This document is a Questions and Answers (Q&A) file for the FA252125QB042 Target Retrieval System solicitation. The Q&A provides critical site-specific details for potential contractors, including confirmation of existing lane dividers, electrical infrastructure, and a mandatory site visit on 28 April 2025 at 10:00 AM EST at Patrick Space Force Base. Interested parties must contact SSgt Gage Belyeu to confirm site visit attendance.
The electrical details reveal that the current target sled charging stations each have individual outlets, with the electric conduit fed from the right side of the range. Electrical control for the target retrieval systems is managed through breaker numbers 38 and 40, with supplementary electrical connections available on breakers 46 and 50-54. The successful contractor will be required to work closely with the Civil Engineering Squadron to ensure proper electrical installations that meet safety and technical standards.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA252125QB042 – Target Retrieval System
Questions & Answers
Question 1: Can it be confirmed if there are existing dividers between the shooters?
Answer: Currently there are dividers set up in between each lane.
Question 2: Can as-builts or pictures be provided showing existing conditions to help determine the extent of what needs to be removed?
Answer: A site visit will be conducted on 28 April 2025 at 10:00 AM EST at Patrick SFB. Please reach out to SSgt Gage Belyeu at gage.belyeu.2@spaceforce.mil or 321-494-9950 to confirm attendance.
Question 3: Can it be confirmed if each target system currently installed are powered with electricity?
Answer: Each target sled charging station has its own outlet.
Question 4: If yes, can you confirm the location of the electrical and current existing power?
Answer: The electric conduit is fed from the wall on the right side of the range which feeds all power to the target sled chargers.
Range Electrical Clarification:
Electrical control for the target retrieval systems on the range is managed through breaker numbers 38 and 40. If supplementary electrical connections are required, breaker numbers 46 and 50-54 can be utilized. The successful awardee will work closely with the Civil Engineering Squadron to ensure that all electrical installations are properly completed in the panel, meeting all relevant safety and technical standards.