Statement of Work - Restripe Speed Humps Crosswalks - 16 SEPT 2025.pdf
PDF 1 MB Posted
- Solicitation number
- FA254325Q0050
About this file
This Statement of Work (SOW) details a project for restriping speed humps and crosswalks across multiple locations at Buckley Space Force Base (BSFB) in Colorado. The contractor will be responsible for providing new striping and signage for 12 different crosswalk locations, including installing crosswalk markings, stop bars, and appropriate signage in accordance with the Manual on Uniform Traffic Control Devices (MUTCD). The work includes both new striping for locations without current markings and restriping for excessively worn crosswalks.
Key project requirements include using low-temperature acrylic waterborne paint for parking space striping, epoxy paint for handicap markings, and adhering to various federal and state standards including the Americans with Disabilities Act, CDOT specifications, and Air Force manuals. The project has a 180-calendar day completion timeline from the Notice to Proceed, with specific requirements for traffic control, stormwater management, hazardous material reporting, and operational security. The project will be managed by Eric Riley from 460 CES/CEOER, with the specific work locations mapped and detailed in the document's attachment, covering areas such as Mississippi Gate Entrance, B1022 Outdoor Recreation, Fire Station, and various other base locations.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CUI
STATEMENT OF WORK (SOW)
Project Number: WT# 16936163
Restripe Speed Humps & Crosswalks – Base-wide
16 SEPT 2025
Project Location: Buckley Space Force Base (BSFB), CO
Contract:
Dissemination Control:
Federal Employees or Contractors Only
FEDCON WT# 16936163
i
CUI
Table of Contents
NOMENCLATURE ............................................................................................................... ii
ACRONYMS AND ABBREVIATIONS ........................................................................ ii
BASIC TERMS ................................................................................................................ v
BACKGROUND
SCOPE
New Striping
Field Verification
Closeout
Locations
GENERAL
Specifications
Operational Security
Sanitary Facilities
Radioactive Materials
OSHA Compliance
Scheduling
Advance Notification
Site Stormwater Sediment Controls
Advance Hazardous Material Reporting
Demolished Materials
Soil-Disturbing Activities
Unknown Material
Site Stormwater Management
PROJECT REQUIREMENTS
CDOT SECTION 105– CONSTRUCTION SURVEYING
CDOT SECTION 614– TRAFFIC CONTROL DEVICES
CDOT SECTION 625– SURVEY RECORDS
CDOT SECTION 630– CONSTRUCTION ZONE TRAFFIC CONTROL
ii
CUI
CUI
CDOT SECTION 708– PAINTS
CDOT SECTION 713– TRAFFIC CONTROL MATERIALS
APPLICABLE CODES, PERMITS AND SPECIFICATIONS:
ASTM’s (INCLUDED, BUT NOT LIMITED TO) ........ Error! Bookmark not defined.
UFC AND UFGS STANDARDS (INCLUDED, BUT NOT LIMITED TO)
WINTER EXCLUSION
Points of Contact
ATTACHMENT A: Parking Lot Maps
ATTACHMENT B: ADA PARKING SPACE REQUIREMENTS
ATTACHMENT C: Buckley CIIL
NOMENCLATURE
ACRONYMS AND ABBREVIATIONS
A/E/C Architecture, Engineering and
Construction CPM Critical Path Method
AASHTO
American Association of State
Highway and Transportation Officials
CSS
Contractor’s Site
Superintendent
ACI American Concrete Institute CTR Contractor
AF Air Force CWA Clean Water Act
AF66 Air Force Submittal Requirements DP Design Professional
AFI Air Force Instruction EMCS Energy Management and
Control System
AFMAN Air Force Manual EPA Environmental Protection
Agency
ASTM
American Society for Testing and
Materials ETL Engineering Technical letter
ANSI American National Standards Institute FAR Federal Acquisition
Regulation
AT/FP Anti-Terrorism Force Protection FEDCON
Limited Dissemination
Control to Federal
Employees or Contractors
Only
AVB Active Vehicle Barrier FHWA Federal Highway
Administration
BSFB Buckley Space Force Base FOD Foreign Object Debris
BCE Base Civil Engineer Ft. Feet iii
CUI
CUI
BMPs Stormwater Control Materials GFCI Gov’t Furnished CTR
Installed
CADD
Computer Assisted Drawing and
Design GPM Gallons per Minute
