Updated Site Visit information under Clause 52.236-27 Site visit changed from Thursday, 20 Jul 17 @ 9 am to Friday, Aug 4 17 @ 9 am.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA252117B0007
Section B - Supplies or Services and Prices
| ITEM NO |
| SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| 1 |
| Each |
DBEH 14-1502 Repair High Vltge Duct Bank
FFP
The work to be performed under this project consists of providing the labor, equipment and materials to remove overhead open wire 13.2 kV circuits and replace with underground duct bank circuits. Additionally, the project involves installation of several 13.2kV pad mounted load break switches. The project also involves the removal and replacement of several 13.2kV (primary) pad mounted transformers. The work area includes Industrial Shops, SAB Annex, Gen Shop, and GPS areas.
All work to be completed in accordance with the Statement of Work, contract specifications and maps/drawings as listed in Section J, Attachments.
FOB: Destination
PURCHASE REQUEST NUMBER: F3K3DH7131A003
PROJECT: DBEH 14-1502
NET AMT
Section E - Inspection and Acceptance
WEEKLY PROGRESS REPORTS
For the purpose of clause 52.236-15, Schedules for Construction Contracts, the Contractor shall use AF IMT 3065, or equivalent, to chart progress and submit weekly within one week of actual performance.
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
| CLIN |
| INSPECT AT |
| INSPECT BY |
| ACCEPT AT |
| ACCEPT BY |
| 0001 |
| N/A |
| N/A |
| N/A |
| Government |
CLAUSES INCORPORATED BY REFERENCE
| 52.246-12 |
| Inspection of Construction |
| AUG 1996 |
Section F - Deliveries or Performance
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
| 0001 |
| 302 dys. ADC |
| 1 |
| 45 CES/CEL - F3K3DH |
COREY COOPER
185 WEST SKID STRIP ROAD CCAFS MS 2006
CAPE CANAVERAL FL 32925
321-853-9718 FOB: Destination
F3K3DH
DELIVERY INFORMATION
| CLIN |
| DELIVERY DATE |
| QUANTITY |
| SHIP TO ADDRESS |
| DODAAC / CAGE |
| 0001 |
| 302 dys. ADC |
| 1 |
| 45 CES/CEL - F3K3DH |
COREY COOPER
185 WEST SKID STRIP ROAD CCAFS MS 2006
CAPE CANAVERAL FL 32925
321-853-9718 FOB: Destination
F3K3DH
CLAUSES INCORPORATED BY FULL TEXT
52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 302 calendar days, including 48 non-access days and 30 days for material lead time.
The time stated for completion shall include final cleanup of the premises.
(End of clause)
52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $326.58 for the first day and $256.95 for each calendar day of delay thereafter until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
(End of clause)
Section G - Contract Administration Data
| 52.232-5 |
| Payments under Fixed-Price Construction Contracts |
| MAY 2014 |
| 252.204-7006 |
| Billing Instructions |
| OCT 2005 |
| 252.232-7003 |
| Electronic Submission of Payment Requests and Receiving Reports |
| JUN 2012 |
252.232-7006 WIDE AREA WORKFLOW PAYMENT INSTRUCTIONS (MAY 2013)
(a) Definitions. As used in this clause--
Department of Defense Activity Address Code (DoDAAC) is a six position code that uniquely identifies a unit, activity, or organization.
Document type means the type of payment request or receiving report available for creation in Wide Area WorkFlow (WAWF).
Local processing office (LPO) is the office responsible for payment certification when payment certification is done external to the entitlement system.
(b) Electronic invoicing. The WAWF system is the method to electronically process vendor payment requests and receiving reports, as authorized by DFARS 252.232-7003, Electronic Submission of Payment Requests and Receiving Reports.
(c) WAWF access. To access WAWF, the Contractor shall--
(1) Have a designated electronic business point of contact in the System for Award Management at https://www.acquisition.gov; and
(2) Be registered to use WAWF at https://wawf.eb.mil/ following the step-by-step procedures for self-registration available at this Web site.
(d) WAWF training. The Contractor should follow the training instructions of the WAWF Web-Based Training Course and use the Practice Training Site before submitting payment requests through WAWF. Both can be accessed by selecting the “Web Based Training” link on the WAWF home page at https://wawf.eb.mil/.
(e) WAWF methods of document submission. Document submissions may be via Web entry, Electronic Data Interchange, or File Transfer Protocol.
(f) WAWF payment instructions. The Contractor must use the following information when submitting payment requests and receiving reports in WAWF for this contract/order:
(1) Document type. The Contractor shall use the following document type(s).
“Construction Payment Invoice”
(2) Inspection/acceptance location. The Contractor shall select the following inspection/acceptance location(s) in WAWF, as specified by the contracting officer.
| Inspect By DODAAC | F3K3DH |
| Accept By DODAAC | FA2521 |
(3) Document routing. The Contractor shall use the information in the Routing Data Table below only to fill in applicable fields in WAWF when creating payment requests and receiving reports in the system.
Routing Data Table Field Name in WAWF Data to be entered in WAWF
| Pay Official DoDAAC | F03000 | ||
| Issue By DoDAAC | FA2521 | ||
| Admin DoDAAC | FA2521 | ||
| Inspect By DoDAAC | F3K3DH | ||
| Ship To Code | N/A | ||
| Ship From Code | N/A | ||
| Mark For Code | N/A | ||
| Service Approver (DoDAAC) | N/A | ||
| Service Acceptor (DoDAAC) | FA2521 | ||
| Accept at Other DoDAAC | N/A | ||
| LPO DoDAAC | N/A | ||
| DCAA Auditor DoDAAC | N/A | ||
| Other DoDAAC(s) | FA2521 |
(4) Payment request and supporting documentation. The Contractor shall ensure a payment request includes appropriate contract line item and subline item descriptions of the work performed or supplies delivered, unit price/cost per unit, fee (if applicable), and all relevant back-up documentation, as defined in DFARS Appendix F, (e.g. timesheets) in support of each payment request.
