Attachment_2_-_SOW_2_C2-D2-FOC_Fuels_Depot.pdf
PDF 3 MB Posted
- Attached to
- Fiber Optic Cable Installation Federal contract opportunity
- Solicitation number
- FA301018R0023_Fiber-Optic
About this file
Attachment 2 - SOW 2 C2-D2-FOC Fuels Depot
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amend_1.pdf | ||
| Addendum_1.pdf | ||
| Sign-In_Sheet.pdf | ||
| Attachment_6_-_Wage_Det_MS180141.pdf | ||
| Attachment_7_-_Notice_of_Compliance.pdf | ||
| Attachment_1_-_SOW_1_C2-D2-FOC_B-404_81_to_B223_ITN.pdf | ||
| Attachment_8_-_SF_1444.pdf | ||
| Attachment_5_-_Reference_List.pdf | ||
| Attachment_3_-_SOW_3_FOC_3501-1101.pdf | ||
| Attachment_4_-_Past_Performance_Questionnaire.pdf | ||
| FA301018R0023.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Page 1 of 33 For Official Use Only
STATEMENT OF WORK (SOW)
For
C2-DS-FOC to Fuel Depot B4407, B4414, B4419, and B4421 from B4705 Base Civil
Engineering
Keesler AFB, MS
23 APR 18
Prepared By
81 CS/SCXP
510 H Street, Keesler AFB, MS 39534
Attachment 2
FA3010-18-R-0023
Page 2 of 33 For Official Use Only
Table of Contents
1. SCOPE 4
2. REQUIREMENTS 4
2.1. GENERAL REQUIREMENTS 4
2.1.1. Safety Requirements 4
2.1.2. Site Coordination 4
2.1.3. Security Requirements 5
2.1.4. Environmental Compliance 6
2.1.5. Permits 6
2.1.6. Integrated Process Team (IPT) 7
2.1.7. Quality Assurance 7
2.1.8. Contractor Personnel 7
2.1.9. Warranty 8
2.1.10. Manuals and Practices 8
2.2. SPECIFIC REQUIREMENTS 8
2.2.1. Maintenance Holes (MHs) and Hand Holes (HHs) 9
2.2.2. Measurements 9
2.2.3. Underground Utilities Markings 9
2.2.4. Splice Conductors 9
2.2.5. Cable Racks and Cable Rack Supports 9
2.2.6. Labeling 9
2.2.7. Pulling Tape 10
2.2.8. Cable Terminations 10
2.2.9. FOC Maintenance Loop(s) 10
2.2.10. New Maintenance Holes/Hand Holes 10
2.2.11. New Maintenance Holes / Hand Holes Placement 11
2.2.12. Grounding 11
2.2.13. Underground Conduit System 11
2.2.14. Outside Plant Installation 14
2.2.15. Site Restoration/Debris Removal 18
2.2.16. Service Outages 18
2.2.17. Identification/Marking 18
2.2.18. Installation Schedules 18
2.2.19. Weekly Status Reports 18
2.2.20. As-Built Drawings 19
2.2.21. Test and Acceptance/Installation Test Plan 19
2.2.22. Acceptance/Installation Test Report 20
2.2.23. Final Acceptance 20
2.2.24. As-Built Documentation in CVC 20
3. GENERAL INFORMATION 20
3.1. Period of Performance 20
3.2. Place of Performance 20
3.3. Hours of Operation 20
3.4. Holidays/Down Days 21
3.5. Base Support 21
3.6. Minimum Contractor Qualifications. 21
APPENDIX A: APPLICABLE STANDARDS 22
APPENDIX B: LIST OF DELIVERABLES 23
APPENDIX C: LIST OF ACRONYMS 24
APPENDIX D: DRAWINGS 26
Page 3 of 33 For Official Use Only
1. SCOPE
This SOW defines the requirement for the Contractor to engineer, furnish, install and test (EFI&T) single mode (SM) fiber optic cable (FOC), including associated terminating equipment and infrastructure to connect existing Communication Maintenance Hole Conduit System (CMHDS) to new CMHDS between the Fuels Depot buildings, building B-4407, B-4414, B4419, and B-4421 to the Base Civil Engineering Building (B-4705). The Contractor shall provide all equipment, tools, materials, supplies, transportation, labor, supervision, management, and other incidentals necessary to meet the requirements as stated in this SOW; no equipment, supplies, or material, will be provided by the government. All equipment, supplies, or materials installed as part of the Customer-
Owned Outside Plant Telecommunications Infrastructure shall be new and not refurbished, and must be rustproof and corrosion-resistant, due to the nature of the environment.
2. REQUIREMENTS
2.1. GENERAL REQUIREMENTS
2.1.1. Safety Requirements
The contractor shall remain in compliance with all Federal, State, and Base security and safety laws, regulations, policies, and requirements.
2.1.2. Site Coordination
The Contractor shall meet with the base safety officer immediately upon arrival on site for review of the specific safety requirements prior to installation.
2.1.2.1. Confined Space
The Contractors and Sub-contractors entering spaces on Keesler AFB (KAFB), MS are responsible for the safety of their personnel and for their own confined space program as outlined in local, state, federal (OSHA CFR 29 Part 1910-268) compliance standards. The
Primary Contractor (Prime) is responsible for all sub- contractor confined space operations. The
Contractor shall notify the KAFB Fire Department on-duty dispatch controller twenty four (24) hours prior to entering any maintenance hole, if emergency services assistance is desired.
