Statement of Work - Restripe Speed Humps Crosswalks - 16 SEPT 2025.pdf

PDF 1 MB Posted

Attached to
Buckley SFB Crosswalk & Speed Hump Striping/Signage
Solicitation number
FA254325Q0050
Issued by

About this file

This Statement of Work (SOW) details a project for restriping speed humps and crosswalks across multiple locations at Buckley Space Force Base (BSFB) in Colorado. The contractor will be responsible for providing new striping and signage for 12 different crosswalk locations, including installing crosswalk markings, stop bars, and appropriate signage in accordance with the Manual on Uniform Traffic Control Devices (MUTCD). The work includes both new striping for locations without current markings and restriping for excessively worn crosswalks.

Key project requirements include using low-temperature acrylic waterborne paint for parking space striping, epoxy paint for handicap markings, and adhering to various federal and state standards including the Americans with Disabilities Act, CDOT specifications, and Air Force manuals. The project has a 180-calendar day completion timeline from the Notice to Proceed, with specific requirements for traffic control, stormwater management, hazardous material reporting, and operational security. The project will be managed by Eric Riley from 460 CES/CEOER, with the specific work locations mapped and detailed in the document's attachment, covering areas such as Mississippi Gate Entrance, B1022 Outdoor Recreation, Fire Station, and various other base locations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI

STATEMENT OF WORK (SOW)

Project Number: WT# 16936163

Restripe Speed Humps & Crosswalks – Base-wide

16 SEPT 2025

Project Location: Buckley Space Force Base (BSFB), CO

Contract:

Dissemination Control:

Federal Employees or Contractors Only

FEDCON WT# 16936163

i

CUI

Table of Contents

NOMENCLATURE ............................................................................................................... ii

ACRONYMS AND ABBREVIATIONS ........................................................................ ii

BASIC TERMS ................................................................................................................ v

BACKGROUND

SCOPE

New Striping

Field Verification

Closeout

Locations

GENERAL

Specifications

Operational Security

Sanitary Facilities

Radioactive Materials

OSHA Compliance

Scheduling

Advance Notification

Site Stormwater Sediment Controls

Advance Hazardous Material Reporting

Demolished Materials

Soil-Disturbing Activities

Unknown Material

Site Stormwater Management

PROJECT REQUIREMENTS

CDOT SECTION 105– CONSTRUCTION SURVEYING

CDOT SECTION 614– TRAFFIC CONTROL DEVICES

CDOT SECTION 625– SURVEY RECORDS

CDOT SECTION 630– CONSTRUCTION ZONE TRAFFIC CONTROL

ii

CUI

CUI

CDOT SECTION 708– PAINTS

CDOT SECTION 713– TRAFFIC CONTROL MATERIALS

APPLICABLE CODES, PERMITS AND SPECIFICATIONS:

ASTM’s (INCLUDED, BUT NOT LIMITED TO) ........ Error! Bookmark not defined.

UFC AND UFGS STANDARDS (INCLUDED, BUT NOT LIMITED TO)