(5) WAWF email notifications. The Contractor shall enter the email address identified below in the “Send Additional Email Notifications” field of WAWF once a document is submitted in the system.
patricia.bates@us.af.mil eugenia.faulkner_russell@us.af.mil kristin.doty@us.af.mil corey.cooper@us.af.mil elsa.feliciano@us.af.mil mary.howze@us.af.mil
(g) WAWF point of contact. (1) The Contractor may obtain clarification regarding invoicing in WAWF from the following contracting activity's WAWF point of contact.
Not applicable.
(2) For technical WAWF help, contact the WAWF helpdesk at 866-618-5988.
Section I - Contract Clauses
| 52.202-1 |
| Definitions |
| NOV 2013 |
| 52.203-3 |
| Gratuities |
| APR 1984 |
| 52.203-5 |
| Covenant Against Contingent Fees |
| MAY 2014 |
| 52.203-6 |
| Restrictions On Subcontractor Sales To The Government |
| SEP 2006 |
| 52.203-7 |
| Anti-Kickback Procedures |
| MAY 2014 |
| 52.203-8 |
| Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity |
| MAY 2014 |
| 52.203-10 |
| Price Or Fee Adjustment For Illegal Or Improper Activity |
| MAY 2014 |
| 52.203-12 |
| Limitation On Payments To Influence Certain Federal Transactions |
| OCT 2010 |
| 52.203-13 |
| Contractor Code of Business Ethics and Conduct |
| OCT 2015 |
| 52.203-17 |
| Contractor Employee Whistleblower Rights and Requirement To Inform Employees of Whistleblower Rights |
| APR 2014 |
| 52.203-18 |
| Prohibition on Contracting With Entities That Require Certain Internal Confidentiality Agreements or Statements--Representation |
| JAN 2017 |
| 52.203-19 |
| Prohibition on Requiring Certain Internal Confidentiality Agreeements or Statements |
| JAN 2017 |
| 52.204-2 Alt II |
| Security Requirements (Aug 1996) - Alternate II |
| APR 1984 |
| 52.204-4 |
| Printed or Copied Double-Sided on Postconsumer Fiber Content Paper |
| MAY 2011 |
| 52.204-9 |
| Personal Identity Verification of Contractor Personnel |
| JAN 2011 |
| 52.204-10 |
| Reporting Executive Compensation and First-Tier Subcontract Awards |
| OCT 2016 |
| 52.204-13 |
| System for Award Management Maintenance |
| OCT 2016 |
| 52.204-16 |
| Commercial and Government Entity Code Reporting |
| JUL 2016 |
| 52.204-18 |
| Commercial and Government Entity Code Maintenance |
| JUL 2016 |
| 52.204-19 |
| Incorporation by Reference of Representations and Certifications. |
| DEC 2014 |
| 52.209-6 |
| Protecting the Government's Interest When Subcontracting With Contractors Debarred, Suspended, or Proposed for Debarment |
| OCT 2015 |
| 52.209-9 |
| Updates of Publicly Available Information Regarding Responsibility Matters |
| JUL 2013 |
| 52.209-10 |
| Prohibition on Contracting With Inverted Domestic Corporations |
| NOV 2015 |
| 52.210-1 |
| Market Research |
| APR 2011 |
| 52.212-3 |
| Offeror Representations and Certifications--Commercial Items |
| JAN 2017 |
| 52.214-26 |
| Audit and Records--Sealed Bidding |
| OCT 2010 |
| 52.214-27 |
| Price Reduction for Defective Certified Cost or Pricing Data - Modifications - Sealed Bidding |
| AUG 2011 |
| 52.214-28 |
| Subcontracting Certified Cost Or Pricing Data--Modifications--Sealed Bidding |
| OCT 2010 |
| 52.214-29 |
| Order Of Precedence--Sealed Bidding |
| JAN 1986 |
| 52.215-8 |
| Order of Precedence--Uniform Contract Format |
| OCT 1997 |
| 52.215-11 |
| Price Reduction for Defective Certified Cost or Pricing Data--Modifications |
| AUG 2011 |
| 52.215-13 |
| Subcontractor Certified Cost or Pricing Data--Modifications |
| OCT 2010 |
| 52.215-15 |
| Pension Adjustments and Asset Reversions |
| OCT 2010 |
| 52.215-17 |
| Waiver of Facilities Capital Cost of Money |
| OCT 1997 |
| 52.215-18 |
| Reversion or Adjustment of Plans for Postretirement Benefits (PRB) Other than Pensions |
| JUL 2005 |
| 52.215-19 |
| Notification of Ownership Changes |
| OCT 1997 |
| 52.215-21 |
| Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data -- Modifications |
| OCT 2010 |
| 52.215-21 Alt III |
| Requirements for Certified Cost or Pricing Data and Data Other Than Certified Cost or Pricing Data -- Modifications (Oct 2010) - Alternate III |
| OCT 1997 |
| 52.219-8 |
| Utilization of Small Business Concerns |
| NOV 2016 |
| 52.219-14 |
| Limitations On Subcontracting |
| JAN 2017 |
| 52.219-28 |
| Post-Award Small Business Program Rerepresentation |
| JUL 2013 |
| 52.222-3 |
| Convict Labor |
| JUN 2003 |
| 52.222-4 |
| Contract Work Hours and Safety Standards- Overtime Compensation |
| MAY 2014 |
| 52.222-6 |
| Construction Wage Rate Requirements |
| MAY 2014 |
| 52.222-7 |
| Withholding of Funds |
| MAY 2014 |
| 52.222-8 |
| Payrolls and Basic Records |
| MAY 2014 |
| 52.222-9 |
| Apprentices and Trainees |
| JUL 2005 |
| 52.222-10 |
| Compliance with Copeland Act Requirements |
| FEB 1988 |
| 52.222-11 |
| Subcontracts (Labor Standards) |
| MAY 2014 |
| 52.222-12 |
| Contract Termination-Debarment |