2.1.2.2. Accident/Incident Reporting and Investigation
The Contractor shall record and report all available facts relating to each instance of injury to either Contractor or Government personnel to the Base Safety Office. The Contractor shall secure the scene of any accident and wreckage until released by the accident investigative authority through the Base POC. If the Government elects to conduct an investigation of the incident, the Contractor shall cooperate fully and assist the Government personnel until the investigation is completed.
2.1.2.3. Work Area(s)
At day’s end, the Contractor shall remove all debris and surplus materials from the work place.
Safety barriers shall be in place to protect unfinished work site at the end of the day. All open holes or trenches shall be completely enclosed by flexible orange construction safety fencing, or other safety barriers, at the end of the work day. Equipment and materials required to complete the work effort may remain on site as long as they are organized/stored in a manner that does not
Page 4 of 33 For Official Use Only cause a safety hazard.
Under no circumstances will any equipment or materials be left unattended within the designated
Keesler AFB Controlled Movement Area (CMA) at any time. The Contractor’s designated on-site project manager will maintain two-way radio contact with the Keesler Air Traffic Control
(ATC) Tower at all times during construction work within the CMA. Two-way radios/LMRs will be provided by the government. On work sites outside the base perimeter, the Contractor shall coordinate with (and abide by the requirements of) the appropriate local, state, and federal agencies to ensure work areas are safe at day’s end.
Due to safety of the aircraft, FOD is a vital concern. Work debris and equipment ejections/outflow must be directed away from the flight line when working nearby the flight line.
2.1.2.4. Traffic control
In the event base vehicular traffic is to be disrupted by trenching or horizontal directional boring, the Contractor shall make appropriate notifications NLT 10 calendar days in advance to inform
Base Security Forces and Emergency Services personnel of the planned disruptions.
2.1.3. Security Requirements
The Contractor shall process and provide a Site Visit Request Letter to 81 CS/SCXP PM within
5 calendar days after contract award. This letter and supporting spreadsheet shall identify the names (as shown on the driver’s license), driver’s license numbers, SSN, state of issue, birth date of the personnel who will be performing work under this SOW, company name, address, phone number and contract number, start and end date. This information is required to grant access to the base. If required by the base, the Contractor shall provide identification badges for their employees. All Contractor personnel shall wear these badges while on duty on the
Government site. The badges shall identify the individual, company name, and be clearly and distinctly marked as Contractor and be in accordance with base regulations
2.1.3.1. Security Clearances
Stated work and associated products shall be performed at the UNCLASSIFIED level. However, some of this work will take place in secure areas where Contractor employees must be escorted at all times. The Contractor must coordinate access to secure areas at least five (5) working days ahead of time. It is the Government's responsibility to provide escorts.
2.1.3.2. Operational Security (OPSEC)
Network infrastructure (CMHDS, MH/HH locations, fiber paths, etc.) is on the 81 CS Critical
Information List (CIL) and must be protected. The Contractor shall take appropriate measures to protect detailed information pertaining to the EFI&T effort, to include appropriate marking of documents as “For Official Use Only (FOUO),” and ensuring limited distribution of documents and schematics/drawings to only those individuals with a valid need to know. In accordance with
(IAW) AFI 10-701, OPSEC Considerations, the Contractor shall develop an OPSEC plan to ensure the protection of FOUO data either furnished by the government or produced by the
Contractor. The Contractor shall provide an OPSEC plan no later than 10 days prior to arrival on-site.
2.1.4. Environmental Compliance
The Contractor shall comply with the most stringent environmental federal, state, and local laws
Page 5 of 33 For Official Use Only and regulations; and Air Force policies, instructions, and plans. The federal Government is not exempt from compliance with environmental regulations. The contractor shall maintain an awareness of changing environmental regulatory requirements to avoid environmental deficiencies for activities on Keesler AFB. The Prime Contractor shall be responsible for their sub-contractors’ compliance with environmental laws and regulations.
2.1.5. Permits
The Contractor shall complete and process all permits required to complete the installation prior to any trenching, or modifications to a facility, maintenance hole or hand hole; for example, Base Civil Engineering Work Clearance Request, a digging permit, (AF Form 103)
Base Civil Engineer Work Request (AF Form 332).
AF Form 103 and AF Form 332 {and any other required permits (as determined by Base Civil
Engineering (BCE) and/or 81 CS/SCXP, etc.)} shall be submitted at IAW local procedures.
All utility markings, flags, etc. shall be maintained by the contractor after the responsible work center/shop identifies/locates them. If a utility is severed or damaged due to neglect or if attributed to the fault of the contractor, then the contractor shall repair and return the utility back to the same condition it was in prior to the damage. The form(s)/permits shall be coordinated with 81 CS/SCXP at minimum one week prior to arrival on-site.
2.1.6. Integrated Process Team (IPT)
The Contractor shall chair a weekly IPT meeting that includes Contractor representatives, the 81
CS/SCXP Project Manager (PM), and other base personnel as required. The Contractor shall provide an agenda and a worldwide “Meet Me” teleconference capability for the duration of the project. The purpose of the IPT meeting is to discuss project progress, problems being encountered, and other information necessary/beneficial to ensure success and timely completion of contract requirements. The Contractor shall record meeting minutes and distribute to the attendees.
2.1.7. Quality Assurance
The Contractor shall provide Quality Assurance Support for the life of the project. The
Contractor’s quality assurance evaluator (QAE) shall assist the Government representative in performing random spot checks and system acceptance tests. The Contractor shall be responsible for identifying system and outside plant deficiencies and /or discrepancies throughout the life of the project. A weekly report (soft copy) shall be submitted indicating progress/status and listing any deficiencies/discrepancies found and actions to correct them.
