FA2521‐17‐B‐0001
Answers to Questions Received #1‐43
19 Apr 17
1. SOW/Technical Specification/Drawings paragraph/page _Spec 32 92 23 and Dwg E506___
Question: _What are the requirements for site restoration for the areas where duct bank is being installed and where poles are being removed? Specifications are provided for sod only.
Answer: Bring site back to original condition with either sod or seed. Grass needs to be established before government will accept.
2. SOW/Technical Specification/Drawings paragraph/page _ED 101 Flag Note 2_________
Question: Drawing ED101 indicates that the line being removed by Flag Note 2 is underground electric. Flag Note 2 indicates that this is overhead electric. Please clarify.
Answer: Section of Flag Not 2 is underground. Circuit transitions from overhead to underground at pole 37-55A
3. Item # 1 Repair F line
SOW states The duct bank will be placed between existing Manholes 211 and 212. Drawing EC- 103 shows going to MH2314
SOW states “Pull cable from switch 3N5 to 3N7 to transformer CX32I1. Drawings seem to indicate transformer CX34I1
Answer: Ductbank between MH 2314 and MH 212. Pull cable from existing switch 3N5 and new switch 3N7 to transformer CX34I1. Also picking up transformer MOTR as per design drawings. CX32I1 should read CX34I1
4. Item # 2 Repair J line
SOW says to (Pull new 4/0 cable from existing switch 3N6 through manhole 2314 to existing switch
CC617 and through existing manhole 2474. Drawings seem to indicate existing switch CCCG17.
Routing is unclear from MH2474 to MH2475, however the cost will be similar between the east or west duct banks 10W6, assuming there is a spare conduit in either.
Answer: pick up CCCG17 by splicing into MH 438 on the corner of Central Control Rd and ICBM road.
5. Item # 3 Radiographic Tests
SECTION 26 05 13.00
Perform and submit radiographic tests on all splices/terminations at the discretion of the Contracting Officer to determine if voids exist. Rework unacceptable cable, splices or terminations at no additional expense to the Government.
Need clarification. X-Ray testing is quite expensive. High-pot testing determines the acceptability of failure of splices and terminations, and is also required. What is meant by “at the discretion of the contracting officer?”
Answer: Use very low frequency (VLF) Testing. X-ray testing is not required.
6. Item # 4 Excavations
SECTION 01 11 00.00 30
19 Apr 17
3.5.2 Restrictions
All excavation at the work site must be accomplished by hand only.
Excavating machinery is prohibited.
Hand digging is required within five feet of located underground utilities.
Need confirmation that all excavation is by hand – no backhoe or other machinery?
Answer: Machinery is acceptable to use. Hand dig within five feet of located underground utilities.
7. Item #5 Pole Heights
Of the poles that are to be removed, what is the length of the concrete poles? What is the length of the wood poles?
Answer: Concrete poles are 60 feet. Wood poles are 50 feet.
8. Item #6 Contaminated Soils
Can any of the contaminated soil be reused? If yes, is there a location on base where any excess soils can be delivered? Is there a location on base from which we can “borrow” fill dirt? If yes, what is the approximate distance between the work area and the spoils/borrow site?
If contaminated soils cannot be used, what is the disposal protocol?
Answer: reuse all soil no soil needs to be disposed of off base. There are locations on base to borrow fill dirt but we cannot guarantee they will be available at the time of construction. Contractor should bid accordingly.
9. Item #7 Copper Credit
01 11 00.00 30 1.2.1
Contractors bid shall clearly indicate amount of credit being provided for copper conductors being removed from this project.
Are all overhead conductors being removed, including static lines, hard-drawn copper?
Are all underground conductors being removed soft-drawn copper?
Answer: Static line is hard-drawn copper. J-line (second line on ICBM road) is Paper and aluminum conductor cable. The rest is a combination of hard-drawn and soft-drawn copper. Include the amount of credit being provided (if any) in your CECC Form 3052 (or equivalent) cost estimate breakdown (Reference solicitation Section L). Any credit should also be reflected in your bid amount. Evaluation of Bids and Basis of Award will be as stated in Section M.