| MAY 2014 |
| 52.222-13 |
| Compliance With Construction Wage Rate Requirements and Related Regulations |
| MAY 2014 |
| 52.222-14 |
| Disputes Concerning Labor Standards |
| FEB 1988 |
| 52.222-15 |
| Certification of Eligibility |
| MAY 2014 |
| 52.222-21 |
| Prohibition Of Segregated Facilities |
| APR 2015 |
| 52.222-26 |
| Equal Opportunity |
| SEP 2016 |
| 52.222-27 |
| Affirmative Action Compliance Requirements for Construction |
| APR 2015 |
| 52.222-34 |
| Project Labor Agreement |
| MAY 2010 |
| 52.222-35 |
| Equal Opportunity for Veterans |
| OCT 2015 |
| 52.222-36 |
| Equal Opportunity for Workers with Disabilities |
| JUL 2014 |
| 52.222-37 |
| Employment Reports on Veterans |
| FEB 2016 |
| 52.222-40 |
| Notification of Employee Rights Under the National Labor Relations Act |
| DEC 2010 |
| 52.222-50 |
| Combating Trafficking in Persons |
| MAR 2015 |
| 52.222-54 |
| Employment Eligibility Verification |
| OCT 2015 |
| 52.222-55 |
| Minimum Wages Under Executive Order 13658 |
| DEC 2015 |
| 52.223-1 |
| Biobased Product Certification |
| MAY 2012 |
| 52.223-2 |
| Affirmative Procurement of Biobased Products Under Service and Construction Contracts |
| SEP 2013 |
| 52.223-3 |
| Hazardous Material Identification And Material Safety Data |
| JAN 1997 |
| 52.223-5 |
| Pollution Prevention and Right-to-Know Information |
| MAY 2011 |
| 52.223-6 |
| Drug-Free Workplace |
| MAY 2001 |
| 52.223-12 |
| Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners. |
| JUN 2016 |
| 52.223-15 |
| Energy Efficiency in Energy-Consuming Products |
| DEC 2007 |
| 52.223-17 |
| Affirmative Procurement of EPA-Designated Items in Service and Construction Contracts |
| MAY 2008 |
| 52.224-1 |
| Privacy Act Notification |
| APR 1984 |
| 52.225-13 |
| Restrictions on Certain Foreign Purchases |
| JUN 2008 |
| 52.227-1 |
| Authorization and Consent |
| DEC 2007 |
| 52.227-2 |
| Notice And Assistance Regarding Patent And Copyright Infringement |
| DEC 2007 |
| 52.227-4 |
| Patent Indemnity-Construction Contracts |
| DEC 2007 |
| 52.228-2 |
| Additional Bond Security |
| OCT 1997 |
| 52.228-5 |
| Insurance - Work On A Government Installation |
| JAN 1997 |
| 52.228-11 |
| Pledges Of Assets |
| JAN 2012 |
| 52.228-12 |
| Prospective Subcontractor Requests for Bonds |
| MAY 2014 |
| 52.228-14 |
| Irrevocable Letter of Credit |
| NOV 2014 |
| 52.228-15 |
| Performance and Payment Bonds--Construction |
| OCT 2010 |
| 52.229-3 |
| Federal, State And Local Taxes |
| FEB 2013 |
| 52.232-17 |
| Interest |
| MAY 2014 |
| 52.232-18 |
| Availability Of Funds |
| APR 1984 |
| 52.232-23 |
| Assignment Of Claims |
| MAY 2014 |
| 52.232-27 |
| Prompt Payment for Construction Contracts |
| JAN 2017 |
| 52.232-33 |
| Payment by Electronic Funds Transfer--System for Award Management |
| JUL 2013 |
| 52.232-39 |
| Unenforceability of Unauthorized Obligations |
| JUN 2013 |
| 52.232-40 |
| Providing Accelerated Payments to Small Business Subcontractors |
| DEC 2013 |
| 52.233-1 |
| Disputes |
| MAY 2014 |
| 52.233-1 Alt I |
| Disputes (May 2014) - Alternate I |
| DEC 1991 |
| 52.233-3 |
| Protest After Award |
| AUG 1996 |
| 52.233-4 |
| Applicable Law for Breach of Contract Claim |
| OCT 2004 |
| 52.236-1 |
| Performance of Work by the Contractor |
| APR 1984 |
| 52.236-2 |
| Differing Site Conditions |
| APR 1984 |
| 52.236-3 |
| Site Investigation and Conditions Affecting the Work |
| APR 1984 |
| 52.236-4 |
| Physical Data |
| APR 1984 |
| 52.236-5 |
| Material and Workmanship |
| APR 1984 |
| 52.236-6 |
| Superintendence by the Contractor |
| APR 1984 |
| 52.236-7 |
| Permits and Responsibilities |
| NOV 1991 |
| 52.236-8 |
| Other Contracts |
| APR 1984 |
| 52.236-9 |
| Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements |
| APR 1984 |
| 52.236-10 |
| Operations and Storage Areas |
| APR 1984 |
| 52.236-11 |
| Use and Possession Prior to Completion |
| APR 1984 |
| 52.236-12 |
| Cleaning Up |
| APR 1984 |
| 52.236-13 |
| Accident Prevention |
| NOV 1991 |
| 52.236-14 |
| Availability and Use of Utility Services |
| APR 1984 |
| 52.236-15 |
| Schedules for Construction Contracts |
| APR 1984 |
| 52.236-17 |
| Layout of Work |
| APR 1984 |
| 52.236-21 |
| Specifications and Drawings for Construction |
| FEB 1997 |
| 52.236-21 Alt I |
| Specifications and Drawings for Construction (Feb 1997) - Alternate I |
| APR 1984 |
| 52.236-26 |
| Preconstruction Conference |
| FEB 1995 |
| 52.242-13 |
| Bankruptcy |
| JUL 1995 |
| 52.242-14 |
| Suspension of Work |
| APR 1984 |
| 52.243-4 |
| Changes |
| JUN 2007 |
| 52.244-5 |
| Competition In Subcontracting |
| DEC 1996 |
| 52.244-6 |
| Subcontracts for Commercial Items |
| JAN 2017 |
| 52.246-21 |
| Warranty of Construction |
| MAR 1994 |
| 52.248-3 |
| Value Engineering-Construction |
| OCT 2015 |
| 52.249-2 |
