maintain a file for each construction site. The file must contain the storm water training credentials of all Contractor personnel involved in storm water management at each construction site.