10. RFP Section _Missing__DRAWINGS_______ Paragraph _________
Question: _We do not find drawings that show “Stormwater Pollution Prevention Plan Notes”, will these be provided since they provide site specific information for a SWPPP plan?
Answer: Yes, See attached SWPPP information sheet. (Incorporated as Attachment 11 in the solicitation)
11. Question: Have environmental survey’s been completed for the existing manholes and PILC cable and will they be provided?
19 Apr 17
Answer: No, PILC Cable will need to be properly recycled.
12. Question: Geological survey of ground water SWPPP?
Answer: All know plumes are indicated on drawings. All manholes installed in a known plumes that need to be dewatered; will be dewatered with a proper infiltration gallery.
13. RFP Section _Section L and IFB SF 1442 para 13_________ Paragraph _________
Question: Please clarify how submission of bid is to be done. Section L indicates Electronic bids only and SF 1442, “Para 13 Additional Solicitation Requirements” requires 2 sealed copies be submitted.
Answer: Only electronic bids will be accepted. Reference Section L. SF 1442, block 13.A. has been changed to read 0 additional copies are required.
14. RFP Section __F ______ Paragraph __”Deliveries and Performance”_______ SOW/Technical Specification/Drawings paragraph/page __5 of 38_________
Question: Deliveries and Performance paragraph missing? Neither the IFB nor the specifications state the number of no-dig/non-access days in which will occur during the 740-day period of performance. With our history of projects containing a period of performance such as this one the no-dig/non-access days can very easily exceed 150 days. After your review please advise accordingly.
Answer: Estimated 80 non-Access Days 540 Working Days 120 days of Material lead time This information was provided via Amendment 0001 issued 18 Apr 17.
15. Other (Specify) General Question
Question: J Line Demo, the existing cable that is to be removed appears to be the oil-filled type.
If this is true is this cable considered toxic or hazardous? And if so do we dispose of it or is it required to stay on site?
Answer: cable is not considered toxic or hazardous. Cable will be cut up and ends properly sealed. Cable to be recycled properly by contractor.
16. RFP Section Drwg ED-104 - 111 Paragraph _N/A_
Question: _We are unsure of the symbol designation of the following, can you explain?
Answer: The symbols are pole anchors.
19 Apr 17
17. SOW/Technical Specification/Drawings paragraph/page Drwg. Multiple Notes
Question: _Within the drawings there are multiple notes stating “Groundwater Plume is known to contain Chlorinated solvents” Are the exact type of contaminates known for hazmat training and PPE requirements?
Answer: The SLC-16 groundwater plume (in the area along ICBM Rd) includes both vinyl chloride (VC) and cis-1, 2-dichloroethene (DCE) at concentrations above regulatory cleanup levels. This is based on several DPT locations and monitoring wells that have been sampled near the roadway. Exceedances have been observed in several depth intervals in this area, to include as shallow as 5-10 ft bls.
The LC34 groundwater plume (in the area along Freedom Rd) includes Trichlorethene (TCE), cis- 1,2-dichloroethene (DCE), and vinyl chloride (VC) at concentrations above regulatory cleanup levels.
This is based on numerous DPT locations and monitoring wells that have been sampled near the roadway. Exceedances of groundwater criteria begin at the water table and continue to a depth of 38 feet below land surface in the area.
18. SOW/Technical Specification/Drawings paragraph/page _EC-110 Flag Note 1_________
Question: _EC-110 Flag Note 1 specifies a “concrete-encased horizontal directional drill 4W5 ductbank” approximately 375 ft long to be installed under an area of standing water. Please clarify that this is actually supposed to be concrete encased. If so, please provide a detail of the concrete-encased HDD duct bank.
Answer: Directional Bore does not require concrete encasement
19. SOW/Technical Specification/Drawings paragraph/page _01 57 19 Section 3.11 & G-003 General Note 9__
Question: G-003 General Note 9 specifies the excess and surface blowout drilling fluids shall be collected and disposed off-site. Throughout the drawings, it is noted that, “groundwater plume is known to contain chlorinated solvents” and certain areas are, “known to contain soils with PCB above residential soil cleanup target levels.” Will the Government require analytical for characterization of all excess surface blowout drilling fluids to be disposed of? If so, will the Government be providing the analytical service or should the contractor include this service in his estimate?
