RFI for B430 CT Sump Pump Repair As of 3 September 2021
1. Discharge pipe size?
See Attch 1 LC Pump & Curve document
2. Pump overall length?
See Attch 1 LC Pump & Curve document
3. Type and size of mechanical seal used?
See Attch 1 LC Pump & Curve document
4. What is the duration of the project?
The current PoP is 60 days, we are willing to discuss extending if no one can provide the immediate services we require.