| Termination For Convenience Of The Government (Fixed-Price) |
| APR 2012 |
| 52.249-2 Alt I |
| Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate I |
| SEP 1996 |
| 52.249-2 Alt III |
| Termination for Convenience of the Government (Fixed-Price) (Apr 2012) - Alternate III |
| SEP 1996 |
| 52.249-10 |
| Default (Fixed-Price Construction) |
| APR 1984 |
| 52.253-1 |
| Computer Generated Forms |
| JAN 1991 |
| 252.201-7000 |
| Contracting Officer's Representative |
| DEC 1991 |
| 252.203-7000 |
| Requirements Relating to Compensation of Former DoD Officials |
| SEP 2011 |
| 252.203-7001 |
| Prohibition On Persons Convicted of Fraud or Other Defense-Contract-Related Felonies |
| DEC 2008 |
| 252.203-7002 |
| Requirement to Inform Employees of Whistleblower Rights |
| SEP 2013 |
| 252.203-7003 |
| Agency Office of the Inspector General |
| DEC 2012 |
| 252.203-7004 |
| Display of Hotline Posters |
| OCT 2016 |
| 252.204-7000 |
| Disclosure Of Information |
| OCT 2016 |
| 252.204-7003 |
| Control Of Government Personnel Work Product |
| APR 1992 |
| 252.204-7004 Alt A |
| System for Award Management Alternate A |
| FEB 2014 |
| 252.204-7012 |
| Safeguarding Covered Defense Information and Cyber Incident Reporting |
| OCT 2016 |
| 252.204-7015 |
| Notice of Authorized Disclosure of Information for Litigation Support |
| MAY 2016 |
| 252.209-7004 |
| Subcontracting With Firms That Are Owned or Controlled By The Government of a Country that is a State Sponsor of Terrorism |
| OCT 2015 |
| 252.219-7011 |
| Notification to Delay Performance |
| JUN 1998 |
| 252.223-7004 |
| Drug Free Work Force |
| SEP 1988 |
| 252.223-7006 |
| Prohibition On Storage, Treatment, and Disposal of Toxic or Hazardous Materials |
| SEP 2014 |
| 252.225-7016 |
| Restriction On Acquisition Of Ball and Roller Bearings |
| JUN 2011 |
| 252.225-7048 |
| Export-Controlled Items |
| JUN 2013 |
| 252.226-7001 |
| Utilization of Indian Organizations and Indian-Owned Economic Enterprises, and Native Hawaiian Small Business Concerns |
| SEP 2004 |
| 252.227-7033 |
| Rights in Shop Drawings |
| APR 1966 |
| 252.232-7010 |
| Levies on Contract Payments |
| DEC 2006 |
| 252.236-7000 |
| Modification Proposals-Price Breakdown |
| DEC 1991 |
| 252.243-7001 |
| Pricing Of Contract Modifications |
| DEC 1991 |
| 252.243-7002 |
| Requests for Equitable Adjustment |
| DEC 2012 |
| 252.244-7000 |
| Subcontracts for Commercial Items |
| JUN 2013 |
| 252.246-7004 |
| Safety of Facilities, Infrastructure, and Equipment for Military Operations |
| OCT 2010 |
| 252.246-7006 |
| Warranty Tracking of Serialized Items |
| MAR 2016 |
| 252.247-7023 |
| Transportation of Supplies by Sea |
| APR 2014 |
52.203-19 PROHIBITION ON REQUIRING CERTAIN INTERNAL CONFIDENTIALITY AGREEMENTS OR STATEMENTS (JAN 2017)
Internal confidentiality agreement or statement means a confidentiality agreement or any other written statement that the contractor requires any of its employees or subcontractors to sign regarding nondisclosure of contractor information, except that it does not include confidentiality agreements arising out of civil litigation or confidentiality agreements that contractor employees or subcontractors sign at the behest of a Federal agency.
Subcontract means any contract as defined in subpart 2.1 entered into by a subcontractor to furnish supplies or services for performance of a prime contract or a subcontract. It includes but is not limited to purchase orders, and changes and modifications to purchase orders.
Subcontractor means any supplier, distributor, vendor, or firm (including a consultant) that furnishes supplies or services to or for a prime contractor or another subcontractor.
(b) The Contractor shall not require its employees or subcontractors to sign or comply with internal confidentiality agreements or statements prohibiting or otherwise restricting such employees or subcontractors from lawfully reporting waste, fraud, or abuse related to the performance of a Government contract to a designated investigative or law enforcement representative of a Federal department or agency authorized to receive such information (e.g., agency Office of the Inspector General).
(c) The Contractor shall notify current employees and subcontractors that prohibitions and restrictions of any preexisting internal confidentiality agreements or statements covered by this clause, to the extent that such prohibitions and restrictions are inconsistent with the prohibitions of this clause, are no longer in effect.
(d) The prohibition in paragraph (b) of this clause does not contravene requirements applicable to Standard Form 312 (Classified Information Nondisclosure Agreement), Form 4414 (Sensitive Compartmented Information Nondisclosure Agreement), or any other form issued by a Federal department or agency governing the nondisclosure of classified information.
