FA2521‐17‐B‐0001
Answers to Questions Received #44‐62
20 Apr 17
44. SOW/Technical Specification/Drawings paragraph/page Drawing G-003 Note 15
Please identify the facilities that will require the use of generator(s) during outages. What is the load/generator size requirements for these facilities?
Answer: Size generator based on size of transformer. Provide generator for AWS and CX 13.
45. SOW/Technical Specification/Drawings paragraph/page Specification Section 01 11 00.00 30 Page 8 Section 1.9
The GFE material referenced in this section does not appear to be part of this project. Please identify what this material is to be used for?
Answer: Specs are not accurate there is no GFE.
46. SOW/Technical Specification/Drawings paragraph/page Drawing EC-110 Flag Note 1
This note indicates concrete-encased horizontal directional drill. Should this read “horizontal directional drill”? We are not familiar with “concrete-encased” horizontal directional drill.
Answer: Directional Bore does not require concrete encasement
47. SOW/Technical Specification/Drawings paragraph/page Drawing EC-109 Flag Note 2
Load Break Switch 3N12 position 4 indicates spare. Should this position be used for CX-13/LZ-1 XFMR 112.5kva?
Answer: Refeed LZ-1(CX13) from switch 3N12/4
48. SOW/Technical Specification/Drawings paragraph/page Drawing EC-111 Flag Note 1
This note indicates a splice in MH-305. Should this read HH-XX? Also, should the conduit & feeder schedule 26 read the same?
Answer: Yes, MH-305 should be HH-XX.
49. SOW/Technical Specification/Drawings paragraph/page EC Drawings General Note 1
This note indicates contractor shall procure MV cable in standard spool lengths. Remaining cable is to be turned over to the Base Maintenance Contractor. Spool lengths are customized to fit the need of each cable run. In addition, each cable manufacture could have different minimum/maximum spool lengths. What is the intent of this note? Does the Government have a minimum length of cable they would like for us to turn over?
Answer: We have had issues in the past with MV concentric neutral cable usually comes in 10,000 LF reels. The purpose of this note is if contractor has to purchase more cable then required for project then access will be turned over the Government. If contractor can purchase just enough cable for the project this would be optimal.
50. SOW/Technical Specification/Drawings paragraph/page Drawing EC-107
Drawing Indicates two road cuts & patch. One at ICBM Road & one at Heavy Launch Road.
Due to the traffic on these roads, is directional bore an acceptable method?
Answer: Yes, directional bore is an acceptable method.
51. FedBizOpps Website Notice Details
20 Apr 17
The website references 80 non-access days to be included in the 740 calendar days of the performance period. This information was only located on the website, we have not found this in the actual IFB. In addition, with the very aggressive launch schedule at CCAFS, FL we have previously experienced extensive no excavation, no manhole access, equipment fall back requirements, no switching for outages as well as non-access days. We feel 80 non-access is insufficient for this scope of work. Please confirm 80 non-access days.
Answer: 80 non-access days are estimated for this project.
52. Drawings – Drawings Sheets E-601; E-602; E-603; & E-604___________
Question: The general note on Drawing Sheets E-6-1; E-602; E-603; and E-604 state “This drawing assumes projects DBEH 07-1550 (Repair P-Line North and SS#3) and DBEH 10-1589 (Repair C-Line) are complete.” Are these projects completed and if not, is there an anticipated completion date?
Answer: Yes these projects are complete
53. Other (Specify) Non-Access; No Dig Days___________________________
Question: The solicitation does not state how may non-access; no dig days are included within the 740 day period of performance. Please clarify the number of non-access/no-dig days that the government will be including in the 740 day period of performance.
Answer: 80 non-Access Days, 540 Working Days and 120 days of Material lead time
54. Technical Specification Section 01 11 00.00 30 Page 12 Part 3 Paragraph 3.1.1 and 3.1.2__
Question: The specifications state that the work to be performed under contract is located within a restricted area. Will the government be providing escorts or can the government provide the required forms to be completed for contractor “Unescorted Entry Authorization Certificate?”
Answer: the only requirement is a CCAFS access badge. Badge request form is solicitation Attachment #7.
55. SOW/Technical Specification/Drawings paragraph/page EC-109 and EC-112___________ Other (Specify) GN2 Nitrogen Lines___________________________
Question: Are the nitrogen lines that are shown on drawings EC-109 and EC-112 active? Are we able to directionally bore under them and if so, what is the required clearance under them?
Answer: GN2 is active. GN2 is 3 foot below grade expect to go a minimum of 5 foot below grade if directional boring. If trenching, hand ding around GN2 line. Concrete ductbank to be minimum of 12in from GN2 line.
56. Other (Specify) Concrete Encased Horizontal Drill Ductbank___________________________
Question: Can the government please provide additional clarification on requirements in spec section 33.71.02 paragraph 1.5.2 (page 7), for the concrete encased horizontal drill ductbank? Is the government’s intent to completely encase the full length of any newly installed directionally bored ductbank?
Answer: Directional Bore does not require concrete encasement.
20 Apr 17
57. SOW/Technical Specification/Drawings paragraph/page _Section 01 11 00.00 30, Paragraph 1.9 (GFE) ________
Question: _Specification indicates the 56 each Siemens Hub RS-485, 8 each Siemens Modem Blocks, and 10 each Siemens Part Hub-4 will be provided as GFE. What is the purpose of these items?
Answer: Specs are not accurate there is no GFE.
58.
SOW/Technical Specification/Drawings paragraph/page _01 57 19 Section 3.11 & ED-108 General Note 3__________
Question: Are the PCB-contaminated potheads removed from Poles G34, G38 and G39 required to be disposed of off-site or turned over to the Government?
Answer: Turn potheads over to government. Contractor to palletize and distribute.
59.
SOW/Technical Specification/Drawings paragraph/page _ED-104 Flag Note 8 & 01 11 00.00 30 Paragraph
1.11.3 (Salvage of Material & Equipment)__________
Question: Are the recloser, cables and controls to be removed from Pole G87IR in reusable condition to be turned over to the Government?_ Answer: Yes.
60.
SOW/Technical Specification/Drawings paragraph/page _G-003 General Note 16, ED-108 Flag Note 4 & 01 11
00.00 30 Paragraph 1.11.3 (Salvage of Material & Equipment)__________
Question: Is the pole-mounted transformer removed from Pole G33 to be turned over to the Government?
Answer: Test pole mounted transformers for PCB if PCBs are detected over action level turn over to the Government if PCBs are not detected contractor to recycle properly.
61. RFP Section ___L_______ Paragraph __4.e_______
Question: What is the format for the CECC Form 3052(s) required? Does the Government want a single CECC Form 3052 for each CLIN and a 4th CECC Form 3052 with the aggregate price or a single 3052 with all CLINs shown? If we are providing 4 CECC Form 3052s, should the 4th be a single line for each CLIN or a compilation of the other CECC Form 3052s?
Answer: Provide a single CECC Form 3052 (or equivalent) cost breakdown for each CLIN. Also provide an aggregate total (sum of all CLINs) on a separate CECC Form 3052 (or equivalent) using a single line for each CLIN.
62. RFP Section ___A_______ Paragraph __13.A_______ Other (Specify) _RFP Section L-4 & L-5__________________________
Question: It was stated during the walkthrough that the bids are due and the bid opening is on Monday, 24 April 2017. The RFP states that bids are due and the bid opening is on Tuesday, 25 April 2017. Please confirm date & time for the bids to be due and for the bid opening.
Answer: Bids are due not later than Tuesday, 25 April 2017 at 0900 EDT. The public bid opening will be held two hours later that same day (1100 EDT).