RFI Volley Ball Court v4.pdf
PDF 95 KB Posted
- Solicitation number
- FA286026Q0040
About this file
This document is a Request for Information (RFI) Government Response consisting of 31 questions and answers regarding a volleyball court renovation project at Joint Base Andrews.
The project involves removing and replacing sand and liner materials in a 45' x 75' volleyball court located near Building B1657 and dormitory facilities. Existing sand depth measures approximately 12 inches around the perimeter and 3-4 inches toward the center, with an existing compacted base in place. The contractor must install a minimum 12-inch compacted sand depth across the entire finished court using commercially available beach/volleyball sand meeting particle-size requirements of 0.50-1.00 mm, with product data required prior to installation. A new liner must comply with PWS Section 3.3.4 specifications, and durable perimeter edging is required that prevents grass encroachment, remains flush with grade, and resists UV degradation and corrosion. All existing sand must be removed and disposed of off-base in accordance with applicable Federal and Maryland environmental laws, with no approved on-base relocation options currently available. The existing drainage system requires no repairs and should be protected during work. Existing net posts, believed to be set in concrete, must be protected throughout construction or carefully removed, stored, and reinstalled if necessary. Preparation of the underlying sub-base requires removal of vegetation and debris without major excavation. Commercial dump trucks and sand-delivery vehicles are permitted direct access to the work area during JBA Pearl-Harbor commercial inbound lane operations (0500-1600 Monday-Sunday) and outbound operations (until 2100 daily). A laydown/staging area is available near B1657. Contractor personnel requiring long-term base access badges need approximately 5 business days for processing, and sand delivery drivers require base passes. An AF Form 103 (Base Civil Engineering Work Clearance Request) is required for excavation exceeding three inches and must be processed by Base Civil Engineer staff or Civil Engineering Squadron, with unknown lead time. Contractors shall coordinate all work operations with the government project manager and notify the government immediately of any unforeseen subsurface conditions before proceeding. Wage determination requirements apply per Clause 52.222-42 with the proper wage determination attached. The offer due date is 1200 PM EDT on 08 September 2026. No minimum self-performance requirements exist for the prime contractor, allowing subcontracting to other small businesses.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment - FA286026Q00400001.pdf | ||
| Volleyball Court Staging Area Map.jpg | JPG image | |
| WD_BeachVolleBallCourt_B1657.pdf | ||
| VB4.jpg | JPG image | |
| VB2.jpg | JPG image | |
| VB6.jpg | JPG image | |
| VB3.jpg | JPG image | |
| PWS_VolleyBallCourt_B1657_Final.pdf | ||
| Addendums52.212-1and52.212-2_VolleyBallCourt_B1657_Final.pdf | ||
| VB5.jpg | JPG image | |
| VB1.jpg | JPG image | |
| VB7.jpg | JPG image | |
| Solicitation - FA286026Q0040.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI # RFI Government Response 1 Existing Sand Quantity: Can the
Government provide the approximate existing depth and/or quantity of sand currently in the volleyball court?
12" around the boarder and 3"- 4" towards the center.
2 Required Sand Depth: Please confirm that the required minimum 12-inch compacted sand depth applies across the entire finished 45' x 75' court.
See PWS sections 3.3.2
3 Edging: Can the Government provide the approximate linear footage and/or any preferred material, manufacturer, or product specification for the required perimeter edging?
In the PWS, section 3.3.5 addresses this " Install durable edging, that prevents grass encroachment, remains flush with grade, and resists UV degration and corrosion
4 Site Access/Staging: Where will the contractor be permitted to stage equipment, trucks, materials, and removed materials during performance?
Map Attached.
5 Delivery Access: Are commercial dump trucks and sand-delivery vehicles permitted to access the volleyball court area directly? Are there any specific vehicle-size, delivery-hour, or access restrictions bidders should include in their pricing?
Yes, they are permitted to enter the area directly. JBA Pearl-Harbor (Commercial) inbound lane operates 0500 - 1600 Monday to Sunday. Outbound lane closes @2100 everyday.
Security Processing: What is the anticipated processing time for contractor and subcontractor personnel requiring long-term base access badges?
5 business days of processing to ensure long-term access granted.
7 Prime Self-Performance: Does the Government have a minimum self-performance requirement for the prime contractor under this solicitation?
This contract does not have limitations on subcontracting to other small businesses
8 Exact Work Location: Please confirm the exact location of the volleyball court in relation to Building B1657 and whether the reference in the PWS to the "dormitories" is intended to identify the same work location.
Map attached.
10 Sand Disposal: Is the contractor required to remove and dispose of all existing sand off Joint Base Andrews, or is there an approved on-base location where the existing sand may be relocated, stockpiled, or reused?
The contractor is required to remove and dispose of all exisiting sand. To date there is no approved on base location for the sand to be relocated to.