2.1.8. Contractor Personnel
2.1.8.1. Project Management
The Contractor shall provide a Project Manager (PM) and alternate(s) responsible for contract performance and continuity. The Contractor shall identify the Project Manager’s or alternate's range of authority to act for the Contractor relating to daily contract operation.
2.1.8.2. Site Point of Contact (POC)
The Contractor shall designate the Contractor's on-site team leader and alternate(s) as the Site
Page 6 of 33 For Official Use Only
POC for individual projects in their Site Visit Request Letter. The Site POC or alternate(s) shall be on site during duty hours until project completion and shall oversee all facets of the installation tasks. The Site POC shall be the interface for all work site communications with the
Government, including quality, safety, and discrepancy matters.
2.1.8.3. Personnel Requirements
The Project Manager, Site POC, and respective alternate(s) shall be able to read, write, speak, and understand English, and shall be on site to coordinate permits, clearances, and receive shipments/materials related to the task order. All reporting and documentation shall be in
English.
The Government requires at least one experienced and technical certified Building Industry
Consulting Service International (BICSI) installer to be at on-site location, and shall be on site to coordinate permits, clearances, and receiving shipments/material related to the task order.
2.1.9. Warranty
The Contractor shall provide a one year warranty or manufacturer’s standard commercial warranty, whichever is longer. This warranty shall include a one year workmanship warranty.
The warranty period shall start from the date of system and/or project acceptance. The
Contractor shall provide written procedures and required information for warranty services at or prior to site acceptance.
2.1.10. Manuals and Practices
The Contractor shall provide the latest version of operation, installation, and maintenance manuals and practice guides, and user guides for each system installed as provided by the original manufacturer with all new equipment and shall be provided to the 81 CS/SCXP PM.
2.2. SPECIFIC REQUIREMENTS
The Contractor shall design and install Customer-Owned Outside Plant Telecommunications
Infrastructure in accordance with TIA-758-B. The cable installation shall be coordinated with the 81 CS/SCXP so that any impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion. See Appendix D – Drawings, for reference and estimated distances of existing and proposed infrastructure and cable routes.
The Contractor shall EFI&T a new CMHDS and install four (4) 12 strand SM FOC from building B-4705 to buildings B-4407, B-4414, B-4419, and B-4421. The total length is approximately 7,550 feet, along with associated fiber optic distribution panels (FODPs) in B-
4705, B-4407, B-4414, B-4419, andB-4421 including all associated splicing and terminations as defined herein. In addition, to support the installation of the four (4) 12 strands SM FOC, the
Contractor shall install two (2) new HH holes (HH), and approximately 930 feet of new 2-way duct bank.
2.2.1. Maintenance Holes (MHs) and Hand Holes (HHs)
The Contractor shall pump out any maintenance hole and hand hole into which entry is required.
The water may be pumped on the ground.
2.2.2. Measurements
Any distances provided in this SOW are approximations and should NOT be used for ordering
Page 7 of 33 For Official Use Only materials or determining duct lengths.
2.2.3. Underground Utilities Markings
The Contractor shall coordinate with base agencies to ensure markings are placed over existing base infrastructure prior to digging or directional drilling (horizontal directional boring) and shall take precautions to protect existing infrastructure. In the event the Contractor cuts or otherwise damages any buried utilities or base infrastructure, then Contractor shall immediately notify the 81 CS/SCXP PM, BOS (PAE), and 81 CONS Contracting Officer. The Contractor is responsible for repair of any damage caused during installation when the infrastructure is clearly marked. The Contractor is responsible for maintaining all markings, and for ensuring AF Form
103 (Dig Permit) remains current. Dig permits must be renewed every 10 calendar days if construction is to continue past the originally approved 10 day period.
2.2.4. Splice Conductors
N/A
2.2.5. Cable Racks and Cable Rack Supports
Cable racks shall be installed in maintenance holes as if not present. The splices shall be supported by cable hooks under the splice case not by the cables only.
Telecommunications industry standard cable hooks of the appropriate length shall be provided to support cables and splice cases. The cable hooks shall be secured using cable rack locking clips.
All cables shall be supported using racking clips, cable racks, and cable hooks.
2.2.6. Labeling
The Contractor shall label all equipment and cables they install in accordance with (IAW) TIA-
606-B and as directed by 81 CS/SCXP and conform to local maintenance identification.
2.2.6.1. Cable Tags
All tags shall be permanently labeled, easily visible and corrosion resistant. Install cable tags in all maintenance holes/hand holes, cable vaults, pull boxes and building entrance terminal locations. When cables pass through a MH/HH, put a tag on the cable, approximately 2 feet from each duct entrance, or on each side of the splice case, if one exists. If there is a slack loop in the cable in the MH/HH, put a tag on the loop. Information on the tag shall conform to the system used by local maintenance personnel to identify cables.
Example (fiber):
FO 4309 – Building fiber is being installed for
4705-4309 – ITN / Building number
1-12 SM or MM – Number and type
Note: The same information shall appear on the Contractor’s completed As-Built- Drawings.
2.2.7. Pulling Tape
All newly installed ducts left vacant shall be provided with a waterproof, corrosion resistant, pre-lubricated flat woven polyester pull tape with sequential footage markings (1250 lb. pulling
Page 8 of 33 For Official Use Only strength) for future cable installations. The pull tape shall extend into the maintenance holes/hand holes and be secured to a cable rack or pulling iron, etc.