WINTER EXCLUSION

Points of Contact

ATTACHMENT A: Parking Lot Maps

ATTACHMENT B: ADA PARKING SPACE REQUIREMENTS

ATTACHMENT C: Buckley CIIL

NOMENCLATURE

ACRONYMS AND ABBREVIATIONS

A/E/C Architecture, Engineering and

Construction CPM Critical Path Method

AASHTO

American Association of State

Highway and Transportation Officials

CSS

Contractor’s Site

Superintendent

ACI American Concrete Institute CTR Contractor

AF Air Force CWA Clean Water Act

AF66 Air Force Submittal Requirements DP Design Professional

AFI Air Force Instruction EMCS Energy Management and

Control System

AFMAN Air Force Manual EPA Environmental Protection

Agency

ASTM

American Society for Testing and

Materials ETL Engineering Technical letter

ANSI American National Standards Institute FAR Federal Acquisition

Regulation

AT/FP Anti-Terrorism Force Protection FEDCON

Limited Dissemination

Control to Federal

Employees or Contractors

Only

AVB Active Vehicle Barrier FHWA Federal Highway

Administration

BSFB Buckley Space Force Base FOD Foreign Object Debris

BCE Base Civil Engineer Ft. Feet iii

CUI

CUI

BMPs Stormwater Control Materials GFCI Gov’t Furnished CTR

Installed

CADD

Computer Assisted Drawing and

Design GPM Gallons per Minute

CDOT Colorado Dept of Transportation EPA Environmental Protection

Agency

CD-ROM Compact Disk –Read Only Memory ETL Engineering Technical letter

CDs Construction Documents FAR Federal Acquisition

Regulation

CEPM Civil Engineering Project Manager GFCI Gov’t Furnished CTR

Installed

CES Civil Engineering Squadron HAZMAT Hazardous Materials

CFE Contractor Furnished Equipment OSP Originally Specified

Product

CL6 ABC Class 6 Aggregate Base Course PDF Portable Document Format

CMI CES Construction Manager Inspector PE Professional Engineer

CO Contracting Officer Ph. Phase (electrical)

COMM Communications PM Project Manager

COR Contracting Officer Representative Psi Pounds per square inch

HMW Hazardous Material or Waste QCP Quality Control Plan

HPU Hydraulic Power Unit QRP Qualified Recycling

Program

HTW Hazardous and Toxic Waste RFP Request for Proposal

IAW In Accord With RPUID Real Property Unique

Identifier

IBC International Building Code SOW Statement of Work

IDIQ Indefinite Date Indefinite Quantity TI Technical Instruction

IFC Issued For Construction TL Technical Letter

IFS Installation Facilities Standards TM Technical Manual

IRSO Installation Radiation Safety Officer UDFCD Urban Drainage and Flood

Control District

ISWM Integrated Solid Waste Management UFC United Facilities Criteria UFGS Unified Facilities Guide

Specifications

MHT Method of Handling Traffic UPS Uninterrupted Power

Supply

MS4 Municipal Separate Storm Sewer

System

V Volts

MUTCD Manual on Uniform Traffic Control

Devices

W Watts

NEC National Electric Code

NFPA National Fire Protection Association

NTP Notice to Proceed iv

CUI

CUI

O&M Operations and Maintenance

OPSEC Operational Security

OSHA Occupational Safety and Health

Administration v

BASIC TERMS

All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to: “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive ( e.g. “remove debris from BAFB" includes “safe and legal removal, disposal and obtaining all necessary permits, etc.”)

A device, equipment or system referred to in the singular (e.g. "the pump", or "the_ system'') includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.

The Term Shall Mean (*=Shall in Addition Mean)

Approved *without waiving or suspending the full force of Contractor obligation to fulfill the CDs

Aspect Distinct feature or element of the project

BSFB Government contracting Authority on Buckley SFB

Construction

Documents

Drawings, specifications, and their references including all Design Criteria and Design & Construction Requirements for this Project

Contractor The Design-Build entity holding a current Government contract including all personnel direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.

Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and

Landscape Architects licensed to practice in one or more states of the U.S.

Day Calendar day unless noted otherwise.

DP Licensed Design Professional fully responsible for all professional design on this project

For example (e.g.) One among many possible examples

Government Buckley Space Force Base Contracting Officer

Including [Includes] Including. but not limited to [Includes, but is not limited to]

Provide [Provision] Furnish [Furnishing] and install [installation ] complete, functional, and ready for use without added government action

Subgrade Specified or existing soil lying beneath the pavement structure

Will, must, shall & similar Terms are mandatory directives whereby ‘Term’= ‘Term + to BSFB satisfaction’

Work The whole or any part, product, system or subsystem of this project

Replace Demolish and dispose of existing element Provide new element of equal or greater value.

