Amend_1.pdf
PDF 77 KB Posted
- Attached to
- Fiber Optic Cable Installation Federal contract opportunity
- Solicitation number
- FA301018R0023_Fiber-Optic
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Addendum_1.pdf | ||
| Sign-In_Sheet.pdf | ||
| Attachment_3_-_SOW_3_FOC_3501-1101.pdf | ||
| Attachment_4_-_Past_Performance_Questionnaire.pdf | ||
| FA301018R0023.pdf | ||
| Attachment_6_-_Wage_Det_MS180141.pdf | ||
| Attachment_7_-_Notice_of_Compliance.pdf | ||
| Attachment_2_-_SOW_2_C2-D2-FOC_Fuels_Depot.pdf | ||
| Attachment_1_-_SOW_1_C2-D2-FOC_B-404_81_to_B223_ITN.pdf | ||
| Attachment_8_-_SF_1444.pdf | ||
| Attachment_5_-_Reference_List.pdf |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE SCHEDULE
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to:
1. Provide Questions & Answ ers
2. Incorporate Addendum 1 to the SOW
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 18-Jun-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA301018R0023
X 9B. DATED (SEE ITEM 11)
31-May-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
18-Jun-2018
CODE
81ST CONTRACTING SQUADRON
SSGT MAXWELL WATANGA
310 M STREET, RM 102
KEESLER AFB MS 39534-2701
FA3010 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA301018R0023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
QUESTIONS & ANSWERS
Questions FOC Installation Keesler AFB
1. Will this solicitation include enterprise network equipment and optical cable in addition to the fiber optic cable installation?
a. As noted in SOW scope, only FOC, associated terminating equipment, and conduit system installation are included
2. The SOW is calling for NEMA 3r J‐box boxes to be installed. What are the sizes of the NEM3R J‐Boxes?
a. Disregard references to NEMA 3r. All J-boxes will be NEMA 4
b. Size of J-box will be left to the contractors discretion
3. Are the J‐boxes fiberglass, Metal or Stainless steel?
a. All J-boxes will be NEMA 4 which requires fiberglass
4. What height is the mounting of each J‐box on each of the buildings?
a. Height will be left up to the contractors discretion
5. In the SOW is calling for cable tray type to be install are part of this project? What type of cable tray is required to be installed? (Rung space, material type, height and width)?
a. Cable ladder of standard size (1ft) will be used
6. Can basket tray be used in place of ladder type cable tray?
a. No. Only ladder type will be accepted.
7. Will the cable tray or basket tray to the grounded and bonded to the telecommunications ground in each of the Comm Room?
a. Please refer to section 2.2 Specific Requirements of each SOW. “The Contractor shall design and install Customer-Owned Outside Plant Telecommunications Infrastructure in accordance with
TIA-758-B.”
8. Each of the SOW is call for 4’’ EMT Sleeve to be installed from the j‐box to install in the building or IT room. Are we to use 4’’ steel set screw connectors or 4’’ steel compressor connector?
a. 4’’ steel compressor connectors are to be used in
9. Instead of EMT conduit and fitting can 4’’ ridge conduit nipples be used for sleeves?
a. No
10. SOW 3 pages 13 of 33 under EMT state a 20 feet of 4” EMT from the J‐box to the IT room and cable basket tray to be installed to room 119. Are both EMT and Basket tray going to be installed from the junction box to the IT room? Also what size cable basket tray is requiring to be installed?
a. Disregard “cable basket”. Only cable ladder will be used.
b. Both will be installed from J-box.
11. Will all the basket tray or cable tray need to meet the grounding and bonding
a. Please refer to section 2.2 Specific Requirements of each SOW. “The Contractor shall design and
12. Requirement of NEC for communication cable tray?
a. Please refer to section 2.2 Specific Requirements of each SOW. “The Contractor shall design and
13. SOW 3 PAGE 12 OF 33 building B‐3501 under building foundation penetrations is call for 2 4’’ sleeves to be installed. In SOW 3 there appears to be no EMT requirement, NEMA 3 J‐box requirement. Is the NEMA 3 j‐box required? How many conduits from the j‐box to inside the building?
a. EMT is not required. Conduit sleeves are required to be schedule 40 or 80.
b. Disregard NEMA 3r. All J-Boxes will be NEMA 4.
c. Placement will be left up to the contractor’s discretion.
14. Can directional boring replace trenching as shown for several long runs?
a. Directional boring can replace trenching so long as it incurs no additional cost.
15. Are cable racks and supports available in the existing maintenance holes?
a. Please refer to section 2.2.4 Cable Racks and Cable Rack Supports “Cable racks shall be installed in maintenance holes as if not present.”
16. Which measurement is the depth for the maintenance hole (manhole) MH, 6' x 12' x 7'?
a. Please see addendum 1. Manhole measurements are corrected to 6’ x 6’ x 6’.
b. Manholes will require a collar.
17. SOW - C2-DS-FOC Critical Path for B404 81 MDG Alternate Unit Control Center to B223 Information
Transfer Building: - Are round covers acceptable for new hand holes? SOW states round covers in 2.2.10, but also calls out for torsion lid in 2.2.14.1.1.
a. Disregard call for torsion lid. Only round covers will be used.
18. All (3) SOW - General Question: - Will the contractor be required to fit any existing man holes or hand holes with LockDown devices?
a. Please refer to section 2.2.10 New Maintenance Holes/Hand Holes “. Round hand hole covers shall be cast with 1/8” raised letters stating “COMMUNICATIONS” displayed on the outside and shall be fitted with a locking mechanism. LockDown Device with Abloy locks or equivalent are use as locking mechanism.”
19. The SOW 2 Building B‐4414 does the NEMA 3R j‐box and conduit install for the fiber optic cable for this building need to meet hazardous location requirements class 1 division 1 or 2?
a. Disregard NEMA 3r. All J-Boxes will be NEMA 4.
b. Building 4414 will require class 1 division 2 from HH-108A
20. SOW 2 Building B‐4407 can what type of structure is the NEMA 3R J‐box required to be mount on?
a. Disregard NEMA 3r. All J-Boxes will be NEMA 4.
b. Building 4407 will have its J-box mounted on a Unistrut A frame.
21. Please confirm the size of Manhole L x W x D
a. Addendum 1 corrects the manhole size to 6’ x 6’ x 6’
22. Please confirm there are explosion proof J boxes at bldg. 4419 and 4421.
a. Class 1 Division 2 conduits and J-Boxes will be required from HH-108A to building 4419 and
4414 but will not be required for building 4421.
SECTION I - CONTRACT CLAUSES
The following have been modified:
SECTION J
SECTION J
Document Type Description Pages Date Attachment 1 SOW 1 C2-D2-FOC B-404 81 to B223 ITN 29 23 Apr 18 Attachment 2 SOW 2 C2-D2-FOC Fuels Depot 28 23 Apr 18 Attachment 3 SOW 3 FOC 3501-1101 32 23 Apr 18 Attachment 4 Past Performance Questionnaire 3 Undated Attachment 5 Past Performance Reference List 1 Undated Attachment 6 Wage Det MS180141 5 05 Jan 18 Attachment 7 Notice of Compliance 2 Undated Attachment 8 SF 1444 2 Undated Attachment 9 Addendum 1 7 15 June 18
(End of Summary of Changes)