2.2.8. Cable Terminations
Fiber optic cable termination will be SC connectors, with no splicing (home run installation), and no jumpers.
2.2.9. FOC Maintenance Loop(s)
The Contractor shall install a 25 foot fiber optic cable maintenance loop in every maintenance hole. The maintenance loop slack shall be properly labeled, securely supported to the cable ladder and off the MH floor. The same information shall appear on the Contractor’s completed
As-Built drawings.
2.2.10. New Maintenance Holes/Hand Holes
New Maintenance Holes (MH) shall have minimum interior dimensions of 6’ x 12’ x 7’, and meet the requirements of TIA-758. New hand holes (HH) shall have minimum interior dimensions of 4’ x 4’ x 4’, and meet the requirements of TIA-758. Sump (with removable perforated cover), pulling-in irons, ¾” x 10’ ground rod, telecommunications industry standard cable racks and hooks, and bonding ribbon attachments shall be provided in all new hand holes.
Round hand hole covers shall be cast with 1/8” raised letters stating “COMMUNICATIONS” displayed on the outside and shall be fitted with a locking mechanism. LockDown Device with
Abloy locks or equivalent are use as locking mechanism. Coordination with 81 CS/SCXP will be required to identify key information.
MH and HH shall be designed to telecommunications industry standards (concrete compressive strength, reinforcing, rebar spacing, etc.); hand holes and covers, shall be capable of supporting
AASHTO H-20 wheel loading. They shall be precast with manufacturer installed wall inserts for attaching cable rack hardware and have predrilled duct entry holes [sealed with knockouts (configured for splayed entry in end walls)] with duct terminators (inside end to be flush with HH interior wall surface) to accept 4-inch
I.D. (inside diameter) schedule 40 conduit. The hand holes shall be installed IAW RUS Bulletin
1751F-644 and commonly accepted telecommunications practices relevant to the task.
Excavation for MH and HH placement and bedding material shall be IAW manufacturer’s recommendations. Backfilling shall be select backfill free from stones, frozen earth, broken concrete, or pavement, wood, etc. They shall be set so that the cover shall extend no more than
½” above paved surface or 3” above surrounding grade if unpaved surface. Hand holes are numbered as indicated on SOW Sketches for the purposes of identifying them for this project only. 81 CS/SCOI representative shall provide permanent numbers for the maintenance/hand holes, which the Contractor shall put on the as-built drawings.
2.2.11. New Maintenance Holes / Hand Holes Placement
Maintenance/Hand Hole placement will be identified by local maintenance team.
2.2.12. Grounding
Grounding hardware such as corrosion resistant wire, bonding ribbon, clamps, ground rod, etc.
necessary to properly bond/ground the cable in MHs shall be provided by the Contractor.
Reference ANSI/TIA 607. Contractor provided ground rods will be installed outside HH/MH
Page 9 of 33 For Official Use Only
IAW ANSI/TIA 607.
2.2.13. Underground Conduit System
The Contractor shall be responsible for any required trenching and/or boring necessary to lay the duct system. The Contractor is also responsible for backfilling ditch lines and compaction of fill materials with appropriate compaction tools. Backfill material shall be clean and free from all organic material, clay, marl, or unstable materials, debris, lumps, or broken paving. NO rocks or stones larger than 3 inches in diameter shall be allowed in backfill. Material for backfill may be material resulting from excavation, if it meets the above requirements. Unless specified otherwise, Directional Drilling shall be used for all paved surface crossings (see Table “: PVC
Duct-banks: Directional Drilling” for details).
Directional drilling shall be used for sidewalks, parking lot driveways, road crossings, taxiways, runways, etc.
2.2.13.1. Composition
The ducts shall be 4-inch inside diameter (I.D.) round or metric equivalent. The ducts shall be made of EPC-40 Polyvinyl Chloride (PVC) (Schedule 40) IAW NEMA TC-2. For unique/site specific situations, the ducts shall be made of EPC-80-PVC (Schedule 80) IAW NEMA TC-2.
Schedule 80 PVC shall be limited to risers, all above ground conduit, and under the roadway/parking pavement. High density polyethylene (HDPE) SIDR 13.5 shall be used when directional boring is used. The ducts shall be appropriately labeled indicating the composition material. Ducts shall have a sleeve or bell-end type coupling and shall be watertight when assembled. In addition, the Contractor shall adhere to any additional Keesler AFB/site specific requirements.
2.2.13.2. Installation
Installation of underground conduits/ducts shall be IAW RUS Bulletin 1751F-643 and RUS
Bulletin 1753F-151. Ducts installed beneath roads, sidewalks, parking areas, other paved surfaces or areas to be paved, etc. shall be installed a minimum of 36" below grade. In a MH with knockouts, ducts shall start at the bottom knockout, allowing for upward expansion in the
MH. All ducts not installed under roads, sidewalks, parking areas, or areas to be paved, etc.
shall have a minimum of 36 inches ground cover, where possible. The Contractor shall provide other protective measures, concrete cap, etc., in those areas where the minimum ground cover cannot be achieved. Grading of ducts shall be accomplished IAW RUS Bulletin 1751F-643. All conduits shall be continuous between MH/HHs (i.e., no breaks or separations in the conduit runs between MH/HHs).