(e) In accordance with section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015, (Pub. L. 113-235), and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions) use of funds appropriated (or otherwise made available) is prohibited, if the Government determines that the Contractor is not in compliance with the provisions of this clause.
(f) The Contractor shall include the substance of this clause, including this paragraph (f), in subcontracts under such contracts.
52.223-9 ESTIMATE OF PERCENTAGE OF RECOVERED MATERIAL CONTENT FOR EPA-DESIGNATED ITEMS (MAY 2008)
Postconsumer material means a material or finished product that has served its intended use and has been discarded for disposal or recovery, having completed its life as a consumer item. Postconsumer material is a part of the broader category of “recovered material.”
Recovered material means waste materials and by-products recovered or diverted from solid waste, but the term does not include those materials and by-products generated from, and commonly reused within, an original manufacturing process.
(b) The Contractor, on completion of this contract, shall--
(1) Estimate the percentage of the total recovered material content for EPA-designated item(s) delivered and/or used in contract performance, including, if applicable, the percentage of post-consumer material content; and
(2) Submit this estimate to Mr. Corey Cooper, Project Manager, 45 CES/CEZ.
52.223-11 OZONE-DEPLETING SUBSTANCES AND HIGH GLOBAL WARMING POTENTIAL HYDROFLUOROCARBONS (JUN 2016)
Global warming potential means how much a given mass of a chemical contributes to global warming over a given time period compared to the same mass of carbon dioxide. Carbon dioxide's global warming potential is defined as 1.0.
High global warming potential hydrofluorocarbons means any hydrofluorocarbons in a particular end use for which EPA's Significant New Alternatives Policy (SNAP) program has identified other acceptable alternatives that have lower global warming potential. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables of alternatives available at (http://www.epa.gov/snap/).
Hydrofluorocarbons means compounds that only contain hydrogen, fluorine, and carbon.
Ozone-depleting substance means any substance the Environmental Protection Agency designates in 40 CFR part 82 as--
(1) Class I, including, but not limited to, chlorofluorocarbons, halons, carbon tetrachloride, and methyl chloroform; or
(2) Class II, including, but not limited to, hydrochlorofluorocarbons.
(b) The Contractor shall label products that contain or are manufactured with ozone-depleting substances in the manner and to the extent required by 42 U.S.C. 7671j (b), (c), (d), and (e) and 40 CFR part 82, subpart E, as follows:
Warning: Contains (or manufactured with, if applicable) *_______, a substance(s) which harm(s) public health and environment by destroying ozone in the upper atmosphere.
* The Contractor shall insert the name of the substance(s).
(c) Reporting. For equipment and appliances that normally each contain 50 or more pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons, the Contractor shall--
(1) Track on an annual basis, between October 1 and September 30, the amount in pounds of hydrofluorocarbons or refrigerant blends containing hydrofluorocarbons contained in the equipment and appliances delivered to the Government under this contract by--
(i) Type of hydrofluorocarbon (e.g., HFC-134a, HFC-125, R-410A, R-404A, etc.);
(ii) Contract number; and
(iii) Equipment/appliance;
(2) Report that information to the Contracting Officer for FY16 and to www.sam.gov, for FY17 and after--
(i) Annually by November 30 of each year during contract performance; and
(ii) At the end of contract performance.
(d) The Contractor shall refer to EPA's SNAP program (available at http://www.epa.gov/snap) to identify alternatives. The SNAP list of alternatives is found at 40 CFR part 82, subpart G, with supplemental tables available at http://www.epa.gov/snap.
52.225-9 BUY AMERICAN—CONSTRUCTION MATERIALS (MAY 2014)
Commercially available off-the-shelf (COTS) item—
(1) Means any item of supply (including construction material) that is--
(i) A commercial item (as defined in paragraph (1) of the definition at FAR 2.101);
(ii) Sold in substantial quantities in the commercial marketplace; and
(iii) Offered to the Government, under a contract or subcontract at any tier, without modification, in the same form in which it is sold in the commercial marketplace; and
(2) Does not include bulk cargo, as defined in 46 U.S.C. 40102(4) such as agricultural products and petroleum products.
Component means an article, material, or supply incorporated directly into a construction material.
Construction material means an article, material, or supply brought to the construction site by the Contractor or a subcontractor for incorporation into the building or work. The term also includes an item brought to the site preassembled from articles, materials, or supplies. However, emergency life safety systems, such as emergency lighting, fire alarm, and audio evacuation systems, that are discrete systems incorporated into a public building or work and that are produced as complete systems, are evaluated as a single and distinct construction material regardless of when or how the individual parts or components of those systems are delivered to the construction site. Materials purchased directly by the Government are supplies, not construction material.
Cost of components means--
(1) For components purchased by the Contractor, the acquisition cost, including transportation costs to the place of incorporation into the construction material (whether or not such costs are paid to a domestic firm), and any applicable duty (whether or not a duty-free entry certificate is issued); or
(2) For components manufactured by the Contractor, all costs associated with the manufacture of the component, including transportation costs as described in paragraph (1) of this definition, plus allocable overhead costs, but excluding profit. Cost of components does not include any costs associated with the manufacture of the construction material.
Domestic construction material means--
(1) An unmanufactured construction material mined or produced in the United States;
(2) A construction material manufactured in the United States, if--
(i) The cost of its components mined, produced, or manufactured in the United States exceeds 50 percent of the cost of all its components. Components of foreign origin of the same class or kind for which nonavailability determinations have been made are treated as domestic; or
(ii) The construction material is a COTS item.
Foreign construction material means a construction material other than a domestic construction material.
United States means the 50 States, the District of Columbia, and outlying areas.
(b) Domestic preference.
