RFI for 743 ARMAG Fiber Install 31 Aug 21.docx
DOCX document 17 KB Posted
- Attached to
- 743 ARMAG Fiber Install
- Solicitation number
- FA254321R0015
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity_24August21.docx | DOCX document | |
| RFI for 743 ARMAG Fiber Install 25 Aug 21.docx | DOCX document | |
| 743rd Camp Rattle Snake.pdf | ||
| RFI for 743 ARMAG Fiber Install 17 Aug 21.docx | DOCX document | |
| Solicitation Amendment FA254321R00150001 SF .pdf | ||
| ARMAG Route.docx | DOCX document | |
| SOW 743rd ARMAG Fiber Connectivity_16August21.docx | DOCX document | |
| UFC 3-550-01 Exterior Elec Power Distribution.pdf | ||
| UFC 3-580-01 Telecommunications Interior Infrastructure.pdf | ||
| RFI for 743 ARMAG Fiber Install 16 Aug 21.docx | DOCX document | |
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity_16August21.docx | DOCX document | |
| Solicitation - FA254321R0015.pdf | ||
| SOW 743rd ARMAG Fiber Connectivity 19July21.docx | DOCX document | |
| ARMAG WD 2015 5419.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI for 743 ARMAG Fiber Install
1. How far does the cable extend into each building?
Depending on where the terminal will be (identified to be at the close right corner near the entrance door) there will be a 6ft maintenance loop inside the ARMAG, terminated on _____(to be identified) and a 10ft maintenance loop in bldg. 1617 to the termination point in the rack; this can be pointed out and ID’d at the site visit.
2. What type of fiber connectors are required?
LC-UPC Connectors
3. How will the 2” conduit enter the ARMAG building?
Break through the concrete in front of the bldg., insert conduit, then cover that with concrete. This will be an option CLIN, meaning contractors will provide estimates, but we will not agree to that CLIN being performed until we exercise it.
4. Do the footages provided in the SOW include the required services loops?
Yes. See SOW Para 2.1
5. What is the total quantity of manholes in the existing route?
There are 8 existing manholes/pull boxes/hand holes (however you prefer to identify them). The approximated distance between last manhole and ARMAG will be determined by Mr. Milstead, but it is the contractor’s responsibility to confirm the distance depending on how they choose to lay the conduit.
6. What is the soil type where the trenching is required? (soft, hard, rock) Sandy/Clay mixture, there are small rocks on top.
7. Will any directional boring be required?
Boring will only be required if you intend to travel across a road; you will have to bore beneath it. Outside of this, boring is optional.
8. Would the Government please verify the footage of the pathway that required (1) Maxcell and (2) Maxcell innerducts.
Because the route chosen to lay conduit it decided by the contractor, this will be verified at site visit on Friday, 20 August, time TBD.
9. What are the Bonding Requirements?
All bonding requirements must meet the NEC and commercial comm codes if they are installing metallic conduit and/or cable with a metal strength member/shielding.
10. Will the 12 Strand fiber-optic material be provided, or will the contractor be responsible for procuring the material?
The contractor should provide the fiber cable.
Questions as of 25 August 2021
1. Is HDP Role acceptable in place of PVC?
HDP Role will not be acceptable in place of PVC Pipe; PVC pipe is the standard.
2. What is the guideline for filling with soil?
Must maintain soft fill – don’t crush rock into the conduit.
3. Will there be access to a fire hydrant for water access?
Yes, but will have to coordinate with the government
4. Is there any intent to add additional 10% slack?
No, 50ft is enough.
5. Regarding the concrete removed that the contractor will be responsible to replace, what is the total sq footage of concrete that will need to be replaced?
The sq footage will be about roughly 2ft x 10ft or about 20 sqft. Contractor is responsible for measurements.
6. 1617 building…is there a patch panel in the building already? Or will one need to be installed?
See SOW Para 2.2
7. Is there a specific spec on the patch panel being requested?
See SOW Para 2.2
Questions as of 31 August 2021
1. Does the 12 strand fiber cable need to be armored or non-armored?
NON armored OSP
2. Will there be plans provided before the bid is due?
Yes
3. What style of fiber connectors are we to splice on? ST or LC?
LC
4. While wheeling out the underground area on the site visit we measured out 200 ft not 170 ft that the plans state. Can this be confirmed?
All footages were approximate, needs to be confirmed by contractor.
5. For the installation of the new pipe, what will be required? Schedule 40 PVC, Schedule 80 PVC or HDPE?
Schedule 80 PVC is required
6. Is there any concrete encasement required?
Yes
7. Will the military cut the concrete required at the hut location and we will only have to restore the concrete?
Concrete requirements are discussed in the SOW. The government will cut the concrete from the edge of the concrete pad to the building. Contractor to back fill and install concrete as per SOW
8. How many existing Manholes will we have to pull the fiber into?
Please refer to drawing in contractor package