2.2.13.3. Bends and Sealing
All bends between MHs//HHs shall be a minimum 40-foot radius with the sum of all bends in all directions not exceeding a total of 90 degrees. Duct(s) shall enter a MH/HH perpendicular to the surface of the wall through which it is entering. All new ducts entering a MH/HH shall be sealed. Universal duct plugs or removable putty sealants (compatible with the application) may be used. Upon completion of conduit sections, a test mandrel ¼” (6.4mm) to ½” (12.7mm) smaller than the inside diameter of the conduit shall be pulled through each duct to ensure proper alignment. In addition, all new ducts shall be cleared of loose materials such as concrete, mud, dirt, stones, etc.
2.2.13.4. Utility Separation
Page 10 of 33 For Official Use Only
When communications ducts cross either power duct or buried power cable, maintain a minimum separation of 3 inches of concrete or 12 inches of well- tamped earth between the two or 12 inches of well tamped earth when parallel; for pipes (e.g., gas, water, oil) maintain 6 inches when crossing or 12 inches when parallel.
2.2.13.5. Spacers and Tracer Wire
Along the length of the duct run, if the ducts are installed by trenching, spacers shall be placed at five (5) foot intervals and cable warning tape shall be buried one (1) foot below the surface and shall follow the duct route. The tape shall be a minimum of three inches wide and orange in color with the appropriate warning message.
In conduits wherein is installed Geotextile Fabric Inner-duct, at least one of the sleeves shall be traceable/detectable.
2.2.13.6. Entrance Conduits into Existing Maintenance Holes
When new entrance conduits/ducts or sleeves are required, the Contractor shall bore and install the necessary holes and install the ducts or sleeves, if a knockout does not exist. Contractor bored holes shall be fitted with duct terminators to accept 4-inch I.D., schedule 40 (or schedule
80) conduit. Penetration shall not be in such a location through the wall as to block use of existing ducts in the maintenance hole. New ducts will be a minimum of 18 inches from either the maintenance hole floor or ceiling, if practical. The minimum bending radius for entry conduit/ducts shall be no less than 10 times the inside diameter of the conduit. Ducts and openings around ducts shall be sealed to prevent moisture from entering the maintenance holes.
All duct entrances shall be flush with the MH/HH interior wall surface.
2.2.13.7. Excavation/Building Penetrations
All wall penetrations, including inside buildings, shall be restored to meet the required base fire ratings.
Building Penetrations w/EMT Sleeves
From To Qty. Via Diame t e r
Figure Comment
N/A B-4414 1 Southeast exterior wall
4” 1, 2, 4, N/A B-4421 2 North exterior wall
4”
N/A B-4419 1 Southeast exterior wall
4” 1, 2, 3, N/A B-4407 1 South exterior wall
4” 1, 2, 3
Building Foundation Penetrations w/EMT Sleeves
From To Qty. Via Diame t e r
Figure Comment
N/A B-4421 2 North side 4”
Page 11 of 33 For Official Use Only
NEMA 3 J-Box Installation
From To Qty. Via Figure Comment
N/A B-4414 1 Southeast exterior wall 1, 2, 4, One (1) 4” conduit
N/A B-4421 1 North exterior wall 1, 2, 4, Two (2) 4” conduits
N/A B-4419 1 Southeast exterior wall 1, 2, 3, One (1) 4” conduit
N/A B-4407 1 South exterior wall
1, 2, 3 One (1) 4” conduit
2.2.14. Outside Plant Installation
This section describes the underground cables, flexible geotextile multiple cell fabric, Innerduct and MH/HH plus conduit system installation requirements. The Contractor shall design and install Customer-Owned Outside Plant Telecommunications
Infrastructure in accordance with ANSI/TIA-758-B. Each cable installation shall be coordinated with Keesler AFB 81 CS/SCXP so that the impact on the building users is properly coordinated. The sequence of installation is at the Contractor’s discretion.
2.2.14.1. Infrastructure Installation
The Contractor shall install the following new infrastructure. All new locations and distances are approximate.
2.2.14.1.1. Maintenance Holes and Hand-Holes
The Contractor shall provide and install two (2) new hand holes (MH) at locations shown on Figures 1, 2, 3, 4 and 5. The dimensions of the HHs shall be 4 feet x 4 feet x
4 feet. Coordinate the exact MH locations with Keesler AFB 81 CS/SCXP.
Install the following Hand-Holes (HH)
HH # See Figure Dimensions Note
Proposed HH-
108A
1, 2, 3, 4 4’ x 4’ x 4’ Approximately 40 ft. north of B- 4419
Proposed HH-
108B 1, 2, 3, 4, 4’ x 4’ x 4’ Approximately 30 feet southeast of B-
NOTE: Keesler AFB 81 CS/SCXP shall provide final numbering/IDs for the new MHs installed IAW this para.
2.2.14.1.2. Duct bank Infrastructure
Install 4” PVC duct banks IAW the following Table:
Page 12 of 33 For Official Use Only
PVC Duct-banks (Directional Drilling)
From
To
Qty.
Size
Approx.
Distance
(Feet)
Figure
Comment
MH-108
Proposed
HH-108B
2 4” 130
1, 2, 4, 5
Under fence and parking area
Proposed HH-108B Proposed
HH-108A
4”
1, 2, 3, 4, Under fuel line and parking area
Proposed HH-108A B-4407 1 4” 200
1, 2, 3, 4 Under two fences
MH-109 B-4421 2 4” 300
1, 2, 4, 5
Under street, fence, and parking area
PVC Duct-banks Schedule (Trench and Place)
From
To
Qty.
Size
Approx.