(1) This clause implements 41 U.S.C. chapter 83, Buy American, by providing a preference for domestic construction material. In accordance with 41 U.S.C. 1907, the component test of the Buy American statute is waived for construction material that is a COTS item. (See FAR 12.505(a)(2)). The Contractor shall use only domestic construction material in performing this contract, except as provided in paragraphs (b)(2) and (b)(3) of this clause.
(2) This requirement does not apply to information technology that is a commercial item or to the construction materials or components listed by the Government as follows:
(3) The Contracting Officer may add other foreign construction material to the list in paragraph (b)(2) of this clause if the Government determines that
(i) The cost of domestic construction material would be unreasonable. The cost of a particular domestic construction material subject to the requirements of the Buy American Act is unreasonable when the cost of such material exceeds the cost of foreign material by more than 6 percent;
(ii) The application of the restriction of the Buy American Act to a particular construction material would be impracticable or inconsistent with the public interest; or
(iii) The construction material is not mined, produced, or manufactured in the United States in sufficient and reasonably available commercial quantities of a satisfactory quality.
(c) Request for determination of inapplicability of the Buy American Act. (1)(i) Any Contractor request to use foreign construction material in accordance with paragraph (b)(3) of this clause shall include adequate information for Government evaluation of the request, including--
(A) A description of the foreign and domestic construction materials;
(B) Unit of measure;
(C) Quantity;
(D) Price;
(E) Time of delivery or availability;
(F) Location of the construction project;
(G) Name and address of the proposed supplier; and
(H) A detailed justification of the reason for use of foreign construction materials cited in accordance with paragraph (b)(3) of this clause.
(ii) A request based on unreasonable cost shall include a reasonable survey of the market and a completed price comparison table in the format in paragraph (d) of this clause.
(iii) The price of construction material shall include all delivery costs to the construction site and any applicable duty (whether or not a duty-free certificate may be issued).
(iv) Any Contractor request for a determination submitted after contract award shall explain why the Contractor could not reasonably foresee the need for such determination and could not have requested the determination before contract award. If the Contractor does not submit a satisfactory explanation, the Contracting Officer need not make a determination.
(2) If the Government determines after contract award that an exception to the Buy American statute applies and the Contracting Officer and the Contractor negotiate adequate consideration, the Contracting Officer will modify the contract to allow use of the foreign construction material. However, when the basis for the exception is the unreasonable price of a domestic construction material, adequate consideration is not less than the differential established in paragraph (b)(3)(i) of this clause.
(3) Unless the Government determines that an exception to the Buy American statute applies, use of foreign construction material is noncompliant with the Buy American statute.
(d) Data. To permit evaluation of requests under paragraph (c) of this clause based on unreasonable cost, the Contractor shall include the following information and any applicable supporting data based on the survey of suppliers:
Foreign and Domestic Construction Materials Price Comparison Construction material description Unit of measure Quantity Price (dollars) \1\ Item 1 Foreign construction material.... ........... N/A........ ....... ……….N/A................ ........ N/A Domestic construction material... ........ N/A ............... ............ N/A .................. .... N/A Item 2 Foreign construction material.... ........... N/A........ ....... ……….N/A................ ........ N/A
Include all delivery costs to the construction site and any applicable duty (whether or not a duty-free entry certificate is issued).
List name, address, telephone number, and contact for suppliers surveyed. Attach copy of response; if oral, attach summary.
Include other applicable supporting information.
52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier's check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds, (1) to unsuccessful bidders as soon as practicable after the opening of bids, and (2) to the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.-
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $3M, whichever is less.-
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.-
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of provision)
52.252-2 CLAUSES INCORPORATED BY REFERENCE (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es):
http://farsite.hill.af.mil/vmfara.htm http://farsite.hill.af.mil/VFDFARA.HTM http://www.acq.osd.mil/dpap/dars/archive/2016/class_deviations.html
52.252-6 AUTHORIZED DEVIATIONS IN CLAUSES (APR 1984)
(a) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the date of the clause.
(b) The use in this solicitation or contract of any Federal Acquisition Regulation (48 CFR Chapter 1) clause with an authorized deviation is indicated by the addition of "(DEVIATION)" after the name of the regulation.
52.253-1 COMPUTER GENERATED FORMS (JAN 1991)
(a) Any data required to be submitted on a Standard or Optional Form prescribed by the Federal Acquisition Regulation (FAR) may be submitted on a computer generated version of the form, provided there is no change to the name, content, or sequence of the data elements on the form, and provided the form carries the Standard or Optional Form number and edition date.
(b) Unless prohibited by agency regulations, any data required to be submitted on an agency unique form prescribed by an agency supplement to the FAR may be submitted on a computer generated version of the form provided there is no change to the name, content, or sequence of the data elements on the form and provided the form carries the agency form number and edition date.
(c) If the Contractor submits a computer generated version of a form that is different than the required form, then the rights and obligations of the parties will be determined based on the content of the required form.
252.219-7010 NOTIFICATION OF COMPETITION LIMITED TO ELIGIBLE 8(A) CONCERNS--
PARTNERSHIP AGREEMENT (MAR 2016)
(a) Offers are solicited only from small business concerns expressly certified by the Small Business Administration (SBA) for participation in the SBA's 8(a) Program and which meet the following criteria at the time of submission of offer:
(1) The Offeror is in conformance with the 8(a) support limitation set forth in its approved business plan.
(2) The Offeror is in conformance with the Business Activity Targets set forth in its approved business plan or any remedial action directed by the SBA.
(3) If the competition is to be limited to 8(a) concerns within one or more specific SBA regions or districts, then the offeror's approved business plan is on the file and serviced by ____.
[Contracting Officer completes by inserting the appropriate SBA District and/or Regional Office(s) as identified by the SBA.]
(b) By submission of its offer, the Offeror represents that it meets all of the criteria set forth in paragraph (a) of this clause.
(c) Any award resulting from this solicitation will be made directly by the Contracting Officer to the successful 8(a) offeror selected through the evaluation criteria set forth in this solicitation.
