Questions and Answers-FA282319RA012 05 July 2019

View the file

Other files for this federal contract opportunity

Other files attached to Renovate Bldg 886, newest first.
File Type Posted
FTFA_17-1100_Pre-Award_Construction_Site_Visit_Sign-In_18_July_2019.pdf PDF
Conformed_Solicit_-_FA282319RA0120007.pdf PDF
Amendment_FA282319RA0120007_SF_30.pdf PDF
FTFA_17-1100_Post_Site_Visit_RFIs_Bldg_886_QA.pdf PDF
Attachment_12-Revised_SPEC_13_34_19_Eng_Canopy_Sys_8_July_2019.pdf PDF
Amendment_FA282319RA0120006_SF_30.pdf PDF
Attachment_10-Updated_BLDG._886_Drawings_8_July_2019.pdf PDF
Conf_Solicit_-_FA282319RA0120006.pdf PDF
Attachment_11-Revised_Section_28_31_64.00_10_Fire_Detection_and_Alarm_8_July_2019.pdf PDF
Bldg_886_Questions_and_Answers_part_2.docx DOCX document
Contractor_Questions_and_Answers_Bldg_886_19RA012.docx DOCX document
Conf_Solicit-_FA282319RA0120005.pdf PDF
Amendment_FA282319RA0120005_SF_30.pdf PDF
50_Div_Cost.xls XLS spreadsheet
Amendment-_FA282319RA0120004_SF_30.pdf PDF
Conformed_Solicit-_FA282319RA0120004.pdf PDF
Conformed_Solit_-_FA282319RA0120003.pdf PDF
Amendment-FA282319RA0120003_SF_30.pdf PDF
Attachment_4-Wage_Determination.pdf PDF
Attachment_2-Bldg_886_Drawings.pdf PDF
Attachment_8-Financial_Responsibility_Questionnaire.pdf PDF
Solicitation_-_FA282319RA012.pdf PDF
Attachment_3-Specification.pdf PDF
Amendment-FA282319RA0120001_SF_30.pdf PDF
Attachment_1-Statement_of_Work.pdf PDF
Conformed_Solicit_-_FA282319RA012.pdf PDF
Conformed_Solicit_-FA282319RA0120002.pdf PDF
Attachment_6-Past_Performance_Questionnaire.pdf PDF
Amendment_FA282319RA0120002_SF_30.pdf PDF
Show all 29

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA2823-19-R-A012/FTFA 17-1100

Renovate Bldg. 886 Solicitation- Contractor Questions

1. Keynote 19 on sheet A201 indicates a pre-engineered metal canopy at the North loading dock and South ramp however no specification is provided. Please provide this specification.

2. The last sentence states “Bid Option will include construction of south side dock as noted in the construction documents.” The SF 1442 does not provide for a line item for this option. Please advise.

3. Reference sheet S-4, Enlarged Plans- Bid Option. The plan view indicates an 8” thick SOG whereas the Legend is calling for a 7” thick SOG which matches the other loading dock thicknesses. Please confirm that the correct thickness is 7”.

4. Reference drawing sheet FP-101 indicates a new 6” fire line from existing 12” Main. What is the distance from the existing 12” Main to the building location? No drawing of the site has been provided for measuring the correct distance.

5. Is it acceptable for the new pre-engineered canopy (13/A301) to be aluminum? Should the finish be Kynar or baked enamel? What color should it be?

a. On sheet A301 the pre-manufactured stairs are shown as aluminum, but the railings along the deck are labeled as galvanized steel (note 11), is this correct?