Distance
(Feet)
Figure
Comment
Proposed HH-108B B-4414 1 4” 30
4, 5
Proposed HH-108A B-4419 1 4” 40
3, 4
2.2.14.1.3. Geo-textile Fabric (or Innerduct)
Installation
Install Geo-textile fabric Innerduct IAW the following Table:
NOTE: One of the three 3x3” geo-textile fabrics in each conduit shall be detectable.
Geotextile Inner-Duct Installation
From To Qty. of 3x3” packs
Approx.
Distance (Feet)
Figure Comment
MH-108 Proposed
HH-108B
6 130 1, 2, 4, 5
Proposed
HH-108B
B-414 3 30 1, 2, 4, 5
Proposed
HH-108B
Proposed
HH-108A
6 230 1, 2, 3, 4, Proposed
HH-108A
B-4407 3 200 1, 2, 3, 4
Proposed
HH-108A
B-4419 3 40 1, 2, 3, 4
MH-109 B-4421 6 300 1, 2, 4, 5
MH-109 MH-108 1 220 1, 5 Remove the two unused Innerducts
MH-109 MH-110 1 350 1, 6
Page 13 of 33 For Official Use Only
2.2.14.2. Fiber Optic Cable Installation
Install outside plant FOC as described in the following paragraphs. The cable shall be all dielectric, loose buffer tube, water blocked, single mode, Inside/Outside plant (ISP/OSP) cable. The Contractor shall coordinate each cable installation with the Keesler AFB 81
CS/SCXP so as to minimize the impact on building users. The FOC shall be installed as a home-run, a continuous cable without splicing shall be utilized in the installation of the
FOC.
2.2.14.2.1. Fiber Optic Distribution Panel Installation
NOTE: Recommend the Contractor obtain and install Corning Pretium Fiber Optic Panels (or equivalent) with SC connectors for the 12-port FODPs. These panels are the 2U Rack Unit
Models. A splice center will also be required at each termination point.
Fiber Optic Distribution Panel Installations/Terminations
Building Qty. Location Note
B-4407 1 Wall mounted cabinet Rack Mount
2-RU
SC bulkheads 1
- 12
B-4419 1 Wall mounted cabinet Rack Mount
2-RU
SC bulkheads
1-12
B-4414 1 Wall mounted cabinet Rack Mount
2-RU
SC bulkheads 1
– 12
B-4421 1 Wall mounted cabinet Rack Mount
2-RU
SC bulkheads 1
– 12
B-4705 4 Existing rack Rack Mount
2-RU
SC bulkheads 1
– 12
(x4)
2.2.14.2.2. FOC Installation
The Contractor shall install one (1) 12 strand SM FOC (12L8.3F) from building 4705 to buildings B-4407, B-4414, B-4419, and B-4421 IAW Figures 1 through 7. For building B-4407, the approximate FOC distance is 2,200 feet. For building B-4414, the approximate FOC distance is 1,725 feet. For building B-4419, the approximate FOC distance is 2,000 feet. For building B- 4421, the approximate FOC distance is 1,625 feet.
Leave a 25 foot maintenance coil in every MH/HH. The new FOC shall utilize any of the newly installed vacant Innerduct and/or flexible geotextile multiple cell
Page 14 of 33 For Official Use Only
Innerduct in the maintenance holes along this route, and any available legacy vacant
Innerduct and/or flexible geotextile multiple cell Innerduct in the maintenance holes along this route. Terminate the 12 strand SM FOC to the FODP with SC type connectors. Verify the locations of the equipment rack and the FODP with Keesler
AFB 81 CS/SCXP.
Install the following Single Mode (SM) Fiber Optic Cable (FOC)
From To Strand count
Via Approx.
Distance
(Feet)
Figure Comment
ITN B-4705 B-4407 12 B-4705 IT Room MH-135
MH-27 MH-26 MH-110
MH-109 MH-108
Proposed HH-108B
Proposed HH-108A B-4407
2,200 1, 2, 3, 4 8.3 SMFO
ITN B-4705 B-4414 12 B-4705 IT Room MH-135
MH-27 MH-26 MH-110
MH-109 MH-108
Proposed HH-108B B-4414
1,725 1, 2, 4, 5 8.3 SMFO
ITN B-4705 B-4419 12 B-4705 IT Room MH-135
MH-27 MH-26 MH-110
MH-109 MH-108
Proposed HH-108B
Proposed HH-108A B-4419
2,000 1, 2, 3, 4 8.3 SMFO
ITN B-4705 B-4421 12 B-4705 IT Room MH-135
MH-27 MH-26 MH-110
MH-109 B-4221
1,625 1, 2, 4, 5 8.3 SMFO
2.2.15. Site Restoration/Debris Removal
The Contractor shall restore all disturbed grounds to the “as found” condition or better after installation. Base grounds restoration requirements shall be complied with.
Common use areas shall be restored to their original condition. The Contractor shall be responsible for disposing of all residues from this project off base and in accordance with Federal, state and base environmental laws and regulations.
All residue produced by directional drilling operations (i.e., slurry) shall be disposed of off base on the same day the residue is produced, at an appropriate disposal facility at the contractor’s expense, IAW federal, state, local and
KEESLER AFB environmental laws and regulations. Under no circumstances will the contractor stage or store boring residue in slurry ponds or other containment areas on KEESLER AFB.
2.2.16. Service Outages
The Contractor shall be responsible for preventing any unscheduled (i.e. cutting or disabling any in-service cables or equipment.), Contractor-caused, Page 15 of 33 For Official Use Only interruptions of communications capabilities that are properly identified. The
Contractor shall coordinate planned outages with the site POC at least 10 calendar days in advance of the outage if the implementation necessitates disruption of service, (e.g., communications, electrical, or other utilities).
