This is a Performance Work Statement (PWS) for water tank repair, cleaning, and inspection services at New Boston Space Force Station in New Boston, New Hampshire.
The project encompasses the inspection, cleaning, and repair of two underground concrete water storage tank systems: Building 135 (B135), which contains three chambers totaling 114,500 gallons (two 55,000-gallon chambers and one 4,500-gallon pump chamber), and Building 107 (B107), which contains a single 60,000-gallon chamber. The contractor must maintain potable water supply to the distribution system throughout the project. Specific work elements include: replacing all tank pump intake screens, replacing two broken isolation valves controlling water flow to B135 chambers, repairing superficial cracking on the exterior of B107 (limited to the lowest two feet), inspecting each tank per New Hampshire Department of Environmental Services (NHDES) regulations, and providing written inspection reports with photographs. The contractor must obtain a temporary groundwater discharge permit from NHDES, implement environmental controls using water discharge filter bags and erosion control measures, produce confined space entry permits, and coordinate all testing and return-to-service activities with government personnel. B135 must be cleaned, inspected, and accepted by government before B107 cleaning begins, with government requiring approximately 48 hours per chamber for bacterial contamination testing. The contractor is responsible for project management, scheduling, temporary utilities, traffic control, environmental protection, waste disposal, and closeout documentation. All work must comply with American Water Works Association standards, NSF certification requirements, NHDES regulations, and Department of Defense Unified Facilities Criteria and Guide Specifications. The performance period allows 8 weeks for construction submittals and approval, followed by 6 weeks for construction and closeout, totaling 14 weeks. All personnel require escort (5-to-1 ratio) and security processing for access to the High Security Area.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW RNGF202XXXXX B107_135 Water Tanks Repair_Cleaning _Inspection 20260206
CUI
CUI
NEW BOSTON SPACE FORCE STATION, NH
PERFOMANCE WORK STATEMENT (PWS)
PWS RNGF202XXXXX B107_135 Water Tanks Repair_Cleaning_Inspection
1. GENERAL
1.1. LOCATION:
New Boston Space Force Station (NBSFS) is located at:
317 Chestnut Hill Road
New Boston, NH 03070
1.2. EXISTING FACILITIES: Under normal operation, water from Building 134 (B134, well #1)
& B111 (well #2) is transferred into B135. B135 houses a 100-gpm radon air stripper and tablet chlorinator. Water is passed through the radon air stripper, and disinfection of the well water is accomplished by dissolving chlorine tablets into the water stream leaving the radon air stripper prior to it entering the 114,500-gallon storage tank below B135 from the northeast corner. B135
114,500-gallon storage tank consists of three (3) tank chambers: two (2) tank chambers, Tank
Chamber A (west) and Tank Chamber B (east), containing 55,000 gallons each, and one (1) central Pump Chamber C containing approximately 4,500 gallons, two (2) pumps, and two (2) valves. Within the east tank chamber there is a sump pit (sump pit is a basin installed below floor level to collect water and prevent flooding) in the southwest corner, and within the west tank chamber there is a sump pit in the southeast corner. The valve leading to Tank Chamber
B is currently broken, and the contractor will replace both controlling valves separating the
Pump Chamber C from Tank Chambers A & B. When isolation is required, central Pump
Chamber C inspection, cleaning, and repair shall be accomplished concurrently with Tank
Chamber B (east). Tank Chamber A (west) inspection, cleaning, and repair are accomplished separately. B135 must be cleaned first by the contractor and then filled and BACT tested as three separate chambers by government personnel, each taking approximately 48 hours. B107 shall be isolated from B135 and provide service while B135 is cleaned. The contractor shall schedule work so that B135 is completely cleaned, inspected and accepted prior to B107 cleaning commencing.
1.2.1.Additional B135 equipment includes two (2) electric fire pumps, a tank discharge pump, and two (2) Variable Frequency Drive (VFD) controlled transfer pumps. The tank discharge pump allows for draining the entire 114,500-gallon storage tank or each individual chamber for maintenance, or in emergency situations. NOTE: If using tank discharge pump to drain Tank Chamber C either Tank Chambers A or Tank Chamber
B must be drained at the same time. Pumped water exits building into a discharge swale east of B135. Environmental controls must be in place and maintained to prevent erosion by water under Restricted Area RA-1 fence.
