SOW 743rd ARMAG Fiber Connectivity_16August21.docx
DOCX document 34 KB Posted
- Attached to
- 743 ARMAG Fiber Install
- Solicitation number
- FA254321R0015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI for 743 ARMAG Fiber Install 31 Aug 21.docx | DOCX document | |
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity_24August21.docx | DOCX document | |
| RFI for 743 ARMAG Fiber Install 25 Aug 21.docx | DOCX document | |
| 743rd Camp Rattle Snake.pdf | ||
| RFI for 743 ARMAG Fiber Install 17 Aug 21.docx | DOCX document | |
| Solicitation Amendment FA254321R00150001 SF .pdf | ||
| ARMAG Route.docx | DOCX document | |
| UFC 3-550-01 Exterior Elec Power Distribution.pdf | ||
| UFC 3-580-01 Telecommunications Interior Infrastructure.pdf | ||
| RFI for 743 ARMAG Fiber Install 16 Aug 21.docx | DOCX document | |
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity_16August21.docx | DOCX document | |
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity 19July21.docx | DOCX document | |
| ARMAG WD 2015 5419.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
743rd ARMAG Fiber Connectivity Buckley Garrison 16 August 2021
1. Description of Services. This statement of work is to provide single mode fiber optic cable connectivity from building 1617 to building 17110.
2. Scope of Work
The Contractor shall install, terminate and test the fiber from building 1617 to the ARMAG building. An updated drawing will be provided at Friday’s site visit.
2.1. Installation: An Outside Plant Cable (OSP) underground rated 12 strand single-mode (SM) fiber optic cable will be installed from building 1617 to the ARMAG building designated on the attached drawing. The cable will be one continuous length with zero splices unless authorized by a Buckley AT&T NaaS representative. The cable will be installed in existing innerduct as shown on the diagram and where innerduct does not exist, 3-Cell Maxcell will be installed in a duct with existing cabling or two (2) 3-Cell Maxcells will be installed in an empty innerduct. At manhole TEHH 13-1 and every third manhole thereafter and at building 1617, a 50-foot maintenance loop will be left in each manhole.
Maxcell innerduct will be installed as indicated in “Red” on the diagram from TEMH 13-9 to TEMH 18-4, TEMH 18-7 and TEMH 18-8. As stated above, a 3-Cell Maxcell will be installed in a duct with existing cabling or two (2) 3-Cell Maxcell will be installed in an empty innerduct.
A trench will be excavated at a minimum depth of 24 inches from TEHH 13-1 to the ARMAG using 2-inch diameter PVC wall conduit with a metallic trace wire to enable locating after installation.
2.1.1 Installing through Concrete
The parameters outside of what is described in this section 2.1.1 is the responsibility of the contractor.
The 460th Civil Engineering Squadron (CES) electrical shop (government) will provide trench and cutting from the concrete pad to the ARMAG building. 460th CES will be installing 120/204 Volt power lines in parallel with the fiber communications line in the same trench. Both power and fiber shall maintain appropriate required separation.
2.1.2 Within Trench
Within the described trench area the contractor will be responsible for:
1 - Coordinate with 460th CES to trench and cut the concrete pad.
2 - Back filling and compacting the trench.
a - Contractor to use compaction equipment to meet the surrounding compaction levels.
b - Contractor to back fill trench with soil level to the bottom of the concrete pad.
c - Contractor shall finish the trench by pouring concrete level with the existing Pad.
i - Contractor to drill and drive rebar along both sides of the concrete pad.
ii - Contractor to finish and match existing concrete surface finish.
2.2. Termination: The cable will be terminated in the rack at bldg. 1617 designated by the ATT representative in a patch panel properly labeled and in designated location with the ARMAG specified by the customer.
The OSP cable will be tested after termination and must meet standards as specified in attachment 1, Unified Facilities Criteria, planning and design guide. Installation must adhere to the standards specified in the guide and Appendix A References in the guide. Test results showing overall loss will be given to AT&T NaaS representative for review. Acceptance approval must be granted by AT&T Naas.
The following is for reference and footages are approximations only.
| · Total footage of duct run | 3782 | ||
| · Maxcell innerduct to install | 1318 | ||
| · Conduit to install | 170 | ||
| · Trench to excavate | 170 | ||
| · Total footage of fiber to install | 5000 |
2.3. Tools, Equipment and Vehicles
All tools, equipment and vehicles will be provided by the contractor. Access to the base must be coordinated with the 704 MI BDE at a minimum of 72 hours before required access to ensure the personnel meet requirements for base entry.
2.4. Safety
The contractor will meet all OSHA, industry, airfield and AF requirements ensuring safe installation on Buckley Space Force Base (SFB).
2.5. Training: N/A
2.6. Warranty: N/A
2.7. Records: The Contractor will provide the Government an official set of as-built drawings that displays the installed equipment.
2.8. Site Clean Up: The Contractor will be responsible for immediately cleaning up any spills, debris, etc., which may occur during installation. The Contractor will be responsible for keeping installation areas in serviceable and safe order.
2.9. Maintenance and Service: N/A
2.9.1. Personnel: Service personnel shall be qualified to accomplish all work promptly and satisfactorily. The Government POCs listed below shall be advised in writing of the name(s) of the designated service representative(s), and of any changes in personnel.
2.9.2. Emergency Service: N/A
3. Points of Contact:
704 MI BDE, Maj. Marjana Bidwell, 720-847-6829;
704 MI BDE, Capt. Theron Hollar, 301-677-7421;
460 MSG ITF, Mr. Marcus Reed, 720-847-5376;
460 CONS/PKA Flight Chief, TSgt Brittainy Shirley, 720-847-6448;
460 CONS/PKA Contract Specialist, A1C Koby Trotter, 720-847-6524
4. Pass and Identification. N/A
4.1. Base Access. To gain base access for the site visit please provide your full name, driver’s license # and issued state to either koby.trotter@spaceforce.mil or brittainy.shirley@spaceforce.mil by 12 PM Mountain Time on Wednesday 18 August.
5. For Official Use Only: A site visit will be held at 3 PM Mountain Time on Friday 20 Aug.
6. Contractor Registration. Contractor shall be required to invoice through the Wide Area Work Flow (WAWF) System at https://piee.eb.mil/. More information regarding WAWF will be provided upon contract award. The contractor must have current registration though System Award Management (SAM), https://www.sam.gov/.
Attachments:
1. UFC 3-580-01 Telecommunications Interior Infrastructure
2. UFC 3-550-01 Exterior Elec Power Distribution
3. RFI for 743 ARMAG Fiber Install 16 Aug 21