This document is a Statement of Objectives (SOO) for a turnkey synthetic turf solution for a K9 obedience area at Hill Air Force Base, covering 11,181 square feet. The key objectives include:
Installation Requirements: Install a flat, seamless synthetic turf surface with a 12-inch concrete border trim around the perimeter to maintain stability and prevent displacement. Coordinate with Hill AFB personnel to ensure proper leveling before installation.
Obstacle Management: Remove existing obstacles, temporarily dismantle the east fence if required, and rearrange obstacles back to their designated locations upon completion.
Quality Assurance: Conduct an initial evaluation to verify the turf is free from defects and address any issues promptly.
Warranty and Timeline: Provide warranty coverage for manufacturer and installation defects, and a project timeline not to exceed 120 days. Define payment terms and responsibilities between the contractor and Hill AFB.
The related federal contract opportunity has the Solicitation Number F2D0CM4170A001 and is being issued by the Department of the Air Force Materiel Command Air Force Sustainment Center.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Q and A.pdf | ||
| Attachment 1 Statement of Objectives (SOO) K9 Turf.pdf | ||
| Solicitation K9 Turf.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES (SOO)
Turnkey Turf Solution for K9 Obedience Area
Building 1780 Hill Air Force Base, Utah 84056
1. Project Overview: The objective is to install a comprehensive synthetic turf solution for the K9 obedience area covering 11,181 square feet underneath the current overhang (See images below).
The installed turf should ensure a uniformly level surface without depressions to prevent water accumulation. Additionally, a 12-inch wide concrete border trim will be implemented around the perimeter to secure the turf edges and prevent displacement.
2. Objectives:
2.1 Installation Requirements:
Install synthetic turf covering 11,181 square feet, ensuring a flat and seamless surface.
Coordinate with Hill AFB personnel for installation approval to ensure the area is leveled before installation begins. Site will be leveled by Implement a 12-inch wide concrete border trim around the entire perimeter of the turf area to maintain stability and prevent displacement.
2.2 Obstacle Management:
Remove all existing obstacles from the work area before commencing turf installation.
Temporarily dismantle the east fence if required to facilitate the entry of heavy machinery, ensuring its reinstatement in its original condition upon project completion.
Rearrange obstacles back to designated locations within the obedience yard area post-installation as directed by the project manager.
2.3 Quality Assurance:
Conduct an initial evaluation upon completion to verify the turf is free from depressions, bunching, or installation defects.
Address any identified issues promptly to ensure project quality and client satisfaction.
3. Warranty and Miscellaneous:
Provide warranty coverage for manufacturer and installation defects related to wear items.
Evaluate labor for warranty repairs on a case-by-case basis for part failure issues.
4. Timeline:
Provide a project timeline with proposal to ensure timely completion not to exceed 120 days
ARO.
Define payment terms and milestones in the contract agreement.
Clarify responsibilities between the contractor and Hill AFB personnel for turf installation, obstacle handling, and site restoration.
5. Acceptance Criteria:
Final project acceptance will be contingent upon meeting all installation requirements as outlined in this Statement of Objectives.
Issue a completion certificate upon successful installation and acceptance.