Answer: In plume areas containerize blowout drilling fluids and have it tested to determine the appropriate disposal methods. Cost should be in contractor’s proposal. If it's hot, our environmental group will dispose of. If not Contractor will have to dispose of.
20. SOW/Technical Specification/Drawings paragraph/page _01 57 19 Section 3.11 __________
Question: If analytical of the excess surface blowout drilling fluids to be disposed determines these to be hazardous waste (i.e. elevated levels of PCB or chlorinated solvents), is this required to be disposed of off-site or turned over to the Government?
Answer: Turned over to Government
20. RFP Section 33 71 02 Paragraph 3.5
Question: This paragraph says to route cables along walls providing the longest route & maximum spare cable lengths. Is a full wrap inside the manholes not necessary?
19 Apr 17
Answer: Full wrap inside manhole on circuits where cables are spliced. Any circuits that will not be spliced will be routed along longest route entering and leaving manhole.
21. RFP Section 26 13 19 .01 Paragraph 2.5
Question: Just so we are on the same page, this paragraph says cabinets shall be equipped with mounting plates that allow installation of industry standard dead-front three- or four-way junction modules and elbows conforming to IEEE 386. Most applications in this project do not need that many modules. Is it allowable to just install the modules as needed on the full size mounting plate?
Answer: Minimum of three junction modules per cabinet.
22. Spec Section 26 05 13.00 98 Paragraph 1.4.1 page 5
Question:
We have noticed the trend at Patrick/CCAFS and other Government installations is for the medium voltage cable splicer's to hold a current, cable splicer certification from the (NCSCB) National Cable Splicing Certification Board, to assure the most qualified installers are performing terminations and splices. Will this requirement be imposed on this project?
Answer: No. Splicer must have certifications issued by splice manufacturer.
23. Drawing G-003 General Notes 15 CONTRACTOR SHALL SUPPLY, CONNECT, OPERATE, FUEL, AND
MAINTAIN TEMPORARY ELECTRICAL GENERATORS FOR THE DURATION OF ELECTRICAL
OUTAGE. THE GENERATORS SHALL BE SIZED TO MAINTAIN FULL FACILITY FUNCTION
WITHOUT VOLTAGE SAG.
Question:
In order to price this we need to have a list of each facility and generator size required to maintain full facility function. Will the government provide this list so we can provide the price of this requirement?
Answer: Size generator based on size of transformer. Provide generator for AWS and CX 13.
24. Drawing G-004 Electric Manhole - new precast conc. 10'x10'x10' and E-505 8'x8' concrete manhole details
Question:
What size should the manhole be?
Answer: 8’X8’
25. RFP Section B - Supplies or Services and Prices
Question:
Should the work shown on the drawings for 37-line be included in this CLIN?
Answer: demolition of 37-Line is part of the first CLIN.
26. Question:
Should the duct bank size be 4W5 or 2W4 as shown on the drawings?
Answer: Per drawings.
19 Apr 17
27. Question:
Where is transformer CX32I1?
Answer: Transformer CX32I1 should read CX34I1
28. Question:
The drawing does not show the new duct bank going to MH211. Should it?
Answer: New ductbank for CLIN 1 is from MH212 to MH 2313
29. Spec Section 01 11 00.00 30 98 Paragraph 1.2.1 page 3
Question:
It appears that the government tested for asbestos fibers in the existing manholes and none was found. This spec section states to test if Orangeburg is encountered. Since the tests have been done is this required? If it is required, who many tests should we include in our price?
Answer: Testing for asbestos was on concrete only not Orangeburg. Test in MH 212, MH 2314 and MH
100. One test per manhole.
30. SOW/Technical Specification/Drawings paragraph/page _Drawing G-003__________
Question: _Drawing indicates “90% DESIGN REVIEW ONLY NOT FOR CONSTRUCTION” please advise if new drawing will be issued. Also drawing Note 16, indicates spec section 01 57 20.00 10, we do not find in documents.