(d)(1) Agreement. A small business concern submitting an offer in its own name shall furnish, in performing the contract, only end items manufactured or produced by small business concerns in the United States or its outlying areas, unless--
(i) The SBA has determined that there are no small business manufacturers or processors in the Federal market place in accordance with FAR 19.502-2(c);
(ii) The acquisition is processed under simplified acquisition procedures and the total amount of this contract does not exceed $25,000, in which case a small business concern may furnish the product of any domestic firm; or
(iii) The acquisition is a construction or service contract.
(2) The ____ [insert name of SBA's contractor] will notify the ____ [insert name of contracting agency] Contracting Officer in writing immediately upon entering an agreement (either oral or written) to transfer all or part of its stock or other ownership interest to any other party.
252.223-7001 HAZARD WARNING LABELS (DEC 1991)
(a) "Hazardous material," as used in this clause, is defined in the Hazardous Material Identification and Material Safety Data clause of this contract.
(b) The Contractor shall label the item package (unit container) of any hazardous material to be delivered under this contract in accordance with the Hazard Communication Standard (29 CFR 1910.1200 et seq). The Standard requires that the hazard warning label conform to the requirements of the standard unless the material is otherwise subject to the labeling requirements of one of the following statutes:
(1) Federal Insecticide, Fungicide and Rodenticide Act;
(2) Federal Food, Drug and Cosmetics Act;
(3) Consumer Product Safety Act;
(4) Federal Hazardous Substances Act; or
(5) Federal Alcohol Administration Act.
(c) The Offeror shall list which hazardous material listed in the Hazardous Material Identification and Material Safety Data clause of this contract will be labeled in accordance with one of the Acts in paragraphs (b)(1) through
(5) of this clause instead of the Hazard Communication Standard. Any hazardous material not listed will be interpreted to mean that a label is required in accordance with the Hazard Communication Standard.
| MATERIAL (If None, Insert "None.") | ACT |
| __________________________________ | _____________________________ |
| __________________________________ | _____________________________ |
(d) The apparently successful Offeror agrees to submit, before award, a copy of the hazard warning label for all hazardous materials not listed in paragraph (c) of this clause. The Offeror shall submit the label with the Material Safety Data Sheet being furnished under the Hazardous Material Identification and Material Safety Data clause of this contract.
(e) The Contractor shall also comply with MIL-STD-129, Marking for Shipment and Storage (including revisions adopted during the term of this contract).
252.223-7008 Prohibition of Hexavalent Chromium (JUN 2013)
Homogeneous material means a material that cannot be mechanically disjointed into different materials and is of uniform composition throughout.
(1) Examples of homogeneous materials include individual types of plastics, ceramics, glass, metals, alloys, paper, board, resins, and surface coatings.
(2) Homogeneous material does not include conversion coatings that chemically modify the substrate.
Mechanically disjointed means that the materials can, in principle, be separated by mechanical actions such as unscrewing, cutting, crushing, grinding, and abrasive processes.
(b) Prohibition.
(1) Unless otherwise specified by the Contracting Officer, the Contractor shall not provide any deliverable or construction material under this contract that--
(i) Contains hexavalent chromium in a concentration greater than 0.1 percent by weight in any homogenous material; or
(ii) Requires the removal or reapplication of hexavalent chromium materials during subsequent sustainment phases of the deliverable or construction material.
(2) This prohibition does not apply to hexavalent chromium produced as a by-product of manufacturing processes.
(c) If authorization for incorporation of hexavalent chromium in a deliverable or construction material is required, the Contractor shall submit a request to the Contracting Officer.
(d) Subcontracts. The Contractor shall include the substance of this clause, including this paragraph (d), in all subcontracts, including subcontracts for commercial items, that are for supplies,maintenance and repair services, or construction materials.
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Reference Drawing Index in sheet G-001, Attachment 2, Section J.
5352.201-9101 Ombudsman
As prescribed in 5301.9103, insert the following clause:
OMBUDSMAN (APR 2014)
(a) An ombudsman has been appointed to hear and facilitate the resolution of concerns from offerors, potential offerors, and others for this acquisition. When requested, the ombudsman will maintain strict confidentiality as to the source of the concern. The existence of the ombudsman does not affect the authority of the program manager, contracting officer, or source selection official. Further, the ombudsman does not participate in the evaluation of proposals, the source selection process, or the adjudication of protests or formal contract disputes. The ombudsman may refer the interested party to another official who can resolve the concern.
(b) Before consulting with an ombudsman, interested parties must first address their concerns, issues, disagreements, and/or recommendations to the contracting officer for resolution. Consulting an ombudsman does not alter or postpone the timelines for any other processes (e.g., agency level bid protests, GAO bid protests, requests for debriefings, employee-employer actions, contests of OMB Circular A-76 competition performance decisions).
(c) If resolution cannot be made by the contracting officer, the interested party may contact the ombudsman, AFICA/KS, 150 Vandenberg St, STE 1105, Peterson AFB, CO 80914, phone 719-554-5300, Fax 719-554-5299, email afica.ks.wf@us.af.mil. Concerns, issues, disagreements, and recommendations that cannot be resolved at the Center/MAJCOM/DRU/HQ AFICA/AFISRA/SMC ombudsman level, may be brought by the interested party for further consideration to the Air Force ombudsman, Associate Deputy Assistant Secretary (ADAS) (Contracting), SAF/AQC, 1060 Air Force Pentagon, Washington DC 20330-1060, phone number (571) 256-2395, facsimile number (571) 256-2431.
(d) The ombudsman has no authority to render a decision that binds the agency.
(e) Do not contact the ombudsman to request copies of the solicitation, verify offer due date, or clarify technical requirements. Such inquiries shall be directed to the Contracting Officer.