1.2.2. Transfer pumps in Pump Chamber C B135 send potable water to 60,000-gallon concrete storage tank below B107. Tanks are used for potable water storage and water reserve for fire suppression. Potable water from B135 enters B107 addition where it can be disinfected by passing through a tablet chlorinator before entering B107 60,000-gallon tank.
CUI
CUI
1.2.3.B107 houses two (2) 100-gpm domestic pumps drawing water from 60,000-gallon storage tank into water distribution system. B107 also houses one (1) 1,500gpm electric fire pump.
Fire pump draws from 60,000-gallon storage tank and connects to water distribution system. B107 does not have a functional drain, therefore the tank must be drained with a sump pump.
1.3. PERMITS REQUIRED: Tanks are considered permit-required confined spaces. A temporary ground water discharge permit is required. (Refer to para. 3.1 and 3.3)
1.4. OVERVIEW: This project repairs, cleans and inspects B135’s three (3) chambers, and B107’s one (1) chamber underground water storage tanks, while maintaining potable water supply to water distribution system. Generate a report at close out in compliance with New Hampshire
Department of Environmental Services (NHDES) and contract requirements. All tank pump pipe screens shall be replaced. Complete concrete repairs for all tanks as encountered.
Inspected/test Linkseal around pipe penetrations and repair/replace as needed.
1.5. ESCORT(S) REQUIRED: All tanks are in the High Security Area, Restricted Area (RA-1), requiring escort (5 to 1 ratio) and completion of security processing. (01 80 00 NBSFS
General Requirements Security)
1.6. PROPOSAL COST ESTIMATE: Provide specific cost details for each work element via a
Work Breakdown Structure identifying separate costs for materials, labor, and equipment for each building. (B107_135)
1.7. FIELD VERIFICATION: The contractor shall field-verify information given and conditions in place. Specifically identify all facilities, available utilities, concrete underground water tanks, shutoff valves, and B107_B135 access for work listed within. Tanks are considered permit required confined spaces requiring a Competent Person to issue the permit and supervise work.
1.8. UTILITIES LOCATE: No excavation is expected on this project; therefore, no ground-penetrating radar (GPR) is required. Should the contractor need to excavate to perform, the contractor is required to perform GPR and identify all utilities in the area. Installation and staking of erosion controls are not expected to encounter utilities unless 18” or more ground penetration (communication cabling).
1.9. WORK PLAN_ACCIDENT PREVENTION PLAN: Plans shall include procedures to protect personnel working in and around water tanks, including within permit required confined spaces, and incorporate local confined space entry/exit log requirements. Identify in Accident
Protection Plan and Work Plan exactly how personnel will be protected and how contractors shall provide protection(s) in place prior to work start and tanks access. This should include at least one Activity Hazard Analysis (AHA) for confined space entry, naming the Competent
Person and providing credentials.
1.10. REGULATORY REQUIREMENTS: The contractor shall coordinate and execute all necessary regulatory reviews, and permit acquisition, including paying the appropriate fees.
Perform all work in accordance with federal, state, and local statutes, regulations, and codes.
Verify the design for this project will not require coordination with and approval by NH DES
CUI
CUI
prior to any work start. All debris shall be taken to a regulated landfill and manifests promptly submitted to COR in Adobe PDF within 30 days of delivery.
1.11. PROJECT MANAGEMENT: The contractor will be responsible for project management, scheduling, inspection and testing services, maintenance of project temporary utilities, temporary controls, traffic control, environmental protection, and project closeout. The contractor will ensure technical accuracy and adequacy of the project design at every submission, providing quality control in all three phases of the project and annotating on required daily reports.
1.12. MEANS & METHODS: The contractor will engage early in the process to allow for the development of the most cost-effective and technically sound solution. Government will rely on the contractor’s expertise in recognizing and addressing problematic issues and successful execution of this project.
