LRS Wash Rack Vendor Questions - answered.xlsx

XLSX spreadsheet 10 KB Posted

Attached to
Wash Rack Removal Federal contract opportunity
Solicitation number
FA286024Q4013
Issued by
Department of the Air Force Headquarters District Washington

About this file

This document is a set of questions and answers related to a federal contract opportunity for the removal and disposal of a wash rack at Building 3356 on Joint Base Andrews in Maryland. The key details are:

The contract opportunity is solicitation number FA286024Q4013, issued by the Department of the Air Force Headquarters District Washington, for a SDVOSB set-aside. The work involves removing and disposing of the existing wash rack at Building 3356 according to the Performance Work Statement (PWS). The PWS specifies that the successful offeror must provide all necessary personnel, equipment, tools, materials, vehicles, supervision, and services to complete the removal. No new work is to be installed. A site visit is scheduled for June 18, 2024, and responses are due by a deadline provided in the Combined Synopsis. The document answers various questions about the project, such as required permits, equipment access, demolition points for utilities, and confirmation of the scope of work outlined in the PWS.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

Will any specific permits for the project need to be requested?Contractor to submit proof of a valid electrician’s license for electrician performing electrical demo. Electrician must be licensed in the State of Maryland.
What's the process to bring large equipment i.e. Genie Lift, dumpster etc, onto the installation?More guidance will come in regards to getting equiptment on to the base
Confirm wiring and conduit for all equipment in scope are to be demolished to the existing panel and that the panel is ETR.Please refer to SOW Section 1.1 Specific Requirements. Electrical Panel to Remain. All lines flowing downstream from the electrical sub panel that powers the incidental equipment shall be removed.
Confirm desired demolition point for existing gas lines is the meter on the Northwest side of B3356.Please refer to SOW Section 1.1 Specific Requirements.
Please indicate desired demolition point of existing water lines.Please refer to SOW Section 1.1 Specific Requirements.
Confirm Two (2) existing high bay heaters w/ exhaust are ETR.Yes. Please refer to SOW Section 1.1 Specific Requirements.
PWS pg. 3 section 1.1 indicates a single 13”x13” roof patch. Confirm Three (3) approximately 13”x13” roof patches.Patches are no longer needed. Please refer to SOW Section 1.1 Specific Requirements.
Confirm no new work to be installed.No new work is to be installed. Please refer to SOW Section 1.1 Specific Requirements.
Will the water pumps and air compressors need to be removed a well?No. Please refer to SOW Section 1.1 Specific Requirements.
Does the job only involve the interior of the building and the supply room on the side?Please refer to SOW Section 1.1 Specific Requirements.