One more Q&A. Also note the RFQ has been extended to 30 Aug, 3pm CDT.

View the file

Other files for this federal contract opportunity

Other files attached to Modular Furniture Demolition and Installation, newest first.
File Type Posted
Site_Visit_Sign-In_Sheet.pdf PDF
Attachments_for_Questions.pdf PDF
Answers_for_Site_Visit_Questions.docx DOCX document
F3YCBS9155A001_Combo.docx DOCX document
F3YCBS9155A001_Combo.docx DOCX document
F3YCBS9155A001_Combo.docx DOCX document
406_SCMS_GUEE_SOW_Systems_and_Modular_REV_6.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

48. I have not been able to find anything in the RFP regarding what type of electrical wiring system the workstations are to accommodate. In plain English, is the wire system infeed for the systems furniture “cubicle” to consist of a four (4) circuit, independent neutral, 10 wire system? This is the standard at Tinker but I have noticed some Manufacturers are bidding a 4 circuit, shared neutral, 8 wire system. If the 8 wire is provided it will not be in accordance with your base design standards. Any chance we can confirm this so all bidders understand the electrical requirement?

Must comply with Tinker Standard.