2.2.17. Identification/Marking
The Contractor shall clearly mark all Contractor-Furnished Property and
Equipment (CFP/CFE) with their company's name. The Contractor shall place an easily read, very visible, sign (minimum 8.5 inches x 11 inches) on large containers, construction equipment, or un-manned rental vehicles while on the
Government installation indicating the company name and both the Contractor and Site POC's names and local telephone numbers.
2.2.18. Installation Schedules
The Contractor shall provide a complete milestone schedule that denotes project activities to include time-phased start and completion dates for the project and sub- projects associated with the installation of the components and system.
2.2.19. Weekly Status Reports
The Contractor shall prepare a Weekly Status Report in English and shall distribute to IPT members. The purpose of the report is to inform IPT members of project progress, problems being encountered, and other topics necessary/beneficial to ensure success and timely completion of the contract requirements.
2.2.20. As-Built Drawings
The Contractor shall submit red line drawings showing the “as-built” configuration in format specified by base SCX project manager. The base communications squadron will provide baseline drawings. The Contractor shall provide As-Built Rack Elevation, Inside Cable Plant and Outside Cable Plant drawings and distribute. These drawings shall depict the entire pathway and details of the installation, including but not limited to: labeling, cables, inner-ducts, maintenance holes, hand holes, conduits, maintenance loops, distances, bores, trenches, building entrances, Inside Cable Plant, and Outside Cable Plant drawings, and As-Built Rack Elevations.
2.2.21. Test and Acceptance/Installation Test Plan
The Contractor shall provide test equipment and personnel required to conduct all pre and post testing. The Contractor shall record all pre and post inspections/tests as they are accomplished. The Contractor shall make all test sheets/results available for 81 CS/SCXP representative upon completed. The
Contractor shall notify the 81 CS/SCXP at least 5 calendar days prior to any testing. All testing will be IAW accepted telecommunications industry standards for the type of project being accomplished. It is assumed that all cable when delivered are fault free from the manufacturer. All cables will be tested prior to installation. No cable faults or splicer’s errors are allowed in the new installation. The Contractor shall provide test reports to the government within
10 calendar days of completion. Contractor is required to locate, repair and
Page 16 of 33 For Official Use Only retest all irregularities found during the testing phase caused by the cable installation. Any splicer’s errors detected shall be corrected in the splice in which they were made. The Contractor will coordinate with 81 CS/SCXP before starting the final system test.
2.2.21.1. Fiber Optic Cable Tests
All strands of all fiber optic cables shall be tested IAW TIA 526-7 Measurement of Optical Power Loss of Installed Single-mode Fiber Cable Plant, or equivalent. As a minimum, the following tests shall be performed. Both Optical
Time Domain Reflectometer (OTDR) and Optical Power Meter tests will be used for all end-to-end circuits. Between FODPs, bi-directional testing at 1310 nm and 1550 nm is required. For incomplete circuits that end in manholes, only
1 way OTDR testing is required. The Contractor shall provide equipment generated documentation (Optical Time Domain Reflectometer (OTDR) and
Optical Power Meter) all test results in a “Test Report(s)” and submit to the
Government. Hand written results can be viewed but will not be accepted as final results.
NOTE: Testing of the Fiber Optic Cables on the reel shall be provided to the 81 CS/SCXP prior to installation.
2.2.21.2. Optical Attenuation
End to end attenuation tests shall be conducted on all fiber optic cable strands. Tests shall be accomplished to ensure the installed cable is within the specified parameters.
2.2.21.3. Distance
Test to determine the installed cable length between optical patch panels. All strands of all fiber optic cables shall be tested.
2.2.22. Acceptance/Installation Test Report
The Contractor shall provide an installation test report of the results of the testing accomplished under the installation test plan IAW CDRL A006. The Test Report(s) shall be provided to the Government no later than 10 calendar days after the test(s) have been completed.
2.2.23. Final Acceptance
The Contractor shall schedule a final project walk-through with the Keesler AFB 81
CS/SCXP. This should be scheduled 10 calendar days prior to acceptance.
2.2.24. As-Built Documentation in CVC
The Contractor shall record geospatial data and provide as-built documentation (shape files) of all new installed maintenance hole system components (including metadata) compatible with the Cyberspace Infrastructure Planning System (CIPS) Visualization
Component (CVC) drawing system. Data points shall be recorded at the center of each manhole/hand hole lid and at intervals not to exceed 25 feet along cable routes.
Sufficient data points shall be recorded to capture any change in direction along the route. All GPS coordinates shall have +/- 3 feet accuracy for all readings. The
Page 17 of 33 For Official Use Only government is responsible for providing the Contractor with a copy of the installation’s most current GeoBase Common Installation Picture (CIP), and current CVC drawings of the areas of interest. The government will review the shape files in CVC and transcribe the information to the CVC system. Shape files shall be delivered upon project completion.
3. GENERAL INFORMATION
3.1. Period of Performance
The period of performance for the project shall be determined based on the proposed schedule and actual contract award date. The project is estimated to take 120 days.
3.2. Place of Performance
The place of performance is Keesler AFB, MS.
3.3. Hours of Operation
The Contractor shall routinely work during normal duty hours of the site. However, mission requirements may necessitate work outside normal hours (nights and/or weekends), especially if existing service must be interrupted. Any site work requested by the Contractor to be performed outside of normal duty hours shall be coordinated with the Keesler AFB 81 CS/SCXP and approved by the Contracting Officer at least 10 calendar days in advance.
