FA252126QB090_QA_20260728.pdf

PDF 44 KB Posted

Attached to
125 HP- 4300 Vertical Inline Pump
Solicitation number
FA252126QB090
Issued by

About this file

This is a Questions and Answers document for federal contract opportunity FA252126QB090. The Q&A addresses two key inquiries regarding delivery schedule requirements and evaluation criteria for this solicitation.

The document clarifies that offerors may propose their actual manufacturer lead time as part of a compliant technical quote, with delivery schedule evaluated as one of the stated evaluation factors under provision 52.212-2 (technical acceptability, price, and schedule) rather than as a pass/fail requirement. Offerors must clearly identify that proposed timeframes reflect manufacturer lead time to enable accurate government evaluation of schedule impacts. The government confirms it is using the Revolutionary FAR Overhaul (RFO) rather than legacy FAR provisions. Additionally, proposing a longer lead time than the stated 60-day delivery requirement will not automatically render an offer nonresponsive, allowing offerors flexibility in scheduling while maintaining technical compliance and enabling comparative evaluation across all three criteria.

View the file

Other files

File Type Posted
RFQ Solicitation_rev. 1-FA252126QB090.pdf PDF
FA252126QB090_QA_20260722.docx DOCX document
RFQ Solicitation-FA252126QB090.pdf PDF
432 south pump.jpg JPG image
Salient Char. Doc Pump Bldg 432 16Jul26.pdf PDF
432.jpg JPG image
432 north motor.jpg JPG image
432 south motor.jpg JPG image
432 north pump.jpg JPG image

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Q&A

Notice ID: FA252126QB090

Received Question and Answers (as of 28 July 2026)

1. May offerors propose their actual manufacturer lead time as part of a compliant technical quote, with delivery schedule considered as one of the stated evaluation factors under provision 52.212-2 (technical acceptability, price, and schedule) rather than as a pass/fail requirement?

Response: Offerors may propose their actual manufacturer lead time as part of a compliant technical quote. Offerors must clearly identify that the proposed timeframe reflects manufacturer lead time so the Government can evaluate schedule impacts accurately.

The Government is not using the legacy FAR; we are required to use the Revolutionary FAR Overhaul (RFO). See the clauses on the RFQ.

2. Is the 60-day delivery requirement a firm requirement that will render an offer non-responsive if a longer lead time is proposed?

Response: Proposing a longer lead time will not automatically render an offer non-responsive. See Question 1.