1.13. CONCRETE REPAIRS SUBMITTALS: Concrete repairs shall only use materials allowed for water storage tank’s concrete repair, including add in materials. All materials shall be submitted for review and shall clearly reflect material is safe and approved by American Water
Works Association (AWWA), National Sanitation Foundation (NSF), and NHDES for concrete repair of domestic concrete water storage tank repair and for use in drinking water systems. (See
Design Criteria references section)
1.14. LINKSEAL PENETRATIONS: Any repairs to concrete tank pipe penetrations shall be repaired/replaced with a product comparable to Linkseal, suitable for use in drinking water systems and shall clearly reflect material is safe and approved by contract documents, AWWA, NSF, NHDES for repair of domestic concrete water storage tanks and in drinking water systems.
2. PROJECT CRITERIA
2.1. UNIFIED FACILITIES CRITERIA (UFC) WEBSITE: This section lists site specific requirements and where none are specified follow the Department of Defense Unified Facilities
Criteria (UFC) program at: https://www.wbdg.org/dod/ufc.
2.2. UNIFIED FACILITIES GUIDE SPECIFICATIONS WEBSITE: This section also lists site specific requirements and where none are specified follow the Department of Defense Unified
Facilities Guide Specifications (UFGS) program at: https://www.wbdg.org/dod/ufgs
2.3. DESIGN CRITERIA: UFC, UFGS, and listed references listed in the RFP package are to be considered text in full for the contractor to read and understand in full for execution of this project. Include below listed UFC/UFGS/References:
2.3.1. American Water Works Association (AWWA) Standards, (http://www.awwa.org/publications/standards.aspx)
2.3.2. New Hampshire Department of Environmental Services (NH DES) Code of
Administrative Rules (CAR), (https://gc.nh.gov/rules/State_Agencies/env-dw500.html#:~:text=PART%20Env%2DDw%20504%C2%A0%20PUBLIC%20WATER
%20SYSTEM%20MAINTENANCE%20REQUIREMENTS).
2.3.3. National Sanitation Foundation (NSF).
CUI
CUI
2.3.4. UFC 1-200-1, DoD Building Code
2.3.5. NBSFS UFGS 01 GENERAL REQUIREMENTS SUPPLEMENT 20241209 (attached)
2.3.6. NBSFS UFGS 01 80 00 SECURITY 2025730 (attached)
2.3.7. UFGS 01 11 00 SUMMARY OF WORK
2.3.8. UFGS 01 14 00 WORK RESTRICTIONS
2.3.9. UFGS O1 30 00 ADMINISTRATIVE REQUIREMENTS
2.3.10. UFGS 01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULE
2.3.11. UFGS 01 33 00 SUBMITTAL PROCEDURES
2.3.12. UFGS 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD)
2.3.13. UFGS 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
2.3.14. UFGS 01 45 00 QUALITY CONTROL
2.3.15. UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
2.3.16. UFGS 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
2.3.17. UFGS 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
2.3.18. UFGS 01 78 00 CLOSEOUT SUBMITTALS
2.3.19. UFGS 01 78 23 OPERATION AND MAINTENANCE DATA
2.3.20. UFGS 02 41 00 DEMOLITION
2.3.21. UFGS 03 01 00 REHABILITATION OF CONCRETE
2.3.22. UFGS 33 11 00 WATER UTILITY DISTRIBUTION PIPING
2.4. REFERENCES REQUIRED: Additional work, or work not included in listed criteria (e.g., unforeseen site conditions), shall require submittal of additional appropriate United Facilities
Criteria (UFC)/United Facilities Guide Specifications (UFGS)/ New Hampshire Department of
Transportation (NHDOT) reference criteria as part of the related submittal or proposed change for incorporation into the contract.
2.5. RECORD INFORMATION: Record documents are maintained in NBSFS Engineering (CEP).
The Contracting Officer’s Representative (COR) will provide all related record data in support of bids at the pre-bid site visit, including post-award access to existing site plans, maps, building plans, etc. The government does not guarantee that all plans are available for review, nor does it guarantee the accuracy of those plans. Specifically, AutoCAD drawings shall be provided to winning bidder for design/build if available and necessary for as-built drawings.
3. SCOPE OF WORK: Work under this project includes, but is not limited to the following for each building:
3.1. TEMPORARY GROUNDWATER DISCHARGE PERMIT: Complete and submit temporary groundwater discharge permit application to NH DES Groundwater Discharge
Program. A copy of a blank application form can be found here:https://onlineforms.nh.gov/nform//app/#/formversion/815e7eff-7f1b-41e4-8d68-
61b6eb621f8f. Government will review and approve permit submittal prior to contractor sending to NH DES. The contractor will submit a copy of approved discharge permit to government once received. No work will be permitted until a temporary discharge permit has been acquired and a copy provided to government.
3.2. ENVIRONMENTAL CONTROLS: Abide by the temporary discharge permit requirements during work completion. Typically, NHDES requires use of a water discharge filter bag, and erosion control measures. The contractor will acquire water discharge filter bags and erosion
CUI
CUI
control measures at no additional cost to the government and will ensure compliance with discharge permit. The contractor will utilize wooden stake and erosion log method as shown in attached erosion control standard plan, unless otherwise directed by government.
Environmental controls shall be checked daily at the beginning of the day and after any weather event of more than .25-inch precipitation. Inspections shall be documented and submitted to
COR along with the contractor’s Daily Inspection Reports.
3.3. CONFINED SPACE ENTRY: Produce confined space entry permit for water tanks entry. A copy of the permit(s) shall be available on site for inspection upon request by Contracting
Officer’s Representative (COR) and NBSFS Safety Office prior to tanks entry. Attach copy of all permits to Daily Inspection Report upon submittal to COR.
3.4. TANK INSPECTIONS: Inspect each tank according to NHDES regulation. During inspection, each tank or chamber shall be individually evaluated for structural strength, corrosion, and other factors related to water quality and tank integrity. The contractor shall submit to the government a written inspection report, including photographs of interior and exterior including any installations and repairs, recommendations for each water tank, including further delineating each of the three (3) B135 chambers.
3.5. TANK REPAIRS: Repair one (1) B107 tank, and three (3) B135 concrete water tank and pump chambers as damage is identified as part of contract. Specifically repair superficial cracking on exterior of B107. Repairs will be limited to lowest two (2) feet of exposed concrete around exterior of B107. All repairs shall be photographed before and after repairs and included in report.
3.6. INTAKE SCREENS REPLACEMENT: Replace intake screens for at least one (1) B107 and two (2) B135 tank pumps.
3.7. REPLACE TWO VALVES: Replace the two (2) valves and valve stems and associated hardware controlling water to B135 Chambers A & B. The valve isolating Tank Chamber B from the Pump Chamber C is currently broken, and the contractor will replace both valves controlling valves to Tank Chambers A & B. Isolating valve to Tank Chamber B needs to be repaired/replaced prior to Tank Chambers A being cleaned/inspected.
3.8. TEMPORARY GROUNDWATER DISCHARGE PERMIT CLOSURE: Complete and submit an email to NHDES following completion of all onsite activities, allowing for closure of temporary groundwater discharge permit. The contractor shall submit a copy of email to the government including any reply from NHDES indicating that permit has been closed.
3.9. MISCELLANEOUS WORK: Accomplish miscellaneous work items not specifically called out above, but necessary to safely and thoroughly complete project such as adjustment of erosion control measures based on actual water discharge paths, installation of roadway safety barriers, loading and hauling extra material off-site, and daily worksite cleanup.
4. SUBMITTALS: The contractor shall provide submittals specified in Statement of Work (SOW) and UFC/UFGS/References to the Contracting Officer and COR for approval. The contractor shall allow the government up to 14 calendar days to review submittals. Disapproved submittals shall be re-accomplished by the contractor at no additional cost to government. Follow procedures in UFGS
01 33 00 SUBMITTAL PROCEDURES for submittals. Submit an AF3000 for each submittal.
CUI
CUI
4.1. Temporary Groundwater Discharge Permit application, to include site-specific erosion control plan, for government review and signature prior to NHDES submission.
4.2. Temporary Groundwater Discharge Permit approval issued by NHDES.
4.3. Sample Confined Space Entry Permit for water tanks entry.
4.4. Work Plan, to include work schedule, materials and appurtenances, specification sheets, and chemical SDSs.
4.5. Security documents necessary for New Boston SFS access. (RAB/VAA/VAR See NBSFS
UFGS 01 80 00 SECURITY 2025730)
4.6. Accident Prevention Plan. (EM385-1-1, Army Corps of Engineers Safety Plan, Appendix A)
Include Confined Space Entry Plan and AHA(s).
4.7. Written inspection report, including photographs and recommendations, for each water tank.
4.8. Email correspondence to and from NHDES indicating work completion and notice of permit closure.
4.9. Solid Waste Management Monthly Reports and weight tickets for waste generated from project activities.
4.10. Concrete repairs products with SDSs.
4.11. Pump screens product.
4.12. Cleaning products with SDSs.
4.13. Sanitizing products with SDSs.
4.14. Provide one Adobe PDF copy of all documents within submittal to the Contracting Officer and
COR.
4.15. Draft(s) & Final Inspection Report for all tank work, repairs, and inspections performed on
B107 & B135 tanks. Include repairs made, inspection checklists (signed), photo documentation, correspondence with NHDES, and other data as necessary to provide all
NHDES inspection requirements in one document.
5. MISCELLANEOUS PROJECT REQUIREMENTS
5.1. SECURITY: Follow NBSFS UFGS 01 80 00 SECURITY 2025730 for security requirements. Work on this project is within high security area of New Boston SFS. The contractor shall coordinate base access for all workers under this project. The contractor shall provide all escorts (five personnel/escort and must be in same vicinity, i.e., an escort can’t observe personnel at B107 and B135 at same time) for all work associated with this project.
Government personnel will assist with opening and closing valves and removing tank covers.
Restricted Area Badge (RAB) processing is lengthy, so it is highly recommended to initiate immediately after award documents are signed.
5.2. FUEL SPILLS: The contractor shall be responsible for cleaning up all fuel spilled during performance of work under this project. Clean up work associated with fuel spills will be subject to approval of the Contracting Officer. The contractor shall clean up fuel spills immediately in accordance with the requirements outlined in the applicable State of New
Hampshire Department of Environmental Services (NHDES) regulations. In addition to state officials, the contractor shall immediately notify COR, New Boston SFS environmental office, and New Boston fire department of any fuel spills greater than 1 gallon.
5.3. ACCIDENT PREVENTION PLAN: The contractor shall submit a proposed Accident
Prevention Plan to the Contractor Officer for approval. No work will start on the project until
CUI
CUI
the government approves the contractor’s Accident Prevention Plan. Follow requirements of
EM 385-1-1, Army Corps of Engineers Safety Manual, for plan and safety and health requirements, specifically Appendix A.
5.4. SUBMITTALS: The contractor shall submit specification sheets for each new appurtenance proposed for installation and all material used to complete the tasks within this statement of work to Contracting Officer for approval. No work will start on project until government approves contractor’s specification documents. All materials used shall meet referenced standards.
5.5. WORK SCHEDULE: The contractor shall submit a proposed work schedule to Contracting
Officer for approval. No work will start on the project until government approves the contractor’s work schedule. New Boston SFS hours of work are from 0700 – 1600 EST excluding weekends and public holidays.
5.6. CHEMICAL SUBMITTALS: The contractor shall submit all materials brought for planned use on New Boston SFS to the Contracting Officer including safety data sheet (SDS).
Specifically, any chemicals used onsite.