Review Review and, if and when acceptable to the government, approval

Subcontractor Subcontractor and all personnel in Subcontractor's direct or indirect employ on any given Project including suppliers and manufacturers

FEDCON 1 WT# 16936163

CUI

CUI

BACKGROUND

The Contractor shall provide all labor, materials, equipment, transportation, and supervision necessary to perform striping, restriping and signage of the crosswalks and speed humps shown in the attached exhibits.

SCOPE

Striping.

The Contractor shall provide new striping for all crosswalk locations that do not currently have striping per the figures in the included Attachment A in compliance with the requirements of the Manual on Uniform Traffic Control Devices (MUTCD).

Existing crosswalks that are excessively worn or partially effaced will be stripped and restriped. The contractor shall place crosswalk markings and stop bars in accordance with (IAW) the MUTCD.

The Contractor shall provide new pavement marking layouts, for all required areas, for approval prior to starting striping operations.

Signage.

The Contractor shall install crosswalk signage IAW the MUTCD at all new crosswalk locations as well as existing crosswalks that do not have the appropriate signage. If satisfactory signage exists at a location, the contractor does not need to provide or install signage for that location.

Field Verification.

The Contractor shall field verify all Government provided measurements at the area(s) of work to provide a firm fixed price proposal.

Closeout.

The Contractor shall provide all closeout documentation per CDOT SECTION 625–

Survey Records.

Locations

Figure 2 - Aspen Street at Mississippi Gate Entrance (RPUID# 398268).

Items of work: install crosswalk signage and striping across Aspen Street.

Figure 3 - Aspen Street at B1032 (LDC) and Camp Hale Way Crosswalk (RPUID #

398268).

Items of work: install crosswalk striping and signage across Aspen Street and restripe

Camp Hale Way crosswalk.

FEDCON 2 WT# 16936163

CUI

CUI

Figure 4 – B1022 (Outdoor Rec) Crosswalk (RPUID # 398268).

Items of work: restripe driveway crosswalk.

Figure 5 – B806 (Fire Station) Crosswalk (RPUID# 398268)

Items of work: install crosswalk signage and striping across Aspen Street.

Figure 6 – B600/602 Crosswalk (RPUID# 398268)

Items of work: install crosswalk striping across driveway.

Figure 7 – B700/701 Crosswalk (RPUID# 398505)

Items of work: install crosswalk striping across driveway.

Figure 8 – B706 Crosswalks (RPUID# 398505)

Items of work: install crosswalk striping across driveways – 2 locations.

Figure 9 – B498 Crosswalk (RPUID# 398268)

Items of work: install crosswalk striping across driveway.

Figure 10 – E Steamboat Crosswalk (ADF-C N) (RPUID# 1169785)

Items of work: restripe crosswalk and stop bars across E. Steamboat Avenue.

Figure 11 – B205 Crosswalk (RPUID# 1169794)

Items of work: install crosswalk striping across driveway.

Figure 12 – Speed Humps at Mississippi Gate (RPUID# 398268)

Items of work: remove old striping and restripe speed humps and approach markings.

FEDCON 3 WT# 16936163

CUI

CUI

GENERAL

Specifications.

All work will be accomplished in accordance with the Unified Facilities Guide

Specifications (UFGS), provided project specific specifications (CDOT-2019), provided plans, manufacture’s written instructions, and the Buckley Installation

Facility Standards (IFS).

Operational Security.

The Contractor shall practice OP - SEC per AFI 10-701 chapter 8, paragraph 8.1:

The Contractor (including subcontractors) shall adhere and be familiar with the organization’s Critical Information and Indicator List (CIIL) and ensure indicators & vulnerabilities are protected from disclosure. See Attachment C for CIIL.

The Contractor (including subcontractors) will return all building plans, diagrams, blueprints, maps, and other infrastructure information provided in performance of this

SOW to the Civil Engineer at the end of contract termination or as directed by the

Contracting Office (460 CONS).

Sanitary Facilities.

The Contractor shall provide latrines. Government latrines will not be available for

Contractor use.

