AF66 - Restripe Speed Humps Crosswalks - Basewide.xlsx

XLSX spreadsheet 26 KB Posted

Attached to
Buckley SFB Crosswalk & Speed Hump Striping/Signage
Solicitation number
FA254325Q0050
Issued by

About this file

This document is a Schedule of Material Submittals for a contract (FA254325Q0050) for restriping speed humps and crosswalks at Buckley Space Force Base. The project involves commercial construction services to install and restripe crosswalk and speed hump signage, requiring comprehensive documentation and material submissions across multiple stages of the project.

Key submission requirements include a construction schedule, pre-construction photos, quality control plan, traffic control plan, pavement marking and signage plan, material specifications (including asphalt, signage, and crack sealant materials), testing results, and record drawings. Critical submission deadlines range from project kick-off meeting to 15 business days after notice to proceed, with final documentation required prior to the Red Zone Meeting. The project is managed by the Department of the Air Force Space Command, with quotes due by 3:30pm MST on 26 Sept 2025, and potential site visits available on 25 Sept 2025 if requested by 23 Sept 2025.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AF66 2014_MM

SCHEDULE OF MATERIAL SUBMITTALS SUBJECT TO UPDATE BY GOVERNMENTFA254325Q0050 - Restripe Speed Humps & Crosswalks - Basewide9/22/25
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALNUMBER OF SUBITTALSREQUIRED SUBMISSION DATE (No Later Than)DATE RECEIVED IN CONTRACTINGDATE TO CIVIL ENGINEERINGRETURN SUSPENSE DATEAF3000 SUBMITTAL NUMBERDATE CONTRACTOR NOTIFIED APPROVED / DISAPPROVEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
1CONSTRUCTION SCHEDULE (AF3064)1+At Kick Off Meetinginitially, then AS NEEDED PER CO
2CPM SCHEDULE1At Project Kick Off Meeting
3Camera request Letter1At Project Kick Off MeetingInclude model, users, etc.
4Pre-construction Photo's1At Project Kick Off Meeting
5Kick Off Meeting - Minutes13 CD After Kickoff Meeting
6Construction Quality Control Plan1At Project Kick Off MeetingMeans and methods of controlling construction,
7Traffic Control Plan (draft), with flagger certifications1At Project Kick Off MeetingAll Parking Lots
8Final Traffic Control Plan11 month Prior to paving operationsAll Parking Lots
9Phasing Plan11 month Prior to operationsPer individual parking lot
11Pavement Marking and Signage Plan115 BD after NTPAll Parking Lots
12Colorado Radioactive Material License; NRC Form 241; proof of Buckley Space Force Base radioactive material Permit as issued by John Kurth.115 BD after NTP
13Initial Construction Hazardous Materials List: Type, quantity, size of container1+At or before const. Pre Operations Meeting
14DIG PERMIT1 month Prior to operationsMust be updated monthy with customer service
15Pavement Marking Materials, per CDOT APL115 BD after NTPpaint, thermoplastic
16Signage Materials15 BD after NTPsign, post, flex base
20Asphalt Crack Sealant, per CDOT APL15 BD after NTPPer CDOT 702.04
21Joint Adhesive, per CDOT APL15 BD after NTP
22Asphalt Reinforcement Mat, per CDOT APL15 BD after NTP
23Class 6 ABC Specs (compaction curve, etc)15 BD after NTP
ALL MATERIAL SUBMITTALS MUST BE APPROVED PRIOR TO PRE-OP MEETING
24Pre Operations Meeting - Minutes13 BD After Pre-Op MeetingHold Pre-op 1 week before construction activities
25CRACK REPAIR- EXAMINATION BY GOV AND APPROVALAS SCHEDULEDMANDATORY INSPECTION POINT! MUST BE APPROVER PRIOR TO LAYING ASPHALT OR APPLYING FOG SEAL
26Asphalt Testing Results: Nuclear Density3 BD after Testingper separate parking lots
28Soil Compaction Tests ASTM D6985 BD after Compaction Testsubgrade under asphalt and concrete
29Class 6 ABC Compaction Tests3 BD after Compaction Testper separate parking lots
30Final HAZMAT listing1prior to Red Zone Meeting
31Total materials to agg yard1prior to Red Zone Meeting
32Total materials hauled off base1prior to Red Zone Meeting
33Record Drawings1prior to Red Zone MeetingAutoCad and pdf electronic copies
34Red Zone Notes13 BD after meeting
35Final Inspection - Meeting Minutes1At Completion
AF FORM 66, OCT 89