A01 Amendment to Solicitation SF30.pdf
PDF 318 KB Posted
- Solicitation number
- ExitControlBooth_10PZ1_08_0222
About this file
A01 - Amendmet to Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| A03 Amendment to Solicitation SF30.pdf | ||
| sf25_f.pdf | ||
| Sf25a.pdf | ||
| A02 Amendment to Solicitation SF30.pdf | ||
| Exit Control Booth Solicitation GS-10P-09-XA-C-0003.pdf | ||
| PBS 3490_1.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
2. AMENDMENT/MODIFICATiON NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicble)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICIATION NO.
9B. DATED
(SEE
ITEM
11)
10A. MODIFICATION OF CONTRACT/ORDER NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended, is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a)By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment your desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
NSN 7540-01-152-8070
Previous edition unusable
SECTION 00700
00700. 1 52.228-1 BID GUARANTEE (SEP 1996)
Table of Contents
SECTION 00700
00700. 1 52.228-1 BID GUARANTEE (SEP 1996)
(a) Failure to furnish a bid guarantee in the proper form and amount, by the time set for opening of bids, may be cause for rejection of the bid.
(b) The bidder shall furnish a bid guarantee in the form of a firm commitment, e.g., bid bond supported by good and sufficient surety or sureties acceptable to the Government, postal money order, certified check, cashier''s check, irrevocable letter of credit, or, under Treasury Department regulations, certain bonds or notes of the United States. The Contracting Officer will return bid guarantees, other than bid bonds--
(1) To unsuccessful bidders as soon as practicable after the opening of bids; and
(2) To the successful bidder upon execution of contractual documents and bonds (including any necessary coinsurance or reinsurance agreements), as required by the bid as accepted.
(c) The amount of the bid guarantee shall be 20% percent of the bid price or $total amount of the contract, whichever is less.
(d) If the successful bidder, upon acceptance of its bid by the Government within the period specified for acceptance, fails to execute all contractual documents or furnish executed bond(s) within 10 days after receipt of the forms by the bidder, the Contracting Officer may terminate the contract for default.
(e) In the event the contract is terminated for default, the bidder is liable for any cost of acquiring the work that exceeds the amount of its bid, and the bid guarantee is available to offset the difference.
(End of Provision)
EXIT CONTROL BOOTH – PACIFIC HIGHWAY BORDER STATION, BLAINE WA.
This solicitation is being amended to extend the bid/proposal due date, from January 8.
2009 to January 20, 2009. Bids/Proposals are now due January 20, 2009 at 5:00pm (PST).
On December 17, 2008 a Tele-Conference and Site Visit was held, however due the weather conditions, and difficulties with the bridge line that day, the following and other information is being posted:
COMMENTS:
1) All questions from the site visit and solicitation package should be submitted in writing to Mae Smith, Contracting Officer and Bill Garrott, Project Manager to be answered officially at mae.smith@gsa.gov or william.garrott@gsa.gov
2) Individual Site Visit can be arranged by contacting the GSA, Property Manager, Lance Kualii. Please call and email Lance Kualii at 206.793.9955 and lance.kualii@gsa.gov to make arrangements before showing up on-site.
QUESTIONS:
3) Will CAD Drawings be made available? Yes, CAD drawings will be FedEx out to all contractors who have already provided a signed copy of the Sensitive But Unclassified (SBU) form. A CD with the CAD Drawings will be mailed out not later than December 30, 2008. If you have not provided a signed copy of the SBU form, please email or fax it to mae.smith@gsa.gov or 253.931.7889 in order to receive a copy of the CAD drawings.
4) Will the bid date be extended? Yes, bids/proposals are now due, January 20, 2008 at 5:00pm (PST).
CORRECTION TO SOLICITATION PACKAGE:
5) A correction is being made to the solicitation package. On page 26 of 28 of the
Clauses. Section 00700. 105. Clause 52.228-1, Bid Guarantee (SEP 1996) (c), the clause should read 20% and not 100%.
“(c) The amount of the bid guarantee shall be 20% percent of the bid price or $total amount of the contract, whichever is less.”
mailto:mae.smith@gsa.gov mailto:lance.kualii@gsa.gov mailto:william.garrott@gsa.gov mailto:mae.smith@gsa.gov
| IDCode: |
| EffDate: DEC 23, 2008 |
| ReqNo: 10PZ1-08-0222 |
| ProjNo: |
| IssuedBy: GSA, NORTHWEST ARCTIC REGION |
AUBURN PMO, 10PZ1F
400 15TH STREET SW
AUBURN WA 98001-6599
AdminBy: GSA, NORTHWEST ARCTIC REGION
WESTERN SERVICE CENTER, 10PZ1
JFB, 915 SECOND AVENUE Ste. 390
SEATTLE WA 98174-1001
| NoCopies: 1 |
| Amended: Yes |
| ChgeOrder: |
| Modify: Off |
| SuppAuth: |
| OthrSpec: |
| Require: Off |
| Copies: |
| Descript: EXIT CONTROL BOOTH Œ PACIFIC HIGHWAY BORDER STATION, BLAINE WA. |
This solicitation is being amended to extend the bid/proposal due date, from January 8. 2009 to January 20, 2009. Bids/Proposals are now due January 20, 2009 at 5:00pm (PST).
On December 17, 2008 a Tele-Conference and Site Visit was held, however due the weather conditions, and difficulties with the bridge line that day, the following and other information is being posted:
Please see attachement.
| SignName: |
| SignTitl: |
| ContDate: |
| CODate: |
| OffrExt: Yes |
| OffrNoEx: Off |
| ChgeOrd: Off |
| SuppAgre: Off |
| ModOthr: Off |
| NoReq: Off |
| ContractorCode: |
| FacCode: |
| ContractorPOC: |
| AwdChg: Off |
| SolChg: Yes |
| SolNo: GS-10P-09-XA-C-0003 |
| SolDate: DEC 05, 2008 |
| AwdNo: |
| IssuedByCode: 10PZ1F |
| AdminByCode: 10PZ1 |
| ContrOfficerInfo: |
| DocNo: A01 |
| AwdDate: |
| text1: 10B. DATED (SEE ITEM 13) |
| block 14: 14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.) |
| pageblock: PAGE OF PAGES |
| block13: 13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14. |
| Contractor: |
| ContratorInfo: |
| ModAmount: |
| block12: 12. ACCOUNTING AND APPROPIATION DATA (If required) |
| ApprData: See Schedule |
| Pages: 4 |
| Page: 1 |