Latrines shall be staked down to prevent spillage.

Radioactive Materials.

The Contractor shall ensure that any radioactive material or instrument/device containing radioactive material brought onto BSFB is done so with written permission from the BSFB radiation safety officer (IRSO). Contact the IRSO at 720-847-6274 or by email at john.a.kurth2.civ@mail.mil prior to bringing radioactive material containing devices onto BSFB. The IRSO will require a copy of the radioactive material license and a copy of NRC Form 241 or equivalent. The IRSO will issue a

BSFB permit that must always accompany the device on BSFB. No radioactive material can be disposed of, abandoned, or left on BSFB for any reason. All users of radioactive material containing devices must comply with AFI 40-201, Managing

Radioactive Materials in the US Air Force and AFI40-201_460SWSUP[1], Managing

Radioactive Materials in the US Air Force.

OSHA Compliance.

The Contractor shall provide an OSHA approved method to safely allow work crews and inspectors safe access to and from the work site and all necessary safety equipment while work occurs on the work site.

mailto:john.a.kurth2.civ@mail.mil

FEDCON 4 WT# 16936163

CUI

CUI

Scheduling.

The Contractor shall attend a Project Kickoff meeting to review project plans, specifications, scheduling and other requirements. The contractor shall submit, for review and discussion, the Construction Schedule (AF3064) and the CPM schedule at the Kickoff meeting.

The Contractor shall provide a critical path method schedule that clearly details major milestones and mandatory inspection points. Updates shall be provided if any of these dates are modified.

The Contractor shall provide a phasing plan for work in parking lots with special use considerations.

The Contractor shall complete all phases of the project within 180 calendar days of the

Notice to Proceed.

Advance Notification.

The Contractor shall notify the government, in writing, (via email) 48 hours in advance of any mandatory inspection point, as identified by the Government in the

AF66.

Site Stormwater Sediment Controls.

The Contractor shall provide best management practices for site sediment erosion control, including inlet protection.

The Contractor shall restrict pedestrian and vehicular traffic within the site limits.

All vegetation disturbances shall be revegetated in accordance with the BSFB Facility

Excellence Plan.

The Contractor shall remove any tracking on roads as soon as it occurs.

The Contractor shall provide methods of handling traffic (MHT) that conform to the

Manual on Uniform Traffic Control Devices (MUTCD) most current addition. The

MHT shall be done by a state of Colorado Certified Traffic Control Supervisor. A copy of the certification will be submitted with all traffic control submittals prior to any traffic modification for construction taking place. The Contractor shall submit the

MHT document a minimum of 21 (twenty-one) calendar days prior to work taking place.

Advance Hazardous Material Reporting

All hazardous materials to be used must be reported prior to use. Quantities used need to be reported ideally when received or at least monthly. AFMAN32-7002 Section 3.3 requires that all hazardous materials (HM) must be submitted for review and

FEDCON 5 WT# 16936163

CUI

CUI

authorization prior to bringing on Buckley SFB. All HM usage is required to be tracked once approved for use and reported to the Environmental Flight each month.

Safety Data Sheets (SDS) must be manufacturer-specific for the HM. Manufacturer part numbers and container sizes are required to enable correct volume for tracking usage. If any HM is needed to complete this work, contact 460 CES/CEIE at 720-847-

9268 for further information to assist with requests for authorization. Types of HM are adhesives, paints, sealants, solvents, and similar products.

Demolished Materials

IAW UFGS 02 41 00 DEMOLITION AND DECONSTRUCTION, demolished materials shall be removed, reused, recycled, or disposed from the project site in an appropriate and legal manner.

Construction & Demolition (C&D) Materials to be recycled/reused include asphalt, bricks, concrete and other masonry materials.

Soil-Disturbing Activities

Excavation and site investigations must comply with the Buckley AF 103 dig permit requirements. Please contact Customer Service at 720 847-9913 for more information and realize AF 103 can take up to 30 days to process so the Contractor must ensure this document is started in a timely manner.

