24R0047 - Q and A.docx

DOCX document 15 KB Posted

Attached to
BOM Concrete
Solicitation number
FA252124R0047
Issued by

About this file

This document is a Q&A related to a concrete solicitation for the construction of a K-Span structure at the Kennedy Space Center for the Department of the Air Force Space Command. The solicitation requires 1,400 cubic yards of ASTM C150/C150M Type II concrete with 3/4" or lower gradation conforming to ASTM C33/C33M, with no additives. A concrete pump will be required for 4 of the 12 estimated concrete pours, while alternative distribution methods can be used for the remaining pours. The document provides the estimated concrete quantities and pour dates for the various components of the project, which includes stem walls, interior building lanes, exterior walls, and cap endwalls.

View the file

Other files

File Type Posted
24R0047 - Q and A.docx DOCX document
Concrete Load Amounts.xlsx XLSX spreadsheet
24R0047 - Q and A.docx DOCX document
24R0047 - Clause Set.pdf PDF
24QB182 Salient Char. Doc.pdf PDF
24R0047 - CSS Final.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA252124R0047 – BOM Concrete Q and A Q: “Could you confirm whether a concrete pump will be required to distribute wet concrete from the mixer trucks, or if an alternative distribution method is acceptable for the project?”

A: A concrete pump will be required for 4 pours (those estimated for the 17th and 18th of December, as well as the 30th of Jan and the 18th of Feb). The rest can use alternative methods of distribution or a pump as the contractor sees fit.

Here are the amounts of concrete that we will need for each of the estimated pour days.

Estimated Date
Pour
Estimated CY
17-Dec-24
Stem wall footer West
93
18-Dec-24
Stem wall footer East
93
3-Jan-25
Interior building lanes (part 1)
178
15-Jan-25
Exterior East and West
196
18-Jan-25
Interior building lanes (part 2)
178
30-Jan-25
Stem wall West
60
18-Feb-25
Stem wall East
60
15-Mar-25
Cap endwalls
28
22-Mar-25
Exterior south end part 1
156
24-Mar-25
Exterior south end part 2
156
7-Apr-25
Exterior north end part 1
101
9-Apr-25
Exterior north end part 2
101
Total
1400