24R0047 - Q and A.docx
DOCX document 18 KB Posted
- Attached to
- BOM Concrete
- Solicitation number
- FA252124R0047
About this file
This document is a set of Questions and Answers (Q&A) related to a federal contract opportunity for concrete needed to erect a K-Span structure at the Kennedy Space Center for NASA.
The key details are:
- A concrete pump will be required for 4 pours on specific dates in December, January, and February, with the contractor able to use alternative distribution methods for the remaining pours. The total concrete required is 1,400 cubic yards.
- The vendor is responsible for delivering the concrete and turning on the pump or auger to pour it, with the government responsible for the concrete after it leaves the truck.
- Specific requirements are provided for the type of pump (boom vs. non-boom), hose length, and pump duration needed for the 4 pours requiring a pump. A slump of 5-6 inches is required for the stem wall pours, and 3-4 inches for all other pours.
- No drawings of the pour site are available, but a separate document with the concrete load amounts has been provided.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Concrete Load Amounts.xlsx | XLSX spreadsheet | |
| 24R0047 - Q and A.docx | DOCX document | |
| 24R0047 - Q and A.docx | DOCX document | |
| 24QB182 Salient Char. Doc.pdf | ||
| 24R0047 - CSS Final.pdf | ||
| 24R0047 - Clause Set.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA252124R0047 – BOM Concrete Q and A Q: “Could you confirm whether a concrete pump will be required to distribute wet concrete from the mixer trucks, or if an alternative distribution method is acceptable for the project?”
A: A concrete pump will be required for 4 pours (those estimated for the 17th and 18th of December, as well as the 30th of Jan and the 18th of Feb). The rest can use alternative methods of distribution or a pump as the contractor sees fit.
Here are the amounts of concrete that we will need for each of the estimated pour days.
| Estimated Date |
| Pour |
| Estimated CY |
| 17-Dec-24 |
| Stem wall footer West |
| 93 |
| 18-Dec-24 |
| Stem wall footer East |
| 93 |
| 3-Jan-25 |
| Interior building lanes (part 1) |
| 178 |
| 15-Jan-25 |
| Exterior East and West |
| 196 |
| 18-Jan-25 |
| Interior building lanes (part 2) |
| 178 |
| 30-Jan-25 |
| Stem wall West |
| 60 |
| 18-Feb-25 |
| Stem wall East |
| 60 |
| 15-Mar-25 |
| Cap endwalls |
| 28 |
| 22-Mar-25 |
| Exterior south end part 1 |
| 156 |
| 24-Mar-25 |
| Exterior south end part 2 |
| 156 |
| 7-Apr-25 |
| Exterior north end part 1 |
| 101 |
| 9-Apr-25 |
| Exterior north end part 2 |
| 101 |
| Total |
| 1400 |
Q: “Page 1 of the "Combined Synopsis Solicitation" states "to be poured by the vendor" Please specify in detail what the government intends to include in that activity. Specifically, does the government expect the vendor to do any work with the concrete after it leaves the delivery truck or pump? If so, what additional work is required.”
A: Vendor would bring concrete to site and turn on pump or auger to pour concrete. Government is entirely responsible for concrete once it leaves the truck.
Q: “The government has advised that it wants the services of a pump to be included for some of the dates. Pump charges are typically based on the equipment and time at the location and other factors. Please provide the following additional information for each date for which a pump is required
(a) Type of pump required, such as with a boom (might be needed for stem walls depending on elevation). If non-boom, how long a hose will be required. If boom, the reach and height needed.
(b) Either how long the pump will need to be at the delivery location or the desired spacing for the trucks. Either of these will allow us to determine the time component cost for the pump.”
A: For the foundation pours estimated to proceed on the 17th and 18th of December, those would not necessarily require a boom, with a 10’ – 15’ long hose substituting just fine. For the stem wall pours estimated to proceed on 30 January and 18 February, a boom with reach of at least 20’ high and 5’ – 10’ out. For all 4 of those pour days, pump would need to be there all day or until all concrete is placed (monolithic pours with estimated cubic yards for each day: 17Dec: 93CY, 18 Dec: 93CY, 30Jan: 60CY, 18Feb: 60CY).
Q: “Slump requirement for each date.”
A: For the two stem wall pours estimated to take place on 30 January and 18 February, we are requesting 5” – 6” of slump. For all other pours we are requesting 3” – 4” of slump.
Q: Are there any drawings regarding the pour site?
A: No, we have been unable to acquire any drawings for the requirement. But, we were able to obtain load amounts now attached onto SAM post, named “Concrete Load Amounts”.