Unknown Material

If any unknown material is encountered, the Contractor must:

Immediately stop soils disturbing activities and control access to the site. Note: do not disturb or move the debris or unknown materials or potentially contaminated equipment.

Immediately report the event to the PM, CO and the 460CES/CEIE Toxics Program

Manager, Martin Burris (MartinBuris@spaceforce.mil, 720.847.5723).

As soon as possible (within 12 hours) and no later than the end of the current work shift, the site and associated soils shall be stabilized by securely placing poly sheeting or geotextile over the soil and installing access controls (barricades or fencing) around the site.

The excavation Contractor must be prepared to complete the above actions within the periods indicated.

The debris or material must be evaluated by a Certified Asbestos Building Inspector

(CABI) with Regulated Asbestos Contaminated Soil (RACS) management experience.

Site Stormwater Management

FEDCON 6 WT# 16936163

CUI

CUI

If the total size of the construction disturbance is greater than one (1) acre, then a

Stormwater Pollution Prevention Plan (SWPPP) and construction general permit

(CGP) is required. A SWPPP must be developed, submitted, reviewed, and deemed substantially complete before the CGP Notice of Intent (NOI) can be applied for.

Please consult Buckley SFB’s stormwater coordinator with any questions at matthew.cohen.3.ctr@us.af.mil

The Contractor shall provide a stormwater BMP site plan where staging and equipment storage areas shall be located. Equipment, staging and storage shall be limited to stabilized and/or paved surfaces to eliminate unnecessary disturbances of vegetated areas.

The Contractor shall provide site management details for BMPs to control erosion and sediment during construction and post-construction phases. Various phases shall be utilized if needed, and as required by C04.1. Stormwater Requirements of the Buckley

IFS. Refer to the City of Aurora Drainage Criteria Manual, or MHFD volumes for examples of applicable stormwater BMPs. BMPs shall be installed before any site work commences, and removed only after the site has been seeded, and stabilized in accordance with the Buckley IFS.

PROJECT REQUIREMENTS

CDOT SECTION 105– CONSTRUCTION SURVEYING

The Contractor shall perform all land surveying by a Professional Land Surveyor

(PLS) and layout necessary to ensure adequate placement of parking lot striping and markings.

The Contractor shall submit to the Government a pdf and DWG format of the land survey and the striping layout.

CDOT SECTION 625– SURVEY RECORDS

As-built Record.

The Contractor shall furnish to the Government an as-built record of the parking lot striping and signage including the existing and installed items, in PDF and DWG format, signed by the Contractor’s PLS as part of the closeout documents.

CDOT SECTION 630– CONSTRUCTION ZONE TRAFFIC CONTROL

The Contractor shall submit a traffic control plan 30 days prior to construction for approval. The traffic control plan will be in accordance with the manual on Uniform

Traffic Control Devices (MUTCD), Part 6: Temporary Traffic Control.

CDOT SECTION 708– PAINTS

FEDCON 7 WT# 16936163

CUI

CUI

The Contractor shall submit pavement marking paint product data and Safety Data

Sheets, per the AF66, for government approval before proceeding with work.

The Contractor shall prepare a traffic marking plan for review prior to installation of the traffic control materials. The plan shall include the layout of parking spaces, new accessible parking spaces, new accessible parking signage, and crosswalk markings.

Layout of the accessible parking spaces shall be per the Architectural Barriers Act, section 502.

Pavement Marking Materials. All pavement marking materials shall be selected from

CDOT’s Approved Products List (APL).

The Contractor shall install new low-temperature acrylic waterborne paint to replace the existing parking space striping. See CDOT Table 708-1 for more guidance.

CDOT SECTION 713– TRAFFIC CONTROL MATERIALS

The Contractor shall install new epoxy paint for handicap markings, conforming to

CDOT section 713.17: Modified Epoxy Pavement Marking Material.