3.4. Holidays/Down Days
The Contractor shall not perform under this contract on federal holidays or site-unique down-days unless expressly authorized by the CO and coordinated with the Keesler AFB
81 CS/SCXP Project Manager.
3.5. Base Support
The Contractor shall identify any base support requirements (for example, laydown and storage areas) necessary to complete this project in their proposal. The contractor shall return all government furnished lay-down and storage areas to their original condition upon completion of the project.
3.6. Minimum Contractor Qualifications
All work shall be performed by an experienced Telecommunications Contractor. The
Contractor shall have a minimum of 3 years of experience in Telecommunications
Systems installations.
Page 18 of 33 For Official Use Only
APPENDIX A: APPLICABLE STANDARDS
The following list is not all-exclusive. The Contractor shall comply with applicable commercial code and standards
AFI 91-203 – Air Force Consolidated Occupational Safety
Instruction OSHA CFR 29 Part 1910-268 – Telecommunications
NEMA TC 2- Electrical Polyvinyl Chloride (PVC) Tubing and Conduit
ANSI/TIA-606-B Administration Standard for Telecommunications Infrastructure
TIA-568-C Commercial Building Telecommunications (568C.1, 568C.2, 568C.3) Cabling
Standard
ANSI/TIA-607-B Commercial Building Grounding (Earthing) and Bonding Requirements for
Telecommunications
TIA-569-C - Commercial Building Standard for Telecommunications Pathways and
Spaces TIA-570-C –Residential Telecommunications Infrastructure Standard
TIA-758 B - Customer-owned Outside Plant Telecommunication Infrastructure Standard
BICSI TDM Manual - Building Industries Consulting Services International
Telecommunications Distribution Methods (TDM) Manual
BICSI – Outside Plan Design Reference Manual
RUS Bulletin 1751F-643 - Underground Plant Design
RUS Bulletin 1751F-644 - Underground Plant Construction Telecommunications
Engineering Shield Continuity and Construction Manual (TE&CM) 451.2
RUS Bulletin 1751F-801 – Electrical Protection Fundamentals
RUS Bulletin 1753F-151 (515b) - Specifications and Drawings for Underground Cable
Installation NFPA 70 - National Electric Code
FGDC-STD-007.3-1998 - Geospatial Positioning Accuracy Standards Part 3: National Standard for Spatial Data Accuracy
Unified Facilities Criteria 3-260-01
Page 19 of 33 For Official Use Only
APPENDIX B: LIST OF DELIVERABLES
All deliverables are subject to Government acceptance and approval. They shall meet professional standards and the requirements set forth in this SOW. All deliverables shall be produced using recommended software tools/versions as accepted by the
Government. The Contractor shall submit the following deliverables:
Data Item Title
As-Builts – Geospatial Information Systems (GIS) locations of new manhole/hand holes, manhole butterfly drawings, rack elevations related to this project
Work Schedule – project time lines (MS Project or Excel)
Status Report – Weekly updates of progress (MS Project or Excel)
Test Plan – Plan depicting Pre/Post testing of FOC
Test Reports – Pre/Post test results
OPSEC Plan
Page 20 of 33 For Official Use Only
APPENDIX C: LIST OF ACRONYMS
AASHTO American Association of State Highway and Transportation Officials
AFM Airfield Management (BaseOPS)
Approx. Approximately
ATC Air Traffic Control Tower
ATCALS Air Traffic Control and Landing Systems
BCE Base Civil Engineering
CFE Contractor-Furnished Equipment
CFP Contractor-Furnished Property
CIL Critical Information list
CIP Common Installation Picture
CIPS Cyberspace Infrastructure Planning System
CMA Controlled Movement Area
CMHDS Communications Maintenance Hole Duct System
CO Contracting Officer
Comm Communications
CS Communications Squadron
CSI-B Cyberspace Integrator-Base
CT Control Tower
CVC CIPS Visualization Component
EBN End Building Node
ECMRA Contractor Manpower Reporting Application
EFI&T Engineer, Furnish, Install, and Test
FOC Fiber Optic Cable
FODP Fiber Optic Distribution Panels
FOUO For Official Use Only
FY Fiscal Year
HDPE High Density Polyethylene
HH Hand Hole
IAW In Accordance With
ID Inside Diameter
ILS Instrument Landing System
IPT Integrated Process Team
LMR Land Mobile Radio
MH Maintenance Hole
MHDS Maintenance Hole Duct System
NLT No Later Than
NPDES National Pollution Discharge Elimination System
OEM Original Equipment Manufacturer
OPSEC Operational Security
OSHA Occupational Safety & Health Administration
OSP Outside Plant
Page 21 of 33 For Official Use Only
OSS Operations Support Squadron
OTDR Optical Time Domain Reflectometer
PDF Portable Document Format
PM Project Manager
POC Point Of Contact
Prime Prime Contractor
PSI Pounds per Square Inch
PVC Polyvinyl Chloride
QAE Quality Assurance Evaluator
QCM Quality Control Manager
Qty Quantity
RUS Rural Utilities Service Bulletin
SCOW Supply Chain Operations Wing
SCX Scheduler Planner
SE System Engineer
SM Single Mode
SOO Statement of Objectives
Sub Sub-Contractor
SWPPP Storm Water Pollution Prevention Plan
TIA Telecommunications Industry Association
TMGB Telecommunication Main Ground Bus-Bar
TRD Technical Requirements Document
APPENDIX D: DRAWINGS
File details come from the government source that posted it.