This document contains questions and answers regarding Solicitation Number FA2517-21-Q-0047 from the Department of the Air Force Space Command. The solicitation requires a contractor to engineer, furnish, install and test new duct-bank infrastructure and single mode fiber optic cable between multiple buildings in four distinct projects at Peterson Space Force Base. The expected period of performance is six months to complete all projects. The contractor must coordinate access to secure areas and any excavation or work impacting buildings with the 21st Contracting Squadron Project Manager in advance. Limited storage space will be available on-site, but vehicles and drilling equipment can be stored in the Cable Yard.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
UNITED STATES SPACE FORCE
PETERSON-SCHRIEVER GARRISON
03 September 2021
FROM: 21 CONS/PKB
SOLICITATION NUMBER: FA2517-21-Q-0047
SUBJECT: Questions and Answers for 21 CS OSP acquisition
# Questions Answers
Is the period of performance 6 months for each phase or 6 months total?
The expected period of performance is 6 months for completion of all projects.
Please ensure you check SAM.gov for any amendments to the RFQ.
Can draft a proposal for a path behind the treeline across from B1038 towards B1?
A change to the SOO with new drawing depicting path across B1038 to B1
Will all manholes remain 6’,7’,8’? Yes
Will there be on-site storage available? 21CS has little inside storage space, limiting to 2 to 3 pallets. Storing of vehicles, drilling equipment can be stored in Cable Yard.
How can access to secure areas be coordinated?
Contractor will coordinate with 21CS/SCX Project Manager at least 5 Calendar days ahead of time.
Will coordination be required for the path across the airfield towards 2025?
Contractor will coordinate with 21CS/SCX Project Manager at least 3 working days ahead of time.
Can the berm above room 1420 at B1 be removed for access to 1420?
Contractor will coordinate with 21CS/SCX Project Manager and Building 1 Facility Manager for approval prior to excavating.
For room 1420, will ducts have to enter through the floor or can they enter through the top or wall of 1420?
Contractor can scope out both, but will have to coordinate with 21CS/SCX and building 1 Facility Manager
Can a copy of the sign-in sheet be provided.
No.