APPLICABLE CODES, PERMITS AND SPECIFICATIONS:

The Contractor shall comply with the following codes, permits, and specifications:

Americans with Disabilities Act 2010

CDOT Standard Plans – M&S Standards (Current Edition).

Colorado Department of Transportation (CDOT) Standards Specifications for Road and Bridge

Constructions. (Current Edition) 2019 AS OF 14 FEB 2020.

Air Force Manual No. 32-1040 MAINTENANCE AND REPAIR OF SURFACE AREAS

MUTCD (Manual on Uniform Traffic Control Devices) Part 1, 5&6 (Current Edition).

AFI40-201, Managing Radioactive Materials in the US Air Force.

AFI40-201_460SWSUP[1], Managing Radioactive Materials in the US Air Force:

https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-

201_buckleyafbsup/afi40-201_buckleyafbsup.pdf

BSFB Critical Infrastructure and Indicators List

BSFB MS 4 Permit

UFC AND UFGS STANDARDS (INCLUDED, BUT NOT LIMITED TO)

https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-201_buckleyafbsup/afi40-201_buckleyafbsup.pdf https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-201_buckleyafbsup/afi40-201_buckleyafbsup.pdf

FEDCON 8 WT# 16936163

CUI

CUI

DIVISION 01 - GENERAL REQUIREMENTS

UFGS 01 32 01.00 10 PROJECT SCHEDULE (February 2015)

UFGS 01 33 00 SUBMITTAL PROCEDURES (August 2018)

UFGS 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD) (May 2016)

UFGS 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS (November 2015) Change 6 -

02/18

UFGS 01 45 00.00 20 QUALITY CONTROL (November 2011) Change 2 - 08/17

UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (May

2018)

UFGS 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS (November 2015) Change 1

- 08/16

UFGS 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT (January

2007) Change 3 - 08/18

UFGS 01 78 00 CLOSEOUT SUBMITTALS (August 2011) Change 3 - 11/17

UFGS 01 78 23 OPERATION AND MAINTENANCE DATA (August 2015)

UFGS 01-78-23 O&M Manual

UFGS 01-200-01 DOD Building Code

WINTER EXCLUSION

Winter exclusion may be allowed by the Contracting Officer upon request.

FEDCON 9 WT# 16936163

CUI

Points of Contact

460 CES/CEOER – Project Manager 460 CONF/PKA – Contracting Officer

Eric Riley TBD

660 S Aspen St., Mail Stop 86 510 S Aspen St.

Buckley SFB, CO 80011 Buckley SFB, 80011

COM 720- 847-6973 TBD

460 CES/CEOER – Project Engineer/Inspector 460 CONF/PKA – Contract Administrator

Bernard Beckner TBD

660 S Aspen St., Mail Stop 86 510 S Aspen St.

Buckley SFB, CO 80011 Buckley SFB, 80011

COM 720- 847-5884 TBD

END OF DOCUMENT BODY

FEDCON 10 WT# 16936163

CUI

ATTACHMENT A: CROSSWALK MAPS

Figure 1. Overall Project Site Map

Fig. 10

Fig. 11

Fig. 12

FEDCON 11 WT# 16936163

Figure 2. Mississippi Gate Entrance Crosswalk – Signage Required

Figure 3. LDC Crosswalk – Signage Required

FEDCON 12 WT# 16936163

Figure 4. B1022 (Outdoor Rec) Crosswalk

Figure 5. B806 (Fire Station) Crosswalk – Signage Required

FEDCON 13 WT# 16936163

Figure 6. B600/602 Crosswalk

Figure 7. B700/701 Crosswalk

FEDCON 14 WT# 16936163

Figure 8. B706 Crosswalks

Figure 9. B498 Crosswalk

FEDCON 15 WT# 16936163

Figure 10. ADF-C North Crosswalk

Figure 11. B205 Crosswalk

FEDCON 16 WT# 16936163

Figure 12. Speed Humps at Mississippi Gate Entrance

File details come from the government source that posted it. Updated .