11 Sand Specification: The PWS requires washed white silica or quartz sand with a particle size of 0.50–1.00 mm. Will the Government accept a commercially available beach/volleyball court sand that meets the required particle-size range and performance characteristics if the supplier's product data demonstrates compliance, or must the material specifically be identified by the supplier as silica or quartz sand?
Gov't could accept a commercially avaliable beach/volleyball court sand so as long as product data is provided to to demonstrate compliance with what the PWS states
For the new liner, is there a required material type, thickness, or minimum specification beyond the solicitation/PWS?
Reference the PWS.
Section 3.3.4 (page 9 )
Is the existing drainage system to remain in place, with the contractor only protecting it during removal and replacement, or is any drainage repair/replacement included in scope?
Currently, there are no issues with the existing drainage system
For the approximately 16 inches of new volleyball sand, may the contractor use locally sourced washed beach/volleyball sand meeting the performance requirements, or is a particular gradation/specification required?
Gov't could accept a commercially avaliable beach/volleyball court sand so as long as product data is provided to to demonstrate compliance with what the PWS states
For disposal of the removed sand and liner, are there any Government-directed disposal, hauling, recycling, or documentation requirements beyond lawful off-site disposal?
No - so as long as state and federal laws are followed
Confirm whether any sand product submittal, approved manufacture, or additional gradtion requirement is required beyond the PWS specification.
Whatever sand is used - there needs to be product data given before install
Provide the required geotextile minimum weight, class/strenght, woven or non-woven preference, and overlap or seam requirements, if any.
No additional minium weight, class/strength seam, or overlap requirement is specified.
Confirm the required permiter edging material, size/profile, and installation method.
In the PWS, section 3.3.5 addresses this " Install durable edging, that prevents grass encroachment, remains flush with grade, and resists UV degration and corrosion
Identify the approximate exisiting sand depth and, if known, the material or base condition beneath the existing liner.
12 inches around the perimeter and approx. 3- 4 inches toward the center.
Exisitng site conditions are assumed to be suitable for replacement without major excavation
Confirm whether aggregate stone or other base material is required beneath the new geotextile, or whether the prepared existing subgrade is to remain in place.
Preparation of the underlying sub-base should be done removing any vegetation, debris, etc.
(PWS 3.3.12)
Without any major excavation (PWS 4.2)
Identify any known underground draininge, utilities, piping or structures within or adjacent to the court that must be protected or incorporated into the work.
The assumption is that there is known underground draininge, utilities, piping or structures within the range of the court. There should not be any major excavation done
If unsuitable soil, soft areas, excessive moisture, buried material, or other unforeseen subsurface conditions are encountered, please confirm how the Contractor should proceed and whether additional corrective work will require Government direction before performance.
Gov't should be notified of all unforseen circumstances and obtain direction prior to any action.
(PWS 3.3.12)
Confirm any advance schedueling, daily truck list/manifest, escort, or other coordination required for dump trucks and material delivery trucks entering and exiting Joint base Andrews.
Contractors shall coordinate work operations with gov't project manager.
AF Form 103. PWS paragraph 2.3 is titled "NOT APPLICABLE," but the text below it requires an approved AF Form 103 whenever the ground surface is disturbed deeper than three inches. This work requires excavation to 12 inches or more.
Is an AF Form 103 required for this effort? If so, who processes the request and what lead time should offerors assume?
An AF Form 103 (Base Civil Engineering Work Clearance Request) is processed by the Base Civil Engineer (BCE) staff or the Civil Engineering Squadron (CES) at the Air Force installation where the work is to be performed.
Lead time is unknown.
Wage determination. Clause 52.222-42 is incorporated with the equivalent-rates table left blank. Please confirm that the attached wage determination (Attachment
01) governs this requirement, and identify the labor classifications the Government anticipates. The proper WD is attached
Disposal of existing material. May the removed sand be disposed of as clean fill, or does the Government require characterization or testing prior to offsite disposal
PWS 3.3.6 - All removed sand should be disposed of in accordance w/applicable Federal and Maryland environmental laws
Existing conditions. What is the current depth of sand in place, and is there an existing compacted base beneath the liner? No site visit is scheduled, and this drives both the demolition and subgrade preparation scope
12 inches around the perimeter and approx. 3- 4 inches toward the center.
There is an exisitng compacted base.
Net posts. Are the existing net posts set in concrete footings, and are they to remain in place during excavation
Per PWS 3.3.8 exisiting nets and poles shall be protected throughout construction. If removal is necessary the contractor shall carefully remove, store and reinstall. Exisitng net posts are believed to be in concrete.
Staging. Is a laydown area available near B1657 for sand stockpiling and equipment during performance
Yes
Delivery vehicle access. Will sand delivery drivers require base passes, or may material be received at a staging point?
Given the volume involved, gate processing time affects pricing Drivers will require base passes
Offer due time. Block 8 of the SF1449 states 12:00 AM on 08 Sep 2026; the Addendum to 52.212-1 states 12:00 PM EDT on 08 Sep 2026. Please confirm the correct time. 1200 PM on 08 Sept 26 is the correct time
Sheet1