F17SOL10027_am_2.pdf

PDF 478 KB Posted

Attached to
Southside Improvements at the National Museum of Natural History
Solicitation number
F17SOL10027
Issued by

About this file

Amendment 2

View the file

Other files

File Type Posted
F17SOL10027__am_7.pdf PDF
F17SOL10027_am_6_complete.pdf PDF
F17SOL10027_am_5.pdf PDF
F17SOL10027_am_4.pdf PDF
F17SOL10027_am_3.pdf PDF
RFIs_Log_Southside_Improvements.pdf PDF
Amendment_1.pdf PDF
F17SOL10027_RFP.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

F17SOL10027

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE RECEIVED AT

THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

OCON

OCON

Washington DC 20013-7012

MRC 1200

P.O. BOX 37012

SMITHSONIAN INSTITUTION

1500102_150011005/12/2017000002

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/12/2017

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not, is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Questions and answers as of June 6, 2017 are incorporated in the solicitation.

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

Thomas Dempsey

STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

NSN 7540-01-152-8070

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

Smithsonian Institution

Office of Planning Design & Construction

PROJECT: 1500102 Renovate South Entrance

1500110 Baird AHU Replacement

SOLICITATION: F17SOL100027

LAST UPDATED: 6/7/2017 3:30 PM REV 1

SI RFI # Bidder RFI # Date Submt'd Company Project # QA# Request for Information SF Response

S001 5/15/2017 Facility Support

Services, LLC

1 Since the combined project magnitude for both is $18M-

$24M, can relevant projects under $10M be considered as acceptable “Past Performance” examples?

SI's intent is to award a project in the $18 to $24 million dollar range.

Past performance needs to be in that range to be acceptable. Two

$10 million dollar projects will not be acceptable to demonstrate adequate past performance.

2 Will receipt of the multi-year funding increments cause any anticipated delays in the project?

SI will award funding based on projected cash flow to eliminate any work stoppage. Do not plan for any delays in construction due to multi-year funding.

3 Will projects that are not in the PPIRS system be acceptable? And if so, will offerors receive higher ratings for submitting past projects in the PPIRS system?

Projects not is PPIRS will be acceptable. No special rating or preference shall be applied for projects in PPIRS.

4 Will multiple task orders on the same project conducted simultaneously be considered acceptable as relevant total project cost?

Projects or task orders that were performed concurrently and proved to be physically related to each other shall be considered relevant for review.

5 Will the Baird AHU Replacement and NMBH Renovation projects be done simultaneously

All Base Contract work and Option work shall be performed within the specified project duration.

S002 6/2/2017 Forrester

Construction

1 The RFP states that all proposals will be submitted in pdf format through file sharing environments. Can you please provide detailed information on what those acceptable file sharing environments are and if there are any file size requirements.

Please use the sharing environment available to you. To confirm workability, please feel free to send us a link to a test file to confirm prior to the bid date. In the alternative, we can make a dropbox file available for you.

2 Please confirm that the Five (5) hard copies of the Technical and Cost Proposals can be hand-delivered on the day following the electronic transmission.

Confirmed

3 Please confirm that the Subcontracting Plan should be submitted with the Cost Proposal package.

Confirmed

4 According to SF1442, 13.b, an offer guarantee is not required. However, RFP Section I, page 28, requires a 20% bid guarantee. Please clarify.

No bid bond is required.

5 Please confirm that the Professional Liability Insurance coverage included in Section I, page 32 of the RFP, does not apply to the Contractor but rather the Designers of the project.

Confirmed

Smithsonian Institution

Office of Planning Design & Construction

PROJECT: 1500102 Renovate South Entrance

1500110 Baird AHU Replacement

SOLICITATION: F17SOL100027

LAST UPDATED: 6/7/2017 3:30 PM REV 1

SI RFI # Bidder RFI # Date Submt'd Company Project # QA# Request for Information SF Response

S003 6/5/2017 Forrester

Construction

1 The specifications of both South Entrance and the Baird

Auditorium AHU Replacement call for the structural steel fabricator and the structural steel erector to be AISC-certified companies. As the amount of the new structural steel work is minimal, can the requirement be modified to companies that follow and abide by the AISC guidelines for steel fabrication and erection?

No, the structural steel fabricator and the structural steel erector shall be AISC-certified companies as defined in the specifications.