RFIs_Log_Southside_Improvements.pdf

PDF 360 KB Posted

Attached to
Southside Improvements at the National Museum of Natural History
Solicitation number
F17SOL10027
Issued by

View the file

Other files

File Type Posted
F17SOL10027__am_7.pdf PDF
F17SOL10027_am_6_complete.pdf PDF
F17SOL10027_am_5.pdf PDF
F17SOL10027_am_4.pdf PDF
F17SOL10027_am_3.pdf PDF
F17SOL10027_am_2.pdf PDF
Amendment_1.pdf PDF
F17SOL10027_RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Smithsonian Institution

Office of Planning Design & Construction

PROJECT: 1500102 Renovate South Entrance

1500110 Baird AHU Replacement

SOLICITATION: F17SOL100027

LAST UPDATED: 5/22/2017 9:40 AM

SI RFI # Bidder RFI # Date Submt'd Company Project # QA# Request for Information SF Response

S001 5/15/2017 Facility

Support

Services, LLC

1 Since the combined project magnitude for both is $18M-

$24M, can relevant projects under $10M be considered as acceptable “Past Performance” examples?

SI's intent is to award a project in the $18 to $24 million dollar range.

Past performance needs to be in that range to be acceptable. Two

$10 million dollar projects will not be acceptable to demonstrate adequate past performance.

2 Will receipt of the multi-year funding increments cause any anticipated delays in the project?

SI will award funding based on projected cash flow to eliminate any work stoppage. Do not plan for any delays in construction due to multi-year funding.

3 Will projects that are not in the PPIRS system be acceptable? And if so, will offerors receive higher ratings for submitting past projects in the PPIRS system?

Projects not is PPIRS will be acceptable. No special rating or preference shall be applied for projects in PPIRS.

4 Will multiple task orders on the same project conducted simultaneously be considered acceptable as relevant total project cost?

Projects or task orders that were performed concurrently and proved to be physically related to each other shall be considered relevant for review.

5 Will the Baird AHU Replacement and NMBH Renovation projects be done simultaneously

All Base Contract work and Option work shall be performed within the specified project duration.

Smithsonian Institution

Office of Planning Design & Construction

PROJECT: 1500102 Renovate South Entrance

1500110 Baird AHU Replacement

SOLICITATION: F17SOL100027

LAST UPDATED: 5/22/2017 9:40 AM

SI RFI # Bidder RFI # Date Submt'd Company Project # QA# Request for Information SF Response