CDOT Colorado Dept of Transportation EPA Environmental Protection
Agency
CD-ROM Compact Disk –Read Only Memory ETL Engineering Technical letter
CDs Construction Documents FAR Federal Acquisition
Regulation
CEPM Civil Engineering Project Manager GFCI Gov’t Furnished CTR
Installed
CES Civil Engineering Squadron HAZMAT Hazardous Materials
CFE Contractor Furnished Equipment OSP Originally Specified
Product
CL6 ABC Class 6 Aggregate Base Course PDF Portable Document Format
CMI CES Construction Manager Inspector PE Professional Engineer
CO Contracting Officer Ph. Phase (electrical)
COMM Communications PM Project Manager
COR Contracting Officer Representative Psi Pounds per square inch
HMW Hazardous Material or Waste QCP Quality Control Plan
HPU Hydraulic Power Unit QRP Qualified Recycling
Program
HTW Hazardous and Toxic Waste RFP Request for Proposal
IAW In Accord With RPUID Real Property Unique
Identifier
IBC International Building Code SOW Statement of Work
IDIQ Indefinite Date Indefinite Quantity TI Technical Instruction
IFC Issued For Construction TL Technical Letter
IFS Installation Facilities Standards TM Technical Manual
IRSO Installation Radiation Safety Officer UDFCD Urban Drainage and Flood
Control District
ISWM Integrated Solid Waste Management UFC United Facilities Criteria UFGS Unified Facilities Guide
Specifications
MHT Method of Handling Traffic UPS Uninterrupted Power
Supply
MS4 Municipal Separate Storm Sewer
System
V Volts
MUTCD Manual on Uniform Traffic Control
Devices
W Watts
NEC National Electric Code
NFPA National Fire Protection Association
NTP Notice to Proceed iv
CUI
CUI
O&M Operations and Maintenance
OPSEC Operational Security
OSHA Occupational Safety and Health
Administration v
BASIC TERMS
All directives, informative, etc. statements are directed to the Contractor even if the term “contractor” or the contractor name is not included (e.g. “Provide a nail” is equivalent to “The contractor shall provide a nail.” And “remove” is equivalent to: “The Contractor shall remove”). Also, the Contractor shall ably and competently execute all directives including all directly or indirectly related tasks required to safely and legally perform the directive ( e.g. “remove debris from BAFB" includes “safe and legal removal, disposal and obtaining all necessary permits, etc.”)
A device, equipment or system referred to in the singular (e.g. "the pump", or "the_ system'') includes all related devices, elements and components required to Provide (see below in this table) that device, equipment, or system.
The Term Shall Mean (*=Shall in Addition Mean)
Approved *without waiving or suspending the full force of Contractor obligation to fulfill the CDs
Aspect Distinct feature or element of the project
BSFB Government contracting Authority on Buckley SFB
Construction
Documents
Drawings, specifications, and their references including all Design Criteria and Design & Construction Requirements for this Project
Contractor The Design-Build entity holding a current Government contract including all personnel direct or indirect employ of same entity servicing same contract including partners, consultants, subcontractors, suppliers, and manufacturers.
Design Professional (Abbreviated: DP) Professionals including Architects, Engineers and
Landscape Architects licensed to practice in one or more states of the U.S.
Day Calendar day unless noted otherwise.
DP Licensed Design Professional fully responsible for all professional design on this project
For example (e.g.) One among many possible examples
Government Buckley Space Force Base Contracting Officer
Including [Includes] Including. but not limited to [Includes, but is not limited to]
Provide [Provision] Furnish [Furnishing] and install [installation ] complete, functional, and ready for use without added government action
Subgrade Specified or existing soil lying beneath the pavement structure
Will, must, shall & similar Terms are mandatory directives whereby ‘Term’= ‘Term + to BSFB satisfaction’
Work The whole or any part, product, system or subsystem of this project
Replace Demolish and dispose of existing element Provide new element of equal or greater value.