5352.223-9000 Elimination of Use of Class I Ozone Depleting Substances (ODS)
As prescribed in 5323.804-90, insert the following clause in solicitations and contracts:
ELIMINATION OF USE OF CLASS I OZONE DEPLETING SUBSTANCES (ODS) (NOV 2012)
(a) Contractors shall not:
(1) Provide any service or product with any specification, standard, drawing, or other document that requires the use of a Class I ODS in the test, operation, or maintenance of any system, subsystem, item, component, or process; or
(2) Provide any specification, standard, drawing, or other document that establishes a test, operation, or maintenance requirement that can only be met by use of a Class I ODS as part of this contract/order.
[Note: This prohibition does not apply to manufacturing.]
(b) For the purposes of Air Force policy, the following products that are pure (i.e., they meet the relevant product specification identified in AFI 32-7086) are Class I ODSs:
(1) Halons: 1011, 1202, 1211, 1301, and 2402;
(2) Chlorofluorocarbons (CFCs): CFC-11, CFC-12, CFC-13, CFC-111, CFC-112, CFC-113, CFC-114, CFC-115, CFC-211, CFC-212, CFC-213, CFC-214, CFC-215, CFC-216, and CFC-217, and the blends R-500, R-501, R-502, and R-503; and
(3) Carbon Tetrachloride, Methyl Chloroform, and Methyl Bromide.
[NOTE: Material that uses one or more of these Class I ODSs as minor constituents do not meet the Air Force definition of a Class I ODS.]
5352.242-9000 Contractor Access to Air Force Installations As prescribed in 5342.490-1, insert a clause substantially the same as the following clause in solicitations and contracts:
CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS (NOV 2012)
(a) The contractor shall obtain base identification and vehicle passes, if required, for all contractor personnel who make frequent visits to or perform work on the Air Force installation(s) cited in the contract. Contractor personnel are required to wear or prominently display installation identification badges or contractor-furnished, contractor identification badges while visiting or performing work on the installation.
(b) The contractor shall submit a written request on company letterhead to the contracting officer listing the following: contract number, location of work site, start and stop dates, and names of employees and subcontractor employees needing access to the base. The letter will also specify the individual(s) authorized to sign for a request for base identification credentials or vehicle passes. The contracting officer will endorse the request and forward it to the issuing base pass and registration office or Security Forces for processing. When reporting to the registration office, the authorized contractor individual(s) should provide a valid driver’s license, current vehicle registration, valid vehicle insurance certificate, and [insert any additional requirements to comply with local security procedures] to obtain a vehicle pass.
(c) During performance of the contract, the contractor shall be responsible for obtaining required identification for newly assigned personnel and for prompt return of credentials and vehicle passes for any employee who no longer requires access to the work site.
(d) When work under this contract requires unescorted entry to controlled or restricted areas, the contractor shall comply with [insert any additional requirements to comply with AFI 31-101, Integrated Defense, and AFI 31-501, Personnel Security Program Management] citing the appropriate paragraphs as applicable.
(e) Upon completion or termination of the contract or expiration of the identification passes, the prime contractor shall ensure that all base identification passes issued to employees and subcontractor employees are returned to the issuing office.
(f) Failure to comply with these requirements may result in withholding of final payment.
(End of clause)
CONTRACTOR ACCESS TO AIR FORCE INSTALLATIONS – ADDITIONAL REQUIREMENTS
(a) Contractors must have an approved request letter on file at Security Forces with employees name and the required data.
(b) Subcontracts: The contractor shall include this Special Contract Requirement in subcontracts of any tier.
(c) Unescorted Access to Installations:
(1) To request access to Cape Canaveral AFS, prior to their proposed business or contract requirements, all contractor personnel shall provide a current completed “CCAFS Badging Request Form”.
(2) Contractor personnel must complete and sign the applicable form cited above before the required background check (see d. and e. below) can be performed.
(d) All personnel entering Patrick AFB and Cape Canaveral AFS must provide two forms of identification (one must be a photo ID) as required by AFI 10-245, and have a background check.
(1) For unescorted entry into non-restricted areas of the installations, personnel must obtain, from AF security personnel, favorable National Criminal Information Center (NCIC) check, and have complete social security employment verifications prior to being issued badges (to include temporary passes.
(2) Prior to being issued restricted area badges for unescorted entry into restricted areas of the installations, U.S. citizens working as contractor employees must obtain a favorable National Agency Check (NAC).
(3) All required information shall be provided to support background checks, and citizenship verification (i.e., birth certificate, passport, voter registration card, resident alien card, or certificate of naturalization).
(e) Escorted Access-Temporary Passes: Personnel may receive a temporary pass, Air Force Form 75/Visitor and Vehicle Pass, for no more than 30 total days in one 365 day period. This pass is issued without a criminal background check, but requires a Wants & Warrants check. Persons with temporary passes receive escorted access rights only, i. e.; they must be escorted at all times by an escort official. Escorted personnel must be with their escort official (the escort official must be in plain view) at all times while on the installation.
(f) Personnel Background Checks
(1) The 45th Security Forces will conduct the background check at no cost to the applicant. Refusal to submit to the background check will result in denial of access. Applicants shall be denied installation access based on an arrest record including, but not limited to the following crimes:
(i) Murder
(ii) Manslaughter
(iii) Rape
(iv) Aggravated Assault
(v) Burglary
(vi) Arson
(vii) Other forms of Sexual Assaults (lewd, malicious acts to a child, etc.)
(viii) Any other felony
(ix) Outstanding warrants
(x) Misdemeanor convictions less that 5-year involving moral turpitude offenses (theft, worthless checks, etc.)
(xi) FBI Terrorist Watch List
(2) Individuals who do not meet the criteria for unescorted base access may still be granted escorted access on a case-by-case basis. The determination will be made based on the results of the background investigation, totality of the criminal record and the types of crime reported.
(3) Individuals may appeal denial of escorted/unescorted installation access through the Security Forces.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .