This Statement of Work (SOW) details an urgent air conditioner repair project for Building 15312 at Duke Field, 96th TW facility. The scope involves repairing five non-functioning air conditioning units before additional units fail. Specific repair requirements include replacing evaporator coils on units A, H, G, and F; replacing the compressor on unit G; and replacing the condensing fan motor for unit J. All units are Bard brand, exterior wall-mounted, with 3-ton capacity.

Detailed repair specifications for each unit include installing new evaporator coils, evacuating and recharging systems with R410A refrigerant, and performing additional component replacements such as drier and capacitor replacements. Unit G requires extensive work, including a 2.0-ton compressor change-out, blower motor replacement, and refrigerant recovery. The repairs are critical to prevent further system failures and maintain operational capabilities at the facility.

View the file

Other files

File Type Posted
Model numbers.jpg JPG image
SITE VISIT.pdf PDF
DAF-Contracting-SPE-Delegate--Open-Letter-to-Contractors-21-Mar-25.pdf PDF
USA000368-25-DPCAP.pdf PDF
USA000392-25-DPCAP.pdf PDF
COMBO_Redacted.pdf PDF
HVAC_SOW PDF.pdf PDF
SITE VISIT.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

for

Air conditioner repair at Bldg. 15312 Duke Field

1.0 INTRODUCTION

1.1 Background

Urgent air conditioner repair at Duke Field 96th TW (15312) facility that has no current maintenance contract

1.2 Scope

Multiple (5) air conditioning units are currently not working and need repair before more of the units fail due to strain.

2.0 TECHNICAL REQUIREMENTS

At a minimum, the Contractor shall accomplish the requirements of this order through fulfilling the following specifications:

• Replace the evaporator coils on unit A, H, G and F. Replace the compressor on unit G, and replace the condensing fan motor for unit J. Pull units A, F, H, and G into a vacuum, and charge according per manufacturers specifications..

3.0 DELIVERABLES

Unit A: Replace Evaporator Coil and Recharge

Install New Evaporator Coil (Up flow A-Coil) Recharge the system with R410A Evacuate the system to remove impurities prior to recharge Type of Unit- Exterior Wall Brand- Bard Serial numbers- 278J1936739-02 Tonnage- 3

Unit F: Replace Evaporator Coil and Recharge

Install New Evaporator Coil (Up flow A-Coil) Recharge the system with R410A Evacuate the system to remove impurities prior to recharge Type of Unit- Exterior Wall Brand- Bard Serial number-278J193671749-02 Tonnage- 3

Unit G: Refrigerant Leak at evaporator has caused it to lose all the Refrigerant Compressor is inoperable Install New Evaporator Coil (Up flow A-Coil)

Evacuate the system to remove impurities prior to recharge Recharge the system with R410A Replace 2.0 Ton Compressor Change Out 1 Phase to include: Up to 8lbs of refrigerant Drier replacement Capacitor replacement Refrigerant Recovery

1/2HP-1/6HP, 1075/240V

Rescue Blower Motor Replace an inoperative blower motor Type of Unit- Exterior Wall Brand- Bard Serial number- 278J193671742-02 Tonnage- 3

Unit H: Replace Evaporator Coil and Recharge Install New Evaporator Coil (Up flow A-Coil) Recharge the system with R410A Evacuate the system to remove impurities prior to recharge Type of Unit- Exterior Wall Brand- Bard Serial number- 278J193671745-02 Tonnage- 3

Unit J: Condenser Fan Motor is Inoperable Replace Condensing Fan Motor w/ capacitor Condenser Motor 825 RPM Replacement of 825 RPM condenser fan motor w/new capacitor Open system disconnects, check electric power "OFF", remove old motor & capacitor, install new, check fan operation Type of Unit- Exterior Wall Brand- Bard Serial number- 278J193671740-02 Tonnage- 3

STATEMENT OF WORK
Air conditioner repair at Bldg. 15312 Duke Field
1.0 INTRODUCTION
2.0 APPLICABLE DOCUMENTS
3.0 TECHNICAL REQUIREMENTS
4.0 DELIVERABLES