Attachment 5 - JOC Site Visit Questions.docx
DOCX document 14 KB Posted
- Attached to
- FY24 SPACECOM JOC Furniture Federal contract opportunity
- Solicitation number
- FA251724Q0020
About this file
This document contains details of a federal contract solicitation for furniture. The solicitation is for SPACECOM JOC Furniture in Room 1418 on Peterson Space Force Base in Colorado. It is a small business set-aside under NAICS code 337214 with a size standard of 1,100 employees. Quotes will be evaluated according to FAR 52.212-2. Offerors must comply with all instructions and requirements in the solicitation and addenda. The purpose is to procure furniture for the SPACECOM Joint Operations Center. The Department of the Air Force Space Command is the contracting agency.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Attachment 2 - Atch 1 - Evans Furniture Layout - JOC Entrance new.pdf | ||
| Attachment 1 - Statement of Work - Bldg 1 New JOC Furniture (Entry) - Revised 27 Mar 24.docx | DOCX document | |
| Attachment 3 - Atch 2 - Additional requirements - Revised 27 Mar 24 new.pptx | PPTX presentation | |
| Amendment 3 Solicitation.pdf | ||
| Attachment 5 - Site Visit Questions.docx | DOCX document | |
| Amendment 2 JOC Combo Synopsis.pdf | ||
| JOC combo synopsis Amendment 1 (clauses remain from the original posting).docx | DOCX document | |
| Attachment 3 - Atch 3 - Additional requirements (not shown in drawings).pptx | PPTX presentation | |
| Attachment 1 - Statement of Work - Bldg 1 New JOC Furniture - Entry 1.docx | DOCX document | |
| JOC Solicitation Official pdf.pdf | ||
| Attachment 4 -Technical Information.docx | DOCX document | |
| Attachment 2- Atch 2 - 19-0301-308 Peterson AFB JOC - Drawings Rev C -.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Site Visit Questions and Answers - #1
Will there be downtime for wall damage and prep?
· Yes. Please include a schedule submission, IAW the SOW.
Can the signs that are currently above the new visiting executive officer station be moved?
· Yes. Signs will be moved by the government.
How will contractors be able to access the area?
· Contractors must be escorted to access the area.
Will the government provide escorts?
· Yes. Government will provide escorts.
What kind of door can be used at the entrance to the workstations?
· The door shall be a sliding door NOT a swing door.
What is the timeline for the project?
· Depending on the number of days schedule, the project timing should be as follows:
· If 4 days, timing should be Thursday – Sunday
· If 5 days, project can either be Saturday to Wednesday or Wednesday to Sunday