Answer: drawings are 100% no new drawings will be issued. Spec section should be 01 57 19.
31. SOW/Technical Specification/Drawings paragraph/page __Drwg EC-101_________
Question: Please confirm the existing 12W5 from MH212 to MH100 is Orangeburg duct or not.
Also has there been any recent survey regarding Asbestos within.
Answer: Yes it is orangeburg. Needs to be tested for asbestos.
32. RFP Section __Clin 1________ Paragraph _________
Question: Clin 1, 3rd sentence indicates “ductbank will be placed between existing MH211 and MH212”. Please advise location of exiting MH211?
Answer: Manhole number should be MH 2314
33. Other (Specify) ____Existing condition_______________________
Question: Existing LZ-1 circuit is currently fed via LBS BMG9/3, please provide more information on where this circuit is to be re-configured.Answer: Refeed LZ-1(CX13) from switch 3N12/4.
Answer: Refeed LZ-1(CX13) from switch 3N12/4.
34. Other (Specify) __Wage determination_________________________
Question: Under the DBW determination , please clarify the proper cost code utilized for a 15 KV cable splicer.
Answer: Journeymen with electrician license.
19 Apr 17
35. SOW/Technical Specification/Drawings paragraph/page _Spec 26 13 19.01 2.5__________
Question: Please confirm what Junctions are required in each of the Sectionalizing Cabinets.
Spec section 26 13 19.01 2.5 calls out either three or four point junctions. Cannot locate a detail to show which to use. Should they all be assumed to be 4 way? In all cases they appear to be for inline feeders; so assume all would be 600A? Bushing height shows to be 24 inches, is this correct?
Answer: minimum of three junction modules per cabinet all 600A. 24 inches is correct.
36. Question: _When removing the “J” line conductor, does the messenger and the clips that hold the conductor on to the messenger have to be removed separately, or can the messenger and the 3 conductor cable be rolled up together?
Answer: Contractor will need to demolish cable safely and in a manner to be properly recycled by contractor. PAC cable should be sealed so oil does not leak out. Best way to do this is up to contractor.
37. RFP Section __B________ Paragraph _Item 0002 & 0003________
Question: _Shall sectionalizers for the G & J replacement line be included with Bid Item 0002 (i.e. duct bank) or Bid Item 0003 (i.e. electrical distribution)? __ Answer: Bid Item 0003
38. SOW/Technical Specification/Drawings paragraph/page _E508 & E509_________
Question: Is there a requirement for bollards associated with installation of new pad-mounted equipment (i.e. transformers, load break switches, & sectionalizers)? If so, could you provide a detail of this requirement?_____ Answer: No Bollards are required
39. On sheet ED-110, note #6 says to remove conductors from between LBS 3N13 to MH 1030 beneath section I . We find LBS 3N13 but not MH 1030 or section I. Can we please receive clarification?
Answer: Flag note 6 on page EC-110 is a typo and the entire flag note should be removed
40. The SF1442 states that the conctractor of subcontractor shall be licensed by the State of Florida or have equivalent out-of-state license in all applicable areas. Would a North Carolina electrical license be acceptable.
Answer: North Carolina Electrical license is considered equivalent to a Florida Electrical license
41. The RFP states that the project duration is based on five 8 hour work days.
Would the government consider allowing four 10 hour work days?
Answer: 10 hour days will be fine.
42. Sheet ED-110, Note 6: Remove (3) 1/C #4/0 EPR conductors installed under Section I between LBS 3N13/3 and MH1030.
Please clarify - LBS 3N13 is printed on the drawing with no accompanying
19 Apr 17 symbol. We have been unable to locate MH1030.
Answer is the Flag note 6 on page EC-110 is a typo and the entire flag note should be removed.
43. Also on ED-110, what appears to be an overhead line extends from Pole G11, diagonally toward Primary OH J-Line. The endpoint does not appear to terminate at a pole or manhole. What is the scope of work for this area?
Answer: The line coming off of G11 is the pole anchor. It is to be demolished with the pole. Cut anchor two foot below grade.