Attachment 5 - Site Visit Questions.docx

DOCX document 15 KB Posted

Attached to
FY24 SPACECOM JOC Furniture Federal contract opportunity
Solicitation number
FA251724Q0020
Issued by
Department of the Air Force Space Command

About this file

This document is the solicitation for the FY24 SPACECOM JOC Furniture contract. The solicitation is seeking quotes to provide office furniture for Room 1418 at Peterson Space Force Base in Colorado. The requirement is for a small business set-aside with a NAICS code of 337214 and size standard of 1,100 employees. Quotes will be evaluated according to FAR 52.212-2 and must comply with all instructions and addenda contained in the solicitation. The soliciting agency is the Department of the Air Force Space Command. The purpose is to furnish SPACECOM's Joint Operations Center with new furniture. Responses are due by the date listed on FEDBIZOPPS and award will be made to the responsible quoter whose quote conforms to the solicitation and is most advantageous to the government, price and other factors considered.

View the file

Other files for this federal contract opportunity

Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Site Visit Questions and Answers - #2

Will there be downtime for wall damage and prep?

· Yes. Please include a schedule submission, IAW the SOW.

Can the signs that are currently above the new visiting executive officer station be moved?

· Yes. Signs will be moved by the government.

How will contractors be able to access the area?

· Contractors must be escorted to access the area.

Will the government provide escorts?

· Yes. Government will provide escorts.

What kind of door can be used at the entrance to the workstations?

· The door shall be a sliding door NOT a swing door.

What is the timeline for the project?

· Depending on the number of days schedule, the project timing should be as follows:

· If 4 days, timing should be Thursday – Sunday

· If 5 days, project can either be Saturday to Wednesday or Wednesday to Sunday Would chairs be needed only at 4 stations or also for the other offices upfront?

· Chairs only needed at the 4 stations Please clarify the day and hours work is to be completed.

· Days answered in previous RFI. Baseline hours are 0730-1630, but can be extended upon request.

File details come from the government source that posted it. Updated .