24R0047 - Q and A.docx
DOCX document 15 KB Posted
- Attached to
- BOM Concrete
- Solicitation number
- FA252124R0047
About this file
This document is a Q&A related to a concrete solicitation for the construction of a K-Span structure at the Kennedy Space Center for the Department of the Air Force Space Command. The solicitation requires 1,400 cubic yards of ASTM C150/C150M Type II concrete with 3/4" or lower gradation conforming to ASTM C33/C33M, with no additives. A concrete pump will be required for 4 of the 12 estimated concrete pours, while alternative distribution methods can be used for the remaining pours. The document provides the estimated concrete quantities and pour dates for the various components of the project, which includes stem walls, interior building lanes, exterior walls, and cap endwalls.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 24R0047 - Q and A.docx | DOCX document | |
| Concrete Load Amounts.xlsx | XLSX spreadsheet | |
| 24R0047 - Q and A.docx | DOCX document | |
| 24R0047 - Clause Set.pdf | ||
| 24QB182 Salient Char. Doc.pdf | ||
| 24R0047 - CSS Final.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA252124R0047 – BOM Concrete Q and A Q: “Could you confirm whether a concrete pump will be required to distribute wet concrete from the mixer trucks, or if an alternative distribution method is acceptable for the project?”
A: A concrete pump will be required for 4 pours (those estimated for the 17th and 18th of December, as well as the 30th of Jan and the 18th of Feb). The rest can use alternative methods of distribution or a pump as the contractor sees fit.
Here are the amounts of concrete that we will need for each of the estimated pour days.
| Estimated Date |
| Pour |
| Estimated CY |
| 17-Dec-24 |
| Stem wall footer West |
| 93 |
| 18-Dec-24 |
| Stem wall footer East |
| 93 |
| 3-Jan-25 |
| Interior building lanes (part 1) |
| 178 |
| 15-Jan-25 |
| Exterior East and West |
| 196 |
| 18-Jan-25 |
| Interior building lanes (part 2) |
| 178 |
| 30-Jan-25 |
| Stem wall West |
| 60 |
| 18-Feb-25 |
| Stem wall East |
| 60 |
| 15-Mar-25 |
| Cap endwalls |
| 28 |
| 22-Mar-25 |
| Exterior south end part 1 |
| 156 |
| 24-Mar-25 |
| Exterior south end part 2 |
| 156 |
| 7-Apr-25 |
| Exterior north end part 1 |
| 101 |
| 9-Apr-25 |
| Exterior north end part 2 |
| 101 |
| Total |
| 1400 |