5.7. RETURN TANKS TO SERVICE AND BACTERIAL CONTAMINATION TESTING:
Only government personnel are authorized to refill chambers and tanks and test for bacterial contamination. The contractor will immediately notify government when all work tasks are completed for each chamber or chamber set (Tank Chamber B and Pump Chamber C shall be accomplished concurrently) at B135, and tank at B107. Once notified, government requires 48 hours to perform testing for bacterial contamination, determination of safe drinking water, and returning to service. The contractor will not continue with the next tank or chamber until government confirms a negative bacteria result. The contractor shall clearly represent time required for testing and returning to service in the proposed work schedule.
5.8. CLOSEOUT: All work completed under project is subject to final inspection and acceptance by the Contracting Officer and the Contracting Officer’s Representative. The contractor shall arrange for a final project inspection with Contracting Officer when work has been completed.
All incomplete and/or deficient work items identified by Contracting Officer shall be completed and/or repaired to the satisfaction of Contracting Officer at no additional cost to government.
6. GOVERNMENT PROJECT MANAGER: 22 SOPS/DET 6/CEO
7. PLANS/DRAWINGS AND AS-BUILT INFORMATION: There are no design or construction drawings for this project. Should drawings become a necessity, provide ESRI ArcGIS and
AutoCAD data most current versions for installed work. Comply with accuracy and other standards at Spatial Data Standards for Facilities, Infrastructure, and Environment (SDSFIE) available at:
https://www.sdsfieonline.org/Home/Index
CUI
CUI
8. PRE-PROJECT CONFERENCE: Prior to physical construction, the contractor shall attend a pre-construction meeting held at New Boston SFS to discuss project requirements such as, but not limited to safety, security, site access, and environmental requirements. Conference will be held in attendance at New Boston SFS B120 Conference Room. At least one representative from all sub-contractor companies shall attend meeting. At their discretion, Contracting Officer may utilize teleconference for meeting.
9. PERIOD OF PERFORMANCE:
9.1. Construction submittals and approval: 8 weeks from Notice to Proceed.
9.2. Construction and Closeout once submittals are approved: 6 weeks, total 14 weeks.
10. ATTACHMENTS:
10.1. Work Locations Water Tank Cleaning
10.2. NBSFS UFGS 01 GENERAL REQUIREMENTS SUPPLEMENT specification
10.3. NBSFS UFGS 01 80 00 SECURITY specification
10.4. Visitor Access Authorization (VAA)
10.5. Process Flow Diagram NBAFS v4
10.6. Previous inspection and cleaning reports
10.7. B135 Tank Dimensions 4-Structural Details-Water Tank
Policies
0.0 Contractor Access to Department of the Air Force Installations
• The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Department of the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
• The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and [ insert any additional requirements to comply with local security procedures ] to obtain a vehicle pass.
• During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
• When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with DAFI 31-101, CUI
CUI
Integrated Defense, and DODMAN5200.02 DAFMAN 16-1405 , Air Force Personnel Security
Program] citing the appropriate paragraphs as applicable.
• Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
• The contractor shall provide an after-hours contact number or after-hours email in the
Emergency Mass Notification System (EMNS) for each of their personnel, whose normal place of duty is on a DoD installation or within a DoD facility. The contractor shall comply with any additional requirements in DAFMAN 10-206 for emergency operational reporting. Foreign
Nationals may participate and may remove themselves from the Emergency Mass Notification
System at any time. To update information, personnel can access the globe icon on their system desktop screens and choose the “Access Self-Service” option.
• Failure to comply with these requirements may result in withholding of final payment.
1.0 Health and Safety on Government Installations
2.0 In performing work under this contract on a Government installation, the contractor shall:
1. Take all reasonable steps and precautions to prevent accidents and preserve the health and safety of contractor and Government personnel performing or in any way coming in contact with the performance of this contract; and
a. Take such additional immediate precautions as the contracting officer may reasonably require for health and safety purposes
2. The contracting officer may, by written order, direct Department of the Air Force Occupational
Safety and Health (AFOSH) Standards and/or health/safety standards as may be required in the performance of this contract and any adjustments resulting from such direction will be in accordance with the Changes clause of this contract.