Review Review and, if and when acceptable to the government, approval
Subcontractor Subcontractor and all personnel in Subcontractor's direct or indirect employ on any given Project including suppliers and manufacturers
FEDCON 1 WT# 16936163
CUI
CUI
BACKGROUND
The Contractor shall provide all labor, materials, equipment, transportation, and supervision necessary to perform striping, restriping and signage of the crosswalks and speed humps shown in the attached exhibits.
SCOPE
Striping.
The Contractor shall provide new striping for all crosswalk locations that do not currently have striping per the figures in the included Attachment A in compliance with the requirements of the Manual on Uniform Traffic Control Devices (MUTCD).
Existing crosswalks that are excessively worn or partially effaced will be stripped and restriped. The contractor shall place crosswalk markings and stop bars in accordance with (IAW) the MUTCD.
The Contractor shall provide new pavement marking layouts, for all required areas, for approval prior to starting striping operations.
Signage.
The Contractor shall install crosswalk signage IAW the MUTCD at all new crosswalk locations as well as existing crosswalks that do not have the appropriate signage. If satisfactory signage exists at a location, the contractor does not need to provide or install signage for that location.
Field Verification.
The Contractor shall field verify all Government provided measurements at the area(s) of work to provide a firm fixed price proposal.
Closeout.
The Contractor shall provide all closeout documentation per CDOT SECTION 625–
Survey Records.
Locations
Figure 2 - Aspen Street at Mississippi Gate Entrance (RPUID# 398268).
Items of work: install crosswalk signage and striping across Aspen Street.
Figure 3 - Aspen Street at B1032 (LDC) and Camp Hale Way Crosswalk (RPUID #
398268).
Items of work: install crosswalk striping and signage across Aspen Street and restripe
Camp Hale Way crosswalk.
FEDCON 2 WT# 16936163
CUI
CUI
Figure 4 – B1022 (Outdoor Rec) Crosswalk (RPUID # 398268).
Items of work: restripe driveway crosswalk.
Figure 5 – B806 (Fire Station) Crosswalk (RPUID# 398268)
Items of work: install crosswalk signage and striping across Aspen Street.
Figure 6 – B600/602 Crosswalk (RPUID# 398268)
Items of work: install crosswalk striping across driveway.
Figure 7 – B700/701 Crosswalk (RPUID# 398505)
Items of work: install crosswalk striping across driveway.
Figure 8 – B706 Crosswalks (RPUID# 398505)
Items of work: install crosswalk striping across driveways – 2 locations.
Figure 9 – B498 Crosswalk (RPUID# 398268)
Items of work: install crosswalk striping across driveway.
Figure 10 – E Steamboat Crosswalk (ADF-C N) (RPUID# 1169785)
Items of work: restripe crosswalk and stop bars across E. Steamboat Avenue.
Figure 11 – B205 Crosswalk (RPUID# 1169794)
Items of work: install crosswalk striping across driveway.
Figure 12 – Speed Humps at Mississippi Gate (RPUID# 398268)
Items of work: remove old striping and restripe speed humps and approach markings.
FEDCON 3 WT# 16936163
CUI
CUI
GENERAL
Specifications.
All work will be accomplished in accordance with the Unified Facilities Guide
Specifications (UFGS), provided project specific specifications (CDOT-2019), provided plans, manufacture’s written instructions, and the Buckley Installation
Facility Standards (IFS).
Operational Security.
The Contractor shall practice OP - SEC per AFI 10-701 chapter 8, paragraph 8.1:
The Contractor (including subcontractors) shall adhere and be familiar with the organization’s Critical Information and Indicator List (CIIL) and ensure indicators & vulnerabilities are protected from disclosure. See Attachment C for CIIL.
The Contractor (including subcontractors) will return all building plans, diagrams, blueprints, maps, and other infrastructure information provided in performance of this
SOW to the Civil Engineer at the end of contract termination or as directed by the
Contracting Office (460 CONS).
Sanitary Facilities.
The Contractor shall provide latrines. Government latrines will not be available for
Contractor use.
Latrines shall be staked down to prevent spillage.
Radioactive Materials.
The Contractor shall ensure that any radioactive material or instrument/device containing radioactive material brought onto BSFB is done so with written permission from the BSFB radiation safety officer (IRSO). Contact the IRSO at 720-847-6274 or by email at john.a.kurth2.civ@mail.mil prior to bringing radioactive material containing devices onto BSFB. The IRSO will require a copy of the radioactive material license and a copy of NRC Form 241 or equivalent. The IRSO will issue a
BSFB permit that must always accompany the device on BSFB. No radioactive material can be disposed of, abandoned, or left on BSFB for any reason. All users of radioactive material containing devices must comply with AFI 40-201, Managing
Radioactive Materials in the US Air Force and AFI40-201_460SWSUP[1], Managing
Radioactive Materials in the US Air Force.
OSHA Compliance.
The Contractor shall provide an OSHA approved method to safely allow work crews and inspectors safe access to and from the work site and all necessary safety equipment while work occurs on the work site.
mailto:john.a.kurth2.civ@mail.mil
FEDCON 4 WT# 16936163
CUI
CUI
Scheduling.
The Contractor shall attend a Project Kickoff meeting to review project plans, specifications, scheduling and other requirements. The contractor shall submit, for review and discussion, the Construction Schedule (AF3064) and the CPM schedule at the Kickoff meeting.
The Contractor shall provide a critical path method schedule that clearly details major milestones and mandatory inspection points. Updates shall be provided if any of these dates are modified.
The Contractor shall provide a phasing plan for work in parking lots with special use considerations.
The Contractor shall complete all phases of the project within 180 calendar days of the
Notice to Proceed.
Advance Notification.
The Contractor shall notify the government, in writing, (via email) 48 hours in advance of any mandatory inspection point, as identified by the Government in the
AF66.
Site Stormwater Sediment Controls.
The Contractor shall provide best management practices for site sediment erosion control, including inlet protection.
The Contractor shall restrict pedestrian and vehicular traffic within the site limits.
All vegetation disturbances shall be revegetated in accordance with the BSFB Facility
Excellence Plan.
The Contractor shall remove any tracking on roads as soon as it occurs.
The Contractor shall provide methods of handling traffic (MHT) that conform to the
Manual on Uniform Traffic Control Devices (MUTCD) most current addition. The
MHT shall be done by a state of Colorado Certified Traffic Control Supervisor. A copy of the certification will be submitted with all traffic control submittals prior to any traffic modification for construction taking place. The Contractor shall submit the
MHT document a minimum of 21 (twenty-one) calendar days prior to work taking place.
Advance Hazardous Material Reporting
All hazardous materials to be used must be reported prior to use. Quantities used need to be reported ideally when received or at least monthly. AFMAN32-7002 Section 3.3 requires that all hazardous materials (HM) must be submitted for review and
FEDCON 5 WT# 16936163
CUI
CUI
authorization prior to bringing on Buckley SFB. All HM usage is required to be tracked once approved for use and reported to the Environmental Flight each month.
Safety Data Sheets (SDS) must be manufacturer-specific for the HM. Manufacturer part numbers and container sizes are required to enable correct volume for tracking usage. If any HM is needed to complete this work, contact 460 CES/CEIE at 720-847-
9268 for further information to assist with requests for authorization. Types of HM are adhesives, paints, sealants, solvents, and similar products.
Demolished Materials
IAW UFGS 02 41 00 DEMOLITION AND DECONSTRUCTION, demolished materials shall be removed, reused, recycled, or disposed from the project site in an appropriate and legal manner.
Construction & Demolition (C&D) Materials to be recycled/reused include asphalt, bricks, concrete and other masonry materials.
Soil-Disturbing Activities
Excavation and site investigations must comply with the Buckley AF 103 dig permit requirements. Please contact Customer Service at 720 847-9913 for more information and realize AF 103 can take up to 30 days to process so the Contractor must ensure this document is started in a timely manner.
Unknown Material
If any unknown material is encountered, the Contractor must:
Immediately stop soils disturbing activities and control access to the site. Note: do not disturb or move the debris or unknown materials or potentially contaminated equipment.
Immediately report the event to the PM, CO and the 460CES/CEIE Toxics Program
Manager, Martin Burris (MartinBuris@spaceforce.mil, 720.847.5723).
As soon as possible (within 12 hours) and no later than the end of the current work shift, the site and associated soils shall be stabilized by securely placing poly sheeting or geotextile over the soil and installing access controls (barricades or fencing) around the site.
The excavation Contractor must be prepared to complete the above actions within the periods indicated.
The debris or material must be evaluated by a Certified Asbestos Building Inspector
(CABI) with Regulated Asbestos Contaminated Soil (RACS) management experience.
Site Stormwater Management
FEDCON 6 WT# 16936163
CUI
CUI
If the total size of the construction disturbance is greater than one (1) acre, then a
Stormwater Pollution Prevention Plan (SWPPP) and construction general permit
(CGP) is required. A SWPPP must be developed, submitted, reviewed, and deemed substantially complete before the CGP Notice of Intent (NOI) can be applied for.
Please consult Buckley SFB’s stormwater coordinator with any questions at matthew.cohen.3.ctr@us.af.mil
The Contractor shall provide a stormwater BMP site plan where staging and equipment storage areas shall be located. Equipment, staging and storage shall be limited to stabilized and/or paved surfaces to eliminate unnecessary disturbances of vegetated areas.
The Contractor shall provide site management details for BMPs to control erosion and sediment during construction and post-construction phases. Various phases shall be utilized if needed, and as required by C04.1. Stormwater Requirements of the Buckley
IFS. Refer to the City of Aurora Drainage Criteria Manual, or MHFD volumes for examples of applicable stormwater BMPs. BMPs shall be installed before any site work commences, and removed only after the site has been seeded, and stabilized in accordance with the Buckley IFS.
PROJECT REQUIREMENTS
CDOT SECTION 105– CONSTRUCTION SURVEYING
The Contractor shall perform all land surveying by a Professional Land Surveyor
(PLS) and layout necessary to ensure adequate placement of parking lot striping and markings.
The Contractor shall submit to the Government a pdf and DWG format of the land survey and the striping layout.
CDOT SECTION 625– SURVEY RECORDS
As-built Record.
The Contractor shall furnish to the Government an as-built record of the parking lot striping and signage including the existing and installed items, in PDF and DWG format, signed by the Contractor’s PLS as part of the closeout documents.
CDOT SECTION 630– CONSTRUCTION ZONE TRAFFIC CONTROL
The Contractor shall submit a traffic control plan 30 days prior to construction for approval. The traffic control plan will be in accordance with the manual on Uniform
Traffic Control Devices (MUTCD), Part 6: Temporary Traffic Control.
CDOT SECTION 708– PAINTS
FEDCON 7 WT# 16936163
CUI
CUI
The Contractor shall submit pavement marking paint product data and Safety Data
Sheets, per the AF66, for government approval before proceeding with work.
The Contractor shall prepare a traffic marking plan for review prior to installation of the traffic control materials. The plan shall include the layout of parking spaces, new accessible parking spaces, new accessible parking signage, and crosswalk markings.
Layout of the accessible parking spaces shall be per the Architectural Barriers Act, section 502.
Pavement Marking Materials. All pavement marking materials shall be selected from
CDOT’s Approved Products List (APL).
The Contractor shall install new low-temperature acrylic waterborne paint to replace the existing parking space striping. See CDOT Table 708-1 for more guidance.
CDOT SECTION 713– TRAFFIC CONTROL MATERIALS
The Contractor shall install new epoxy paint for handicap markings, conforming to
CDOT section 713.17: Modified Epoxy Pavement Marking Material.
APPLICABLE CODES, PERMITS AND SPECIFICATIONS:
The Contractor shall comply with the following codes, permits, and specifications:
Americans with Disabilities Act 2010
CDOT Standard Plans – M&S Standards (Current Edition).
Colorado Department of Transportation (CDOT) Standards Specifications for Road and Bridge
Constructions. (Current Edition) 2019 AS OF 14 FEB 2020.
Air Force Manual No. 32-1040 MAINTENANCE AND REPAIR OF SURFACE AREAS
MUTCD (Manual on Uniform Traffic Control Devices) Part 1, 5&6 (Current Edition).
AFI40-201, Managing Radioactive Materials in the US Air Force.
AFI40-201_460SWSUP[1], Managing Radioactive Materials in the US Air Force:
https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-
201_buckleyafbsup/afi40-201_buckleyafbsup.pdf
BSFB Critical Infrastructure and Indicators List
BSFB MS 4 Permit
UFC AND UFGS STANDARDS (INCLUDED, BUT NOT LIMITED TO)
https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-201_buckleyafbsup/afi40-201_buckleyafbsup.pdf https://static.e-publishing.af.mil/production/1/buckleyafb/publication/afi40-201_buckleyafbsup/afi40-201_buckleyafbsup.pdf
FEDCON 8 WT# 16936163
CUI
CUI
DIVISION 01 - GENERAL REQUIREMENTS
UFGS 01 32 01.00 10 PROJECT SCHEDULE (February 2015)
UFGS 01 33 00 SUBMITTAL PROCEDURES (August 2018)
UFGS 01 33 16.00 10 DESIGN DATA (DESIGN AFTER AWARD) (May 2016)
UFGS 01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS (November 2015) Change 6 -
02/18
UFGS 01 45 00.00 20 QUALITY CONTROL (November 2011) Change 2 - 08/17
UFGS 01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS (May
2018)
UFGS 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS (November 2015) Change 1
- 08/16
UFGS 01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT (January
2007) Change 3 - 08/18
UFGS 01 78 00 CLOSEOUT SUBMITTALS (August 2011) Change 3 - 11/17
UFGS 01 78 23 OPERATION AND MAINTENANCE DATA (August 2015)
UFGS 01-78-23 O&M Manual
UFGS 01-200-01 DOD Building Code
WINTER EXCLUSION
Winter exclusion may be allowed by the Contracting Officer upon request.
FEDCON 9 WT# 16936163
CUI
Points of Contact
460 CES/CEOER – Project Manager 460 CONF/PKA – Contracting Officer
Eric Riley TBD
660 S Aspen St., Mail Stop 86 510 S Aspen St.
Buckley SFB, CO 80011 Buckley SFB, 80011
COM 720- 847-6973 TBD
460 CES/CEOER – Project Engineer/Inspector 460 CONF/PKA – Contract Administrator
Bernard Beckner TBD
660 S Aspen St., Mail Stop 86 510 S Aspen St.
Buckley SFB, CO 80011 Buckley SFB, 80011
COM 720- 847-5884 TBD
END OF DOCUMENT BODY
FEDCON 10 WT# 16936163
CUI
ATTACHMENT A: CROSSWALK MAPS
Figure 1. Overall Project Site Map
Fig. 10
Fig. 11
Fig. 12
FEDCON 11 WT# 16936163
Figure 2. Mississippi Gate Entrance Crosswalk – Signage Required
Figure 3. LDC Crosswalk – Signage Required
FEDCON 12 WT# 16936163
Figure 4. B1022 (Outdoor Rec) Crosswalk
Figure 5. B806 (Fire Station) Crosswalk – Signage Required
FEDCON 13 WT# 16936163
Figure 6. B600/602 Crosswalk
Figure 7. B700/701 Crosswalk
FEDCON 14 WT# 16936163
Figure 8. B706 Crosswalks
Figure 9. B498 Crosswalk
FEDCON 15 WT# 16936163
Figure 10. ADF-C North Crosswalk
Figure 11. B205 Crosswalk
FEDCON 16 WT# 16936163
Figure 12. Speed